What was decided
Cabinet approved the start of a procurement exercise to appoint a Strategic Partner to support the delivery of Local Government Reorganisation across the Oxfordshire and West Berkshire councils in scope, covering both the statutory transition to new unitary arrangements and wider transformation objectives.
Cabinet approved procurement on the basis of an estimated contract value in the region of £3.0 million, with the contract expected to start in September 2026 and run until March 2029 or 12 months following vesting day, whichever is later.
Cabinet delegated authority to the Chief Executive, in his capacity as LGR Oxfordshire and West Berkshire System Implementation Team Leader, to award and enter into the contract after the procurement process, provided the final arrangement stays within the agreed value and duration. Any arrangement outside those parameters will come back to Cabinet for approval.
Why
The Strategic Partner is intended to enable a safe and legally compliant transition to new unitary arrangements and to support a transformation-led approach that redesigns services, operating models and system working.
The partner is to operate at system level, working across councils and partners to translate ambition into deliverable plans, develop future operating models, and support implementation before and after vesting.
Cabinet approval was required because the decision is a key decision, committing the Council to a significant procurement and enabling delegated authority to progress and award the contract.
What happens next
The procurement exercise will commence, with proposed costs tested and refined through the process and final costs confirmed before contract award.
Costs will be shared in line with the cost-sharing agreement between the councils in scope, with the agenda noting an 80/20 split: 80% funded by Oxfordshire County Council and 20% collectively by the partner councils.
Following completion of procurement and required approvals, the Chief Executive will take the necessary steps to award and enter into the contract within the agreed parameters.
The money
- £3.0 million Estimated contract value for the Strategic Partner procurement
Implications
- Financial: Estimated contract value in the region of £3.0 million, with 80% funded by Oxfordshire County Council and 20% collectively by partner councils under the Memorandum of Understanding.
- Legal: Procurement is intended to support a legally compliant transition to new unitary arrangements under Local Government Reorganisation.
- Governance: Authority to award the contract is delegated to the Chief Executive, acting as LGR Oxfordshire and West Berkshire System Implementation Team Leader, subject to the agreed value and duration.
- Risk: Final costs will only be confirmed prior to contract award; any arrangement outside the agreed value or duration parameters must return to Cabinet for approval.
Who and where
- Oxfordshire County Council
- West Berkshire council and other partner councils in scope of LGR
Timeline
- September 2026: Contract expected to commence
- March 2029: Contract end date, or 12 months following vesting day, whichever is later
Plain English for the jargon
- LGR: Local Government Reorganisation
- Strategic Partner: An external supplier to be appointed through procurement to support delivery of LGR and wider transformation across the councils in scope
- Vesting day: The day on which the new unitary arrangements take effect
- Memorandum of Understanding: The 80/20 cost-sharing agreement between councils in scope of LGR for relevant work, with 80% funded by Oxfordshire County Council and 20% collectively by partner councils