Oxfordshire County Council
Place, Environment and Climate Action, Friday 1 May 2026 at 10.00am

Approve and Authorise the Award of the HIF1 Culham River Crossing Construction Contract

Agreed Key decision Committee 1 paper

AI summaryOxfordshire cabinet member delegates authority to award the HIF1 Didcot to Culham River Crossing construction contract to John Graham Construction Limited, subject to agreement on cost, programme, terms and funding. The director is also authorised to enter land and access agreements.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeAgreedSubject to four conditions being met first
MoneyNot stated
What happens nextDirector to finalise award conditionsTarget cost, programme, terms, funding
Who it affectsDidcot to Culham river crossing schemeIncludes land deals in Sutton Courtenay

What was decided

Authority is delegated to the Director of Environment and Highways to award a Stage Two NEC4 Engineering and Construction Contract to John Graham Construction Limited for the HIF1 Didcot to Culham River Crossing scheme, under Crown Commercial Service framework RM6088 Lot 5, subject to agreement of the target cost, agreement of the programme, finalising the contract terms, and confirmation that sufficient funding is allocated.

Authority is delegated to the Director of Environment and Highways to enter into a Works and Access Agreement with FCC Environment UK Limited for land at Sutton Courtenay, and a two Party Overbridge Agreement and a Restoration Agreement with Hanson Quarry Products Europe Limited.

Why

The decision seeks approval and authorisation for the award of the HIF1 Culham River Crossing construction contract.

What happens next

The Director of Environment and Highways will agree the target cost with the contractor before award.

The Director will agree the programme for the works, finalise the contract terms and confirm that sufficient funding is allocated before the contract is awarded.

The Director will progress the Works and Access Agreement with FCC Environment UK Limited and the overbridge and restoration agreements with Hanson Quarry Products Europe Limited.

Implications

  • Legal: The council will enter into binding land and access agreements with FCC Environment UK Limited and Hanson Quarry Products Europe Limited.
  • Financial: The award is conditional on confirmation that sufficient funding is allocated to the scheme.
  • Other: The item is recorded as a Key Decision on the Forward Plan (reference 2025/268).

Who and where

  • John Graham Construction Limited, the intended contractor
  • FCC Environment UK Limited, as a party to a Works and Access Agreement for land at Sutton Courtenay
  • Hanson Quarry Products Europe Limited, as a party to an overbridge agreement and a restoration agreement

Timeline

  • 2026-05-01: Place, Environment and Climate Action committee considered agenda item 38/26
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38/26

Resolved

RESOLVED to: a) Delegate authority to the Director of Environment and Highways to award the Stage Two NEC4 Engineering and Construction Contract for the HIF1 Didcot to Culham River Crossing scheme to John Graham Construction Limited under the Crown Commercial Service Construction Works and Associated Services Framework RM6088, Lot 5 (National Lot across all UK regions) subject to: ( i ) agreement of the target cost, (ii) agreement of the programme for the works, (iii) finalising the contract terms and (iv) confirmation that sufficient funding is allocated. b) Delegate authority to the Director of Environment and Highways to enter into a Works and Access Agreement relating to land at Sutton Courtenay with FCC Environment UK Limited (FCC) and a two Party Overbridge Agreement and a Restoration Agreement with Hanson Quarry Products Europe Limited.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Place, Environment and Climate Action
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Approve and Authorise the Award of the HIF1 Culham River Crossing Construction ContractReport 144 KB Copy on its way

At this meeting

Whole meeting
38/26Approve and Authorise the Award of the HIF1 Culham River Crossing Construction ContractThis decision

On this subject at Oxfordshire

Search all
  1. Approve and Authorise the Award of the HIF1 Culham River Crossing Construction ContractThis decision
  2. Approve and Authorise the Award of the HIF1 Clifton Hampden Bypass Construction ContractAgreed

More from Oxfordshire Place, Environment and Climate Action

All decisions
MeetingDecisionOutcome
23 Apr 2026 Approval to Sign Space Clipper Sub-ContractRESOLVED to: a) Agree that the Council enters into a sub-contract agreement with Space Clipper for the purpose of sup... Agreed Open
26 Mar 2026 Rights of Way Improvement Plan ExtensionRESOLVED to: a) Agree to retain the current Rights of Way Improvement Plan (2015-2025), at Annex 4, extending it unti... Agreed Open
26 Feb 2026 Biodiversity Action At Oxfordshire County Council (Jan 2023-Dec 2025)RESOLVED to: a) Approve the ‘Biodiversity Action at Oxfordshire County Council Jan 2023-Dec 2025’ report for publicat... Approved Open
26 Feb 2026 Approve and Authorise the Award of the HIF1 Clifton Hampden Bypass Construction ContractRESOLVED to: a) Delegate authority to the Director of Environment and Highways to award the Stage Two NEC4 Engineerin... Agreed Open
22 Jan 2026 North West Bicester Strategic Link Road Award of Detailed Design ContractRESOLVED to: a) Authorise the procurement of a contract for the detailed design of the North West Bicester Strategic ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies