Peterborough City Council
Audit Committee, Monday 24 November 2025 at 6.00pm

Risk Management Update

Decided Finance 2 papers

AI summaryPeterborough City Council's Audit Committee reviewed the Strategic Risk Register, which flags four Band 8 (highest) risks: financial sustainability, cyber crime, growth delivery, and local government reorganisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedProvided comments on deep dive and strategic risks
MoneyReserves forecast c£20mDown from £70m at end of 2022/23
What happens nextNo further action setDecision was to review and comment only
Who it affectsCouncil-wide strategic risksIncluding residents, staff, vulnerable people

What was decided

The Audit Committee reviewed the Deep Dive report, the Strategic Risk Register, and the accompanying matrix in Appendix A, and provided comments on them.

Why

The Council's usable reserves are forecast to fall to c£20m (excluding Dedicated Schools Grant deficit) from £70m at the end of 2022/23, with a £5m overspend reported for 2024/25 and a £22m savings plan set for 2025/26 (only 68% of 2024/25 plans were delivered). Report P2

Four risks are rated at the highest Band 8, each with potential losses over £20m: financial sustainability, cyber crime, delivery of growth and regeneration schemes, and local government reorganisation. Report P2, P6, P11, P13, P21

The Council holds around c£0.5bn of borrowing, costing almost £40m a year to finance, and around c£50m in sundry debt across council tax, NNDR, housing benefits and adult social care. Report P2, P10

What happens next

Officers will continue existing mitigations tracked in the register, such as refreshing the on-call director cohort, recruiting a standalone emergency planning team, and extending the Towns Fund for a further 12 months with an extra £2m from the Cambridgeshire and Peterborough Combined Authority for the Cygnet Bridge project. Report P3, P4, P12

The full business cases for local government reorganisation are to be sent to MHCLG by 28th November, with the council aiming to secure the best outcome for residents and communities. Report P13, P14

The money

  • c£20m Forecast usable reserves by end of plan period (excluding DSG deficit) Report P2
  • £70m Reserves at end of 2022/23 Report P2
  • £5m Outturn overspend for 2024/25 Report P2
  • £22m Ambitious savings plan set for 2025/26 Report P2
  • c£0.5bn Council borrowing levels Report P2
  • almost £40m a year Cost of servicing the borrowing Report P2
  • c£50m Sundry debt across council tax, NNDR, housing benefits and adult social care Report P10
  • £2 million Additional Towns Fund contribution from CPCA for Cygnet Bridge project Report P12

Options considered

  • Chosen: Review and provide comments on the Deep Dive report, Strategic Risk Register and matrix

Implications

  • Financial: Reserves are forecast to fall to c£20m (excluding DSG deficit), with a £5m 2024/25 overspend and only 68% of the previous year's savings plan delivered; borrowing of c£0.5bn costs almost £40m a year. Report P2
  • Risk: Four risks sit at the highest Band 8 (loss over £20m): financial sustainability, cyber crime, growth/regeneration delivery, and local government reorganisation. Report P2, P6, P11, P13, P21
  • Legal: Failure on safeguarding adults, safeguarding children, or health and safety could expose the council to significant legal action, claims and penalties. Report P4, P5, P7, P8, P21, P22
  • Equalities: Safeguarding and community cohesion risks could lead to substantial disadvantage to large parts of the community, including many vulnerable residents, if not managed. Report P4, P5, P14, P21
  • Staffing: Workforce planning and recruitment risks are flagged, including over-reliance on contractors and temporary staff, with focused work ongoing to reduce agency use and improve retention. Report P9
  • Other: Local government reorganisation risk is rated Band 8, with business cases due to MHCLG by 28th November covering contracts, IT, HR, organisational design and public health grant funding. Report P13, P14

Who and where

  • Council staff and on-call directors across all directorates Report P3, P9
  • Vulnerable adults, children and young people receiving council services Report P4, P5, P9, P12
  • Council tax, NNDR and housing benefits debtors, and adult social care clients Report P10
  • Residents, businesses and communities across Peterborough, including asylum seekers and minority groups Report P11, P13, P14
  • Funders and partners including MHCLG, DfT, Homes England, LNER, Network Rail and the Combined Authority Report P11, P12, P13

Timeline

  • End of 2022/23: Reserves stood at £70m Report P2
  • 2024/25: Outturn was a £5m overspend, with only 68% of savings plans delivered Report P2
  • May 2025: Council recruited and launched its own standalone emergency planning team Report P3
  • Autumn 25: Refreshed and enhanced Prevent training to be rolled out to council staff Report P14
  • 28th Nov: Full business cases for local government reorganisation to be sent to MHCLG Report P14
  • July 2025: Emergency planning bespoke Executive Leadership Team input took place Report P3
  • 1-3 April: CQC Assurance visit took place; initial feedback to Executive Director on 16 April was positive, with a draft report expected shortly after 16 June Report P12

Plain English for the jargon

  • Band 8: Highest financial impact band, defined as a loss over £20 million
  • DSG deficit: Dedicated Schools Grant deficit, excluded from the c£20m reserves forecast
  • S114: Statutory Section 114 notice, issued when a council cannot balance its budget
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • MHCLG: Ministry of Housing, Communities and Local Government
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29

Resolved

It was RESOLVED : That the Audit Committee reviews and provides any comments on this Deep Dive report and the Strategic Risk Register and accompanying matrix included as Appendix A to the report.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Audit Committee

Peterborough Trending ↓ Inherent Residual Residual Risk Categorisation Supporting & Related Risks (the Triggers for the Lhood Impact CLT Residual Risk Financial Improving City Council RAG Proposed Mitigations Key contact Risk Lhood RAG Reputational Impact / Description Strategic Risks) 1-5 1-5 Owner Impact 1-5 Band 0-8 ↑Worsening Objectives Status 1-5 Status ↔ Stable

Financial Sustainable • A rapid decline in reserves- The Councils 5 5 25 • Strong Financial Management owned throughout the CM Emma Riding 4 5 20 The risk here is likely Band 7 to be High. However, ↑ Resilience of Future City reserves are forecast to reduce to c£20m (exc organisation- Budget Manager ownership and accountability is £10 - £20 this could become Council Council DSG deficit) from £70m at the end of 2022/23. key. extremley high if the Million • The outturn position for 2024/25 is a £5m • Ensuring clearer plans and mitigations are in place to deliver council entered into overspend. savings, and tracking these through a refreshed revenue and S114 territory and/or statutory services were • Debt levels- Borrowing stands at around savings board. not being provided, c£0.5bn costing almost £40m a year to finance. • Managing Reserves, only using these in line with the reserves and indeed it could be • A failure to plan and deliver savings, only 68% policy and ensuring the transformation reserve commitments moderate to low of plans were delivered in 2024/25, with an generate a Return on Investment. looking at some elements of this risk in ambitious £22m plan set for 2025/26. • Capital programme to be monitored and borrowing to only be isolation. • Budget gap in 2025/26 has been closed - but approved where a return on investment is expected or where it is includes a high level of risk, as demonstrated by absolutely necessary eg Health and Safety (moratorium in place) the previous point. • Spend and recruitment controls in place to manage the in year position to an improved position. • Budget Setting Process for 2026/27 has been reviewed and re- established with strong comms across the organisation.

Emergency Economy and • PCC's emergency planning team will be 4 4 16 1. On call cohort refreshed and enhanced. Now all ECLT are on CLT Rob Hill 2 3 6 The risk here depends Band 3 325

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CLT SRR October Audit Committee 2025Report 333 KB DownloadRead as text
PDF
Risk Management UpdateReport 206 KB Download

At this meeting

Whole meeting

Who was there

6 of 17 attended
DS
Daniel SchumannChair, present
ZA
Councillor Zameer AliVice Chair, present
IA
Councillor Imtiaz AliCommittee Member, present
MF
Councillor Mohammed FarooqCommittee Member, present
SQ
Councillor Shabina QayyumCommittee Member, present
SG
Stuart GreenCo-Optee, absent
ML
Mike LanghornCo-Optee, present
MG
Matthew GladstoneOfficer, in attendance
GK
Graham KitchenOfficer, in attendance
CM
Christine MarshallOfficer, in attendance
IA
Isaac AisuOfficer, in attendance
SC
Steve CrabtreeOfficer, in attendance

All 17 on the meeting page

On this subject at Peterborough

Search all
  1. Risk Management UpdateThis decision
  2. Risk Management- Annual Risk Report 2025/26 & Deep Dive ReviewAgreed
  3. Peterborough Flood Risk Management StrategyApproved
  4. Peterborough Flood Risk Management StrategyApproved
  5. Risk Management Strategy, Business Continuity Strategy and Update on Risk Management: Strategic RisksAgreed

More from Peterborough Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Actions and Matters ArisingThe Sustainable Future City Council Scrutiny Committee noted the action tracker and covering report. Noted Open
20 Jul 2026 Annual Governance Statement 2025/26The Audit Committee agreed the recommendations as amended: 1. To note the arrangement for compiling, reporting on, an... Agreed Open
20 Jul 2026 Draft Statement of Accounts 2025/26The Audit Committee agreed the recommendations: 1. To review and approve the Draught Statement of Accounts 2025/26, s... Agreed Open
20 Jul 2026 Peterborough City Council - Draft Audit Plan May 2026The Audit Committee noted the verbal update and the Draft Audit Plan May 2026. Noted Open
20 Jul 2026 2025/26 final outturn reportThe Audit Committee agreed the recommendations: 1. To note the final 2025/26 revenue and capital outturn as set out i... Agreed Open