Woodstock Road Bus Lane Experimental Traffic Regulation Order (ETRO) and St Giles' Waiting Restrictions ETRO

Approved Committee 6 papers

AI summaryOxfordshire County Council's Transport Management Committee approved making the Woodstock Road bus lane reversal and revised St Giles' waiting restrictions permanent [D]. The approved northbound lane will run 707 metres towards Wolvercote Roundabout, and the St Giles' restriction will apply at all times [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNorthbound lane, southbound removal, St Giles' waiting at all times [D].
MoneyNot stated
What happens nextMake the ETRO measures permanent [D]As part of the current ETRO [D].
Who it affectsNot stated

What was decided

Make a northbound bus lane permanent, starting 61 metres north of Blenheim Drive and running 707 metres towards the Wolvercote Roundabout [D].

Remove the previous southbound bus lane section from the Wolvercote Roundabout to the junction with Field House Drive [D].

Replace the previous No Waiting restriction from 8am to 6.30pm, shown with single yellow lines, with No Waiting at Any Time double yellow lines. The restriction applies on the northwest arm of St Giles, opposite a point 12 metres southeast of the junction with Little Clarendon Street [D].

Why

The project aims to improve bus journey time reliability, provide more active travel facilities and reduce road danger [P8]. Report P8

Modelling indicated that reversing the bus lane should improve bus journey reliability, mitigate potential delays from the trial filters and allow their impact to be understood before more significant changes [P12]. Report P12

The active travel measures should mitigate the loss of amenity for cyclists using the relocated bus lane and provide a safer, more consistent environment for people walking and wheeling [P12]. Report P12

What happens next

Make the approved bus lane and waiting restriction changes permanent under the current ETRO [D].

Use the trial traffic filter results to understand the corridor before introducing more significant changes [P12]. Report P12

Options considered

  • Chosen: Make a northbound bus lane and remove the southbound section. Modelling indicated improved bus journey reliability and mitigation of potential delays from the trial filters [P12]. Report P12
  • Chosen: Replace the St Giles' timed waiting restriction with No Waiting at Any Time double yellow lines
  • Rejected: Allocate more of the current highway to bus and cycle lanes. The wider scheme was reduced in 2021 because delivery would not meet funding timescales. The larger change was considered more likely to be supported if the trial filters reduced general traffic [P12]. Report P12
  • Rejected: Retain the previous 8am to 6.30pm single yellow waiting restriction

Implications

  • Legal: Making the measures permanent will place the bus lane reversal and revised St Giles' waiting restriction within the current ETRO. The report says existing permissions for pedal cyclists, taxis and licenced private hire are retained alongside the northbound lane [D][P10]. Report P10
  • Risk: The lane reversal is intended to improve bus journey time reliability and mitigate potential delays caused by the trial traffic filters [P12]. Report P12
  • Equalities: The assessment says active, sustainable travel can be more affordable than private car ownership and maintenance. It rates reduced poverty and inequality, better health and reduced exposure to poor air quality positively [P16]. Report P16
  • Climate: The assessment rates increased public transport use at 3 and support for climate action at 2. Oxfordshire Council has committed to being carbon neutral by 2030 [P6][P16]. Report P6, P16
  • Climate: The assessment records no tree loss, with localised trimming and planting added to place making and side road narrowing [P13]. Report P13
  • Risk: Existing drainage was reviewed with the proposals, and localised improvements and maintenance were undertaken [P15]. Report P15
  • Financial: The larger scheme's funding would be reallocated across other Housing and Growth Deal funded projects because delivery would not meet the funding timescales [P12]. Report P12
  • Other: Stakeholder engagement, co production and feedback informed the design principles. Traffic modelling results were used to shape the proposals [P11]. Report P11

Who and where

  • Northbound bus passengers Report P8, P10, P12
  • Bus operators Report P12
  • Pedal cyclists using the bus lane Report P10, P12
  • Taxi and licenced private hire users Report P10
  • People walking and wheeling Report P12
  • Drivers affected by the bus lane changes Report P10
  • People waiting near the St Giles' northwest arm
  • People affected by the trial traffic filters Report P12

Timeline

  • 2021: The scope of the larger scheme was reduced because delivery would not meet funding timescales [P12]. Report P12
  • 7/5/2024: The climate impact assessment was first dated on this date [P8]. Report P8
  • May and June: Formal consultation on the statutory elements was completed [P11]. Report P11
  • July 2024: The consultation on the statutory elements was reported for decision [P11]. Report P11
  • between September 2024 and March 2025: Formal consultation on the ETRO elements was undertaken [P11]. Report P11
  • January 2025: The ETRO consultation was due to be reported for decision [P11]. Report P11
  • 23/12/25: The climate impact assessment was updated on this date [P8]. Report P8
  • 2026-01-22: Transport Management approved the measures for permanent inclusion in the current ETRO [D].

Plain English for the jargon

  • ETRO: The current Experimental Traffic Regulation Order in which the approved measures will be made permanent [D].
  • Active travel: Cycling, wheeling and walking, which the report groups as active travel [P10].
  • Trial traffic filters: Trial measures intended to reduce general traffic levels on the corridor [P12].
  • No Waiting at Any Time: A waiting restriction shown with double yellow lines [D].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item121/26

Resolved

RESOLVED to: a) Approve the making permanent of the following measures as part of the current Experimental Traffic Regulation Order (ETRO); i. bus lane for northbound buses, from a point 61 metres north of Blenheim Drive for 707 metres towards the Wolvercote Roundabout, ii. remove section of the previous southbound bus lane from the Wolvercote Roundabout down to the junction with Field House Drive, iii. `No Waiting at Any Time` (double yellow lines) to replace the previous `No Waiting 8am-6.30pm` (single yellow lines) on the northwest arm of St Giles at a point opposite 12 metres southeast of the junction with Little Clarendon Street. Cllr Liz Leffman left the meeting at this stage and Cllr Andrew Gant assumed the Chair for the rest of the meeting.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Transport Management, 4 pages

Climate Impact Assessment Summary

Directorate and Service Environment & Highways Generated Preview 23/12/25 Area v1.36 Just transition Energy What is being assessed Woodstock Road Corridor Improvements (+5) (↓↑ 0)

Is this a new or existing New Transport / Highways Project People & Transport & Organizations Connectivity function or policy? (+4) (+6)

Bus Lane Reversal and Introduction of Active Travel Procurement +23 Buildings Improvements. & Investment (↓↑ 0) (+4)

Summary of assessment Resilience & Nature Adaptation Waste & (+1) (+3) Consumption (↓↑ 0)

Oxfordshire Council has committed to being a carbon neutral Rob Freshwater - Infrastructure Development Lead (Central) organisation by 2030 (8 years and 0 months away). Completed by

Climate action sign off by

Director sign off by Assessment date Original - 7/5/2024, Updated - 23/12/2025 Detail of proposal The project aims to improve bus journey time reliability and improve provision for Active Travel and reduce road danger.

Context / Background

Improved bus, cycling and walking facilities on Woodstock Road as set out below: Phase 1 – Reversing an approx 700m length of 24-hour southbound bus lane between the Wolvercote roundabout (A40) and Squitchey Lane and replace it with a northbound bus lane of similar length retaining existing permissions (i.e. for pedal cyclists, taxis and licenced private hire) alongside delivery of minor complementary measures. It is hoped the measure will improve bus journey time reliability and support the planned trial traffic filters. Proposal Phase 2 – A package of active travel (cycling, wheeling, walking) priority measures focussed on the southern end of the Woodstock Road including side road entry treatments and place making at Little Clarendon Junction, and Observatory Street.

Bus journey time (city swift) and vehicle journey time (inrix) data has been collected before and during the ETRO trial period. Traffic modelling has been completed and results used to inform the proposals. Prior to trial delivery, stakeholder engagement and co-production was undertaken and feedback received was used to inform the design principles. FoFormal consultation on the statutory elements including side road entry treatments, the new zebra crossing and changes to parking was completed during May and June and was reported to CMD in July 2024. Formal consultation on ETRO elements was undertaken between September Evidence / Intelligence 2024 and March 2025 and will be reported to CMD for decision in January 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CMDTM22012026: Woodstock Road ETRO (Climate Impact Assessment).docx /26Report 4 pages DownloadRead as text
PDF
CMDTM22012026: Woodstock Road ETRO (Consultation Responses) /26Report 113 pages Withheld: personal details
PDF
CMDTM22012026: Woodstock Road ETRO (Data Monitoring) /26Report 6 pages Download
PDF
CMDTM22012026: Woodstock Road ETRO (Equalities Impact Assessment) /26Report 14 pages Download
PDF
CMDTM22012026: Woodstock Road ETRO (Scheme Layout) /26Report 3 pages Download
PDF
Woodstock Road Bus Lane Experimental Traffic Regulation Order (ETRO) and St Giles' Waiting Restrictions ETROReport 11 pages Download

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Woodstock Road Bus Lane Experimental Traffic Regulation Order (ETRO) and St Giles' Waiting Restrictions ETROThis decision
  2. Oxford - A44 (Woodstock Road) - Proposed Formalisation of Bus LanesApproved
  3. Oxford - A44 (Woodstock Road) - Proposed Formalisation of Bus LanesDeferred
  4. A4144 Woodstock Road, Oxford - Proposed conversion of a Zebra Crossing to Parallel CrossingApproved
  5. A44 Manor Road, Woodstock - Proposed 30mph Speed Limit ExtensionApproved
  6. Woodstock Road Sustainable TravelApproved

More from Oxfordshire Transport Management

All decisions
MeetingDecisionOutcome
23 Apr 2026 Copenhagen Drive, Abingdon - Proposed Toucan Crossing and Shared Use PathRESOLVED to: Approve the following measures on Copenhagen Drive in Abingdon, as advertised: a) New Toucan Crossing, t... Approved Open
23 Apr 2026 Proposed Bus Stops - Ladygrove, DidcotRESOLVED to: a) Approve the introduction of two new bus stop clearways (with ‘No stopping except local buses’ restric... Approved Open
23 Apr 2026 Wallingford Area LCWIPRESOLVED to: a) Approve Wallingford Area Local Cycling and Walking Infrastructure Plan (LCWIP). Approved Open
23 Apr 2026 A4130, Steventon Lights - Proposed Traffic Management MeasuresContact: Mohamed Gulamhussein, Project Manager – Infrastructure Delivery ( [email protected] ) ... Approved Open
23 Apr 2026 Proposed Puffin Crossing - A329 Reading Road, CholseyRESOLVED to: a) Approve the introduction of a new Puffin crossing on the A329 Reading Road in Cholsey, as advertised. Approved Open