Cabinet, Tuesday 14 July 2026 at 2.00pm

Capital Programme Monitoring Report

Noted Key decision Executive 2 papers

AI summaryCabinet approved the updated 2026/27 Capital Programme, releasing £4.0m for drainage and £1.4m for Didcot Valley Park SEND school, while accepting £11.299m in SEN grant funding. The programme remains £10.365m over-programmed.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedMonitoring noted, budget releases and grants agreed
MoneyFive sums noted or approvedDrainage, SEND school, schools, SEN, over-programming
What happens next2027/28 budget processReview of corporate resources and DfT funding
Who it affectsSchools and drainage assetsDidcot SEND project, SEN reserves, drainage schemes

What was decided

Cabinet approved the updated Capital Programme at Annex 2, incorporating the changes set out in the report.

Cabinet noted the proposed release of £4.0m from corporate resources for drainage infrastructure improvements, agreed by Council in February 2026, and the inclusion of Didcot Valley Park SEND school into the capital programme with a development budget of £1.4m.

Cabinet agreed grant funding updates: a revised School Condition Allocation 2026/27 of £4.645m, and inclusion of the SEN High Needs Capital Allocation 2026/27 of £11.299m to earmarked reserves for SEN reform requirements.

Why

The item is a financial report on capital spending against budget allocations, including any necessary capital programme approvals for 2026/27.

What happens next

The impact of the review of corporate resources and the additional DfT Transport consolidated funding settlement will be considered as part of the budget process for 2027/28.

The money

  • £4.0m Release from corporate resources for drainage infrastructure improvements
  • £1.4m Development budget for inclusion of Didcot Valley Park SEND school
  • £4.645m Revised School Condition Allocation 2026/27
  • £11.299m SEN High Needs Capital Allocation 2026/27 to earmarked reserves
  • £10.365m Current over-programming of the capital programme

Implications

  • Financial: Capital programme is over-programmed by £10.365m as agreed by Council in February 2026, pending the 2027/28 budget process.
  • Financial: Corporate resources and DfT Transport consolidated funding will be revisited in 2027/28 to address over-programming.

Who and where

  • Didcot Valley Park SEND school project
  • Drainage infrastructure schemes
  • School condition maintenance programme
  • Special Educational Needs provision and earmarked reserves

Timeline

  • February 2026: Council agreed the £4.0m drainage release and the £10.365m over-programming position
  • 2026/27: Capital programme monitoring year, with revised School Condition Allocation of £4.645m and new SEN High Needs Capital Allocation of £11.299m
  • 2027/28: Budget process to consider review of corporate resources and the DfT Transport consolidated funding settlement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item108/26

Resolved

RESOLVED to: Capital Programme a. Note the capital monitoring position for 2026/27 set out in this report and summarised in Annex 1. b. Approve the updated Capital Programme at Annex 2 incorporating the changes set out in this report. Budget Changes / Budget Release c. Note the proposed release of £4.0m from corporate resources agreed by Council in February 2026 for drainage infrastructure improvements (para 69). d. Note the proposed inclusion of Didcot Valley Park SEND school into the capital programme with a development budget of £1.4m (para 70-71). Funding Updates e. Agree the inclusion in the capital programme of the following grant funding updates and allocations: · Revise of the previous forecasted value of the School Condition Allocation 2026/27 to £4.645m (para 73). · Include the SEN High Needs Capital Allocation 2026/27 of £11.299m to earmarked reserves to address SEN reform requirements (para 74-77). f. Note the current over-programming of the capital programme is £10.365m as agreed by Council in February 2026. The impact on the review of corporate resources and the additional funding available through the DfT Transport consolidated funding settlement will be considered as part of the budget process for 2027/28.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
& 2: Capital Programme Summary (Cabinet July 26) draft /26Appendix 1 132 KB Copy on its way
PDF
Capital Programme Monitoring ReportReport 297 KB Copy on its way

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Capital Programme Monitoring ReportThis decision
  2. Capital Programme Update and Monitoring ReportNoted
  3. Capital Programme Approvals - January 2026Approved
  4. Capital Programme Update and Monitoring ReportNoted
  5. Capital Programme Approvals - November 2025Approved
  6. Capital Programme Update and Monitoring ReportNoted

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies