Blackthorn Road, Ambrosden - Traffic Calming and Speed Limits

Approved Committee 1 paper

AI summaryOxfordshire County Council approved extending the 40mph limit by 90 metres on Blackthorn Road, plus raised tables and side road entry treatments. A 30mph limit will be reviewed, and the developer will fund the work. [D][P30]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved40mph extension, raised tables and SRETs were approved. [D]
MoneyDeveloper funded [P11][P30]Consultation was funded, with implementation also funded by the developer. [P11][P30]
What happens next30mph limit review [D]The 40mph extension is subject to reviewing a 30mph limit. [D]
Who it affectsBlackthorn Road users [D]The limit and traffic calming at adjoining junctions will change. [D]

What was decided

The council approved extending the existing 40mph speed limit by 90 metres on Blackthorn Road, as advertised. The approval is subject to reviewing a potential 30mph speed limit on that stretch.

The council approved new raised table traffic calming features, as advertised, on Blackthorn Road at its junctions with Ploughley Road and Quintan Avenue.

The council approved new raised Side Road Entry Treatments, as advertised, on Blackthorn Road at its junctions with Quintan Avenue and Allectus Avenue.

Why

The proposals arose from adjacent residential development and the S.106 obligation to create a shared footway and cycleway route. Report P6

The 40mph extension is for safety and visibility around the new residential development access. The 50mph limit will start after that access junction. Report P31

Officers noted objections but said the proposals would be implemented and funded by the developer as part of the S.106 obligations. Report P30

What happens next

Review a potential 30mph speed limit on the 90 metres stretch covered by the approved 40mph extension.

Implement the approved 40mph extension, relocate the 50mph limit beyond the development access junction, and install the raised tables and SRETs. Report P31

The developer must provide the continuous active travel route along Blackthorn Road required by the S.106 obligations. Report P30

Options considered

  • Chosen: Extend the existing 40mph speed limit by 90 metres on Blackthorn Road. The extension is for safety and visibility around the new residential development access. [P31] Report P31
  • Chosen: Review a potential 30mph speed limit on the extended stretch. Consultation feedback called for a 30mph limit in the area. [P50][P52] Report P50, P52
  • Chosen: Install raised tables at the Ploughley Road and Quintan Avenue junctions. The measures complement new foot and cycle provision and reduce danger for vulnerable road users. [P20] Report P20
  • Chosen: Install raised SRETs at the Quintan Avenue and Allectus Avenue junctions. The measures complement new foot and cycle provision and reduce danger for vulnerable road users. [P20] Report P20

Implications

  • Financial: The developer funds consultation and implementation, and no potentially significant financial impacts were identified. [P11][P21][P30] Report P11, P21, P30
  • Legal: The consultation met requirements under the Highways Act 1980, the Road Traffic Regulation Act 1984 and other relevant legislation. Oxfordshire County Council promoted the scheme as Highway Authority and Traffic Authority. [P12][P13] Report P12, P13
  • Equalities: No negative equality or inclusion implications were identified. [P18] Report P18
  • Climate: The proposals support the Greener Oxfordshire priority through safer and sustainable movement, including cycling and walking. [P8][P20] Report P8, P20
  • Risk: No significant health and safety or service provision risks were identified. The 40mph extension is intended to improve safety and visibility around the development access. [P21][P31] Report P21, P31
  • Staffing: There are no negative staff implications, and no effect on team capacity is expected. [P16] Report P16
  • Other: The traffic calming is intended to reduce danger for vulnerable road users and allow safe traffic passage. [P20] Report P20
  • Other: The developer must provide a continuous active travel route along Blackthorn Road. [P30] Report P30

Who and where

  • Drivers using Blackthorn Road Report P31
  • Drivers entering or leaving adjoining side roads
  • Pedestrians and cyclists using nearby or planned routes Report P6, P20, P30
  • People living in the immediate vicinity Report P24
  • Children and parents walking near the school Report P42, P58
  • Mulberry Homes, as developer Report P30

Timeline

  • 16 October and 14 November 2025: Formal consultation was carried out. Report P23
  • 22 January 2026: The council approved the speed limit and traffic calming changes.

Plain English for the jargon

  • Side Road Entry Treatment (SRET): A raised traffic calming feature on Blackthorn Road at a side road junction. [P4][P5]
  • Raised table: A raised traffic calming feature on Blackthorn Road near junctions. [P3][P5]
  • S.106 obligation: A developer requirement linked to the development, including a continuous active travel route. [P6][P30]
  • Active travel route: A route for walking and cycling along Blackthorn Road. [P6][P30]
  • Bell mouth access junction: The access junction serving the new residential development. [P31]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item130/26

Resolved

RESOLVED to: a) Approve the extension of the existing 40mph speed limit by 90 metres on Blackthorn Road, as advertised, subject to reviewing a potential 30mph speed limit on that stretch of road : b) Approve the introduction of new raised table traffic calming features on Blackthorn Road at its junctions with Ploughley Road & Quintan Avenue, as advertised. c) Approve the introduction of new raised Side Road Entry Treatments (SRETs) on Blackthorn Road at its junctions with & Quintan Avenue & Allectus Avenue, as advertised.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Transport Management, 9 pages

Recommendation

The Cabinet Member is RECOMMENDED to:

(a) Approve the extension of the existing 40mph speed limit by 90 metres on Blackthorn Road, as advertised:

(b) Approve the introduction of new raised table traffic calming features on Blackthorn Road at its junctions with Ploughley Road & Quintan Avenue, as advertised.

(c) Approve the introduction of new raised Side Road Entry Treatments (SRETs) on Blackthorn Road at its junctions with & Quintan Avenue & Allectus Avenue, as advertised.

Executive summary

2. This report presents responses received to a statutory consultation on proposals to extend the existing 40mph speed limit on Blackthorn Road (running north-eastwards to the B4011), and introduce new traffic calming features – in the form of raised tables on the ‘Blackthorn road’ either side of the junctions with Ploughley Road & Quintan Avenue, and Side Road Entry Treatments (SRETs) at the ‘Blackthorn road’ junctions with Quintan Avenue, Allectus Avenue – as shown in Annex 1.

3. The proposals have been put forward as a result of adjacent residential development, and the associated S.106 obligations for the creation of a new shared footway and cycleway route.

Corporate Policies and Priorities

4. Of the three priorities identified within the newly adopted ‘Oxfordshire Strategic Plan 2025-2028’ which are listed below, these proposals actively support priority nos.1 & 3: (1) Greener Oxfordshire – “We want our communities to enjoy clean air, access to green space, and safe and sustainable ways to move around. This means reducing traffic congestion and investing in public transport, cycling and walking; protecting our natural environment; and helping Oxfordshire respond and adapt to a changing climate.”

(2) Fairer Oxfordshire – “We want all our residents to benefit from the advantages our county has to offer. This means supporting a local economy that benefits everyone; assisting people who face challenges in finding work; making our services as easy to access as possible; and helping communities in need.”

(3) Healthier Oxfordshire – “We want all our residents to be happy, healthy and safe. This means helping children get the best start in life; creating opportunities for young people to reach their full potential; supporting older people to age well and stay independent for as long as possible; and encouraging everyone to make healthy choices.”

Financial implications

5. Funding for consultation on the proposals has been provided directly by the developer, with the relevant agreements in place to also fund implementation if approved.

6. The consultation that has been undertaken complies with the consultation requirements for the various elements as required by law including under the Highways Act 1980, the Road Traffic Regulation Act 1984 and any other relevant legislation.

7. The scheme has been promoted by Oxfordshire County Council as the Highway Authority and Traffic Authority under the Highways Act 1980, and the Road Traffic Regulation Act 1984.

Comments checked by: Jennifer Crouch – Principal Solicitor (Regulatory) [email protected]

Staff Implications

8. There are no negative staff implications, with the appraisal of the proposals, as well as the consultation process having been undertaken by Officers from the ‘Highway Agreements’ and ‘TRO & Schemes’ teams as part of their regular day- to-day duties, with no additional/negative impact on capacity expected.

Equality & Inclusion Implications

8. No negative implications in respect of equalities or inclusion have been identified in respect of the proposals.

Sustainability Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackthorn Road, Ambrosden: Traffic Calming and Speed LimitsReport 9 pages DownloadRead as text

More from Oxfordshire Transport Management

All decisions
MeetingDecisionOutcome
23 Apr 2026 Copenhagen Drive, Abingdon - Proposed Toucan Crossing and Shared Use PathRESOLVED to: Approve the following measures on Copenhagen Drive in Abingdon, as advertised: a) New Toucan Crossing, t... Approved Open
23 Apr 2026 Proposed Bus Stops - Ladygrove, DidcotRESOLVED to: a) Approve the introduction of two new bus stop clearways (with ‘No stopping except local buses’ restric... Approved Open
23 Apr 2026 Wallingford Area LCWIPRESOLVED to: a) Approve Wallingford Area Local Cycling and Walking Infrastructure Plan (LCWIP). Approved Open
23 Apr 2026 A4130, Steventon Lights - Proposed Traffic Management MeasuresContact: Mohamed Gulamhussein, Project Manager – Infrastructure Delivery ( [email protected] ) ... Approved Open
23 Apr 2026 Proposed Puffin Crossing - A329 Reading Road, CholseyRESOLVED to: a) Approve the introduction of a new Puffin crossing on the A329 Reading Road in Cholsey, as advertised. Approved Open