Budget Monitoring Report Final Outturn 2014/15

Noted Executive 1 paper

Cabinet noted this item on Monday 15 June 2015. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED to note: 1. The final outturn position for 2014/15 (subject to finalisation of the statutory statement of accounts) of a balanced position on the Council’s revenue budget; 2. The final outturn spending of £108.8m under the Council’s capital programme 2014/15; 3. The reserves position for the Council, including the use of £0.6m from reserves to support the budget in 2014/15, which was less than forecast as actions have reduced pressures; 4. The performance against the prudential indicators; 5. The performance on treasury management activities, payment of creditors, collection performance for debtors, local taxation and benefit overpayments; and 6. The forecast budget gap of over £10m for 2016/17 was expected to increase with the update of national expenditure plans, and that Cabinet may need to review 2015/16 plans in light of the Budget to be released on 8 July 2015 . REASONS FOR THE DECISION The report formed part of the closure of accounts and decision making framework culminating in the production of the Statement of Accounts and informs Cabinet of the final position. ALTERNATIVE OPTIONS CONSIDERED There were no alternative options considered or required.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

CABINET AGENDA ITEM No. 6

15 JUNE 2015 PUBLIC REPORT

Cabinet Member(s) responsible: Cllr David Seaton, Cabinet Member for Resources Contact Officer(s): John Harrison, Corporate Director Resources Tel. 452520 Steven Pilsworth, Service Director, Financial Services Tel. 384564

BUDGET MONITORING REPORT FINAL OUTTURN 2014/15

RECOMMENDATIONS FROM : Corporate Director Resources Deadline date : N/A

That Cabinet:

1. Note the final outturn position for 2014/15 (subject to finalisation of the statutory statement of accounts) of a balanced position on the council’s revenue budget.

2. Note the final outturn spending of £108.8m under the Council’s capital programme 2014/15.

3. Note the reserves position for the Council, including the use of £0.6m from reserves to support the budget in 2014/15, which is less than forecast as actions have reduced pressures

4. Note the performance against the prudential indicators;

5. Note the performance on treasury management activities, payment of creditors, collection performance for debtors, local taxation and benefit overpayments, and

6. Note the forecast budget gap of over £10m for 2016/17 is expected to increase with the update of national expenditure plans, and that Cabinet may need to review 2015/16 plans in light of the Budget to be released on 8th July .

1 ORIGIN OF THE REPORT

1.1This report is submitted to Cabinet as a monitoring item. The report will also be submitted to Audit committee on 29 June as part of the closure of accounts process.

2 PURPOSE AND REASON FOR REPORT

2.1The report provides Cabinet with the outturn financial position for both the revenue budget and capital programme for 2014/15, subject to any changes required in the finalisation of the detailed statutory statement of accounts.

2.2The report also contains performance information on treasury management activities, payment of creditors and collection performance for debtors, local taxation and benefit overpayments.

2.3The report is for Cabinet to consider under its terms of reference 3.2.7 to be responsible for the council’s overall budget and determine action to ensure that the overall budget remains within the cash limit.

3 TIMESCALE

Is this a Major Policy Item/ No If yes, date for Cabinet N/A Statutory Plan meeting 15 4 FINAL OUTTURN 2014/15

4.1Corporate Overview

4.1.1 The Council at its meeting in March 2014 approved a balanced budget for 2014/15 that supported the council’s key priorities to meet the changing characteristics of the city, its residents, businesses and those that visit the city. The approved budget included £19m of savings as a result of a £9m reduction in funding and increased demand for services creating pressures of £10m. The MTFS also outlined a number of risks that required to be monitored during the year.

4.1.2 Since the budget was set by Council in March 2014 the council has experienced a variety of pressures against those budget plans. Audit Committee approved a one-off contribution of £3.2m from the capacity fund in June 2014 to mitigate pressures on children’s services and adult social care. There remained a £1.3m forecast overspend based on July 2014 figures.

4.1.3 During the year CMT received regular updates on the in-year budget position including tracking the delivery of savings approved as part of the budget and monitoring of identified risks. Through robust management action savings have been made to mitigate pressures, albeit some of the savings are one off actions, and the budget outturn has steadily improved. The November information upon which the probable outturn was based was for a £0.3m overspend with CMT committed to delivering a balanced position.

4.1.4 The Cabinet discussed the financial position regularly, with formal positions reported to Cabinet meetings held between September 2014 and March 2015 to ensure that pressures and risks were managed and taken account of in developing budget proposals for 2015/16 and future financial years. Financial plans were also considered by a cross-party budget working group.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Report Final Outturn 2014/15Report 328 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JH
Councillor John Holdich OBECommittee Member, present
GE
Councillor Gavin ElseyCommittee Member, apologies
WF
Councillor Wayne FitzgeraldCommittee Member, present
PH
Councillor Peter HillerCommittee Member, present
NN
Councillor Nigel NorthCommittee Member, present
SS
Councillor Sheila Scott OBECommittee Member, present
DS
Councillor David SeatonCommittee Member, present
LS
Councillor Lucia SerlucaCommittee Member, present
DL
Councillor Diane LambCommittee Member, present
GC
Councillor Graham CaseyAdvisory Member, present
YM
Councillor Yasmeen MaqboolAdvisory Member, present

On this subject at Peterborough

Search all
  1. Budget Monitoring Report Final Outturn 2014/15This decision
  2. Budget Monitoring Report Final Outturn 2015/16Noted
  3. Budget Monitoring Report Final Outturn 2013-14Noted
  4. Budget Monitoring Report Final Outturn 2011 / 2012Agreed
  5. Budget Monitoring Report Final Outturn 2010/2011Agreed
  6. NHS Peterborough Budgetary Monitoring - 2009/10 OutturnAgreed

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open
25 Aug 2026 Approval to deliver the construction phase of the sports quarter leisure developmentCabinet unanimously RESOLVED to: 1. Approve acceptance and use of the £20,000,000 grant from the Department of Busine... Approved Open