Approve and Authorise the Award of the HIF1 Clifton Hampden Bypass Construction Contract
AgreedKey decisionCommittee1 paper
AI summaryOxfordshire County Council delegated the Director of Environment and Highways to award the Clifton Hampden Bypass contract to John Graham Construction Limited, conditional on agreeing the target cost within the released budget, works programme and final contract terms. The contractor's estimated cost is circa £38m. [D] [P13]
Written from the decision and the officer reportPDF Pro
OutcomeAgreedJohn Graham's award needs three contract conditions agreed. [D]
Moneycirca £38m [P13]Contractor estimate; target cost remains to be agreed. [P13]
What happens nextDirector to award after conditions [D]Target cost, programme and final terms must first be agreed. [D]
Who it affectsDidcot, Culham and Science Vale [P5]Supports a 12,655 home target and employment growth. [P5] [P16]
What was decided
Authority was delegated to the Director of Environment and Highways to award the Stage Two contract to John Graham Construction Limited under Crown Commercial Service framework RM6088, Lot 4.1, for England and Wales. Report P2
The award is conditional on agreement of a target cost within the released budget, the works programme and the final contract terms. Report P3, P21, P22
The Stage Two contract is an NEC4 Engineering and Construction Contract using Option C, funded primarily by the Housing Infrastructure Fund grant. Report P7
Why
The contract approval is needed to maintain programme momentum and ensure the Homes England grant is spent within the agreed March 2028 timeframe. Report P14
Delay could cause failure to deliver key milestones, loss of funder confidence and possible withdrawal of grant funding. Report P15
The released Full Business Case budget covers the proposed construction contract and includes contingency and inflation allowances. Report P21, P22
What happens next
The Director must agree the target cost within the released budget, the construction programme and final contract terms before awarding the Stage Two contract. Report P3, P20
The main contractor is due to enter the contract and land acquisition is planned for February 2026. Report P31
Main construction and infrastructure start on site are planned for April 2026. The main works run to December 2027, within the Homes England funding period ending March 2028. Report P31
The money
circa £38m Contractor estimate for completing construction; target cost still to be agreed. Report P13
£332.538 million Total programme funding secured by the revised Grant Determination Agreement. Report P12
£79.6 million Homes England funder contingency. Report P12
£4.2 million Current total risk allowance, equal to 11.4% of total Stage 3 costs. Report P32
Options considered
Chosen: Crown Commercial Services framework mini competition. The procurement strategy recommended this method for detailed design and construction. Report P18, P19
Chosen: Professional Services Contract Option A for detailed design. Stage One detailed design and early contractor involvement was awarded under this contract. Report P19, P20
Chosen: Engineering and Construction Contract Option C for construction. This is the form of the Stage Two main construction contract. Report P19, P20
Chosen: Short contract for site investigation and enabling works. A Stage One site investigation and enabling works contract was awarded. Report P19, P20, P25
Rejected: Delay contract award. It could miss key milestones, reduce funder confidence and lead to grant funding withdrawal. Report P15
Implications
Financial: The Stage Two contract is funded primarily by the Housing Infrastructure Fund grant, supplemented by approved Council capital allocations, Local Enterprise Partnership and S106 contributions. Report P7
Legal: The Council is acting as the highway authority for Oxfordshire under the Highways Act 1980. Report P24
Legal: The mini competition complied with the Public Contracts Regulations 2015 and the Council's Contract Procedure Rules. Report P25
Equalities: There are no equalities implications from the previously completed Climate Impact Assessment and Equalities Impact Assessment as a result of this decision. Report P28, P35
Climate: The scheme promotes walking and cycling, reduces congestion in Didcot, and includes biodiversity enhancements and carbon reduction measures. Report P28
Risk: Main NEC4 contract insurances have been confirmed as acceptable to the contractor. Delay could miss milestones, reduce funder confidence and risk withdrawal of grant funding. The current risk allowance is £4.2 million. Report P15, P26, P32
Staffing: No additional staff resources are required, and the scheme remains with the existing HIF1 Project Team. Report P27
Other: The contractor must provide social value, including local employment opportunities, lower construction carbon impact and support for local communities. Report P29
South Oxfordshire and Vale of White Horse Report P16
The Council's HIF1 Project Team Report P27
Timeline
December 2024: Planning permission for the bypass and associated infrastructure was granted by the Secretary of State. Report P11, P31
30 June 2025: The CPO was confirmed by the Department for Transport and published on 31 July 2025. Report P11
September 2025 to March 2026: Enabling works are scheduled. Report P31
October 2025: Public information events were held in six locations. Report P33
2018 and 2020: Extensive public consultation was undertaken. Report P32
February 2026: The main contractor is due to enter the contract and land acquisition is scheduled. Report P31
April 2026 to December 2027: Main construction is scheduled, with infrastructure start on site in April 2026. Report P31
March 2028: The Homes England funding period ends. Report P31
Plain English for the jargon
HIF1: Didcot Garden Town Housing Infrastructure Fund programme. [P4]
NEC4: Engineering and Construction Contract used for Stage Two works under Option C. [P7]
FBC: Full Business Case for the bypass, approved. [P6]
CPO: Compulsory Purchase Order for the scheme. [P11]
CCS: Crown Commercial Service, which ran the framework mini competition. [P20] [P25]
GDA: Grant Determination Agreement with Homes England. [P12]
PSC: Professional Services Contract used for detailed design in Stage One. [P19]
S106: A source of contributions listed in the Stage Two funding mix. [P7]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23/26
Resolved
RESOLVED to: a) Delegate authority to the Director of Environment and Highways to award the Stage Two NEC4 Engineering and Construction Contract for the HIF1 Clifton Hampden Bypass scheme to John Graham Construction Limited under the Crown Commercial Service Construction Works and Associated Services Framework RM6088, Lot 4.1 (England and Wales) subject to: (i) agreement of the target cost (within the released budget), (ii) agreement of the programme for the works and (iii) finalising the contract terms.
Word for word from the decision Oxfordshire published for this meeting.Source: mycouncil.oxfordshire.gov.uk
Report to Place, Environment and Climate Action, 5 pages
Recommendation
The Cabinet Member is RECOMMENDED to:
a) Delegate authority to the Director of Environment and Highways to award the Stage Two NEC4 Engineering and Construction Contract for the HIF1 Clifton Hampden Bypass scheme to John Graham Construction Limited under the Crown Commercial Service Construction Works and Associated Services Framework RM6088, Lot 4.1 (England and Wales) subject to:
(i) agreement of the target cost (within the released budget), (ii) agreement of the programme for the works and (iii) finalising the contract terms.
Executive Summary 1. This report seeks a delegation to the Director of Environment & Highways to award and enter into the Stage 2 main construction contract for the Clifton Hampden Bypass scheme, one of three major infrastructure projects within the Didcot Garden Town Housing Infrastructure Fund (HIF1) programme.
2. The Clifton Hampden Bypass forms a critical component of the wider HIF1 package designed to improve connectivity between Didcot and Culham, relieve congestion, and support the delivery of over 12,655 new homes and significant employment growth across the Science Vale.
3. The Full Business Case (FBC) for the Clifton Hampden Bypass scheme has been approved.
4. The Stage Two construction contract is an NEC4 Engineering and Construction Contract (ECC) Option C, and will be funded primarily through the Housing Infrastructure Fund (HIF) grant, supplemented by approved Council capital allocations, Local Enterprise Partnerships (LEP) and S106 contributions.
Background 5. The Clifton Hampden Bypass is a single carriageway bypass for Clifton Hampden, between Culham Science Centre and B4015 just north of Clifton Hampden Village (1.8km including link roads). It includes a new relief road northwest of the village between the A415 at Culham Science Centre and the B4015 Oxford Road north of Clifton Hampden, a new roundabout at the western end near Culham Science Centre and Culham Rail Station, and other access junctions along the Bypass. Walking and cycling facilities segregated from the carriageway are also proposed.
6. The scheme forms part of the wider HIF1 Access to Didcot Garden Town Programme, which also includes:
Didcot to Culham River Crossing Didcot Science Bridge
7. Planning permission for Clifton Hampden Bypass and associated infrastructure was granted by the Secretary of State in December 2024 following a conjoined Planning and Compulsory Purchase Order (CPO) Inquiry. The CPO was confirmed by the Department for Transport on 30 June 2025, with publication on 31 July 2025.
8. The project is fully funded under the revised Grant Determination Agreement (GDA) with Homes England, approved by Cabinet in July 2024, which secures total programme funding of £332.538 million and a £79.6 million Homes England funder contingency.
9. The contractor’s estimated cost to complete construction is circa £38m, with the target cost still to be agreed.
Key Issues 10. The approval of this construction contract is essential to maintain programme momentum and ensure expenditure of the Homes England grant within the agreed timeframe of March 2028.
11. Delay in contract award would risk non-delivery of key milestones, loss of confidence from funders, and potential withdrawal of grant funding.
12. The scheme directly supports the housing delivery target of 12,655 set out in the South Oxfordshire and Vale of White Horse Local Plans and is a fundamental enabler of the Didcot Garden Town Delivery Plan and Science Vale Transport Strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place, Environment and Climate Action at Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
Rights of Way Improvement Plan ExtensionRESOLVED to: a) Agree to retain the current Rights of Way Improvement Plan (2015-2025), at Annex 4, extending it unti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.