Risk Management- Annual Risk Report 2025/26 & Deep Dive Review
AgreedFinance2 papers
AI summaryPeterborough City Council Audit Committee agreed to keep reviewing risk and to comment on the findings of the 2025/26 annual risk report and its deep dive reviews.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedContinue risk review and approve comments on deep dives
MoneyNot stated
What happens nextOngoing risk review continuesComments to be considered on deep dive findings
Who it affectsCouncil-wide risk managementAudit Committee oversight role
What was decided
The committee agreed to keep the ongoing review of risk going under its terms of reference. Report 4.1
The committee agreed to consider and approve comments on the deep dive review findings and the annual risk report at Appendix A.
Why
The report was submitted to the Audit Committee as part of its role in managing and overseeing risk across the council. Report 4.1
What happens next
The committee will continue its review of risk as set out in its terms of reference.
Members will consider and approve any comments on the deep dive findings and the annual risk report.
Implications
Financial: The report states there are no financial implications. Report 5.1
Legal: The report states there are no legal implications. Report 6.1
Equalities: The report states there are no equalities implications arising. Report 7.1
Who and where
Peterborough City Council, through its Audit Committee Report 4.1
Timeline
20 July 2026: Audit Committee meeting where the decision was made. Report P7
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67
Resolved
Decision : The Audit Committee agreed the recommendations: 1. To continue the process of the ongoing review of risk as per the committee's terms of reference. 2. To consider and approve any comments on the findings of the deep dive reviews included within the covering report and the annual risk report attached as Appendix A.
Word for word from the decision Peterborough published for this meeting.Source: democracy.peterborough.gov.uk
Responsible Director: Christine Marshall, Executive Director of Corporate Services and Section 151 Officer
Cabinet Member(s) Councillor Mohammed Jamil, Cabinet Member for Finance and Corporate responsible: Governance
Key Decision: No
Exempt: Public
Exemption Paragraph: N/A
Executive Summary: This report is submitted to Audit Committee following a recommendation from the committee in July 2024 for it to monitor progress in addressing risk-related issues and to monitor the effective development and operation of risk management in the council.
Recommendations: It is recommended that the Audit Committee:
1. Continues the process of the ongoing review of risk as per the committee’s terms of reference.
2. Considers and provides any comments on the findings of the Deep Dive reviews included within the covering report and the Annual Risk Report attached as Appendix A
363 20 July 2026 Audit Committee Agenda Item 11
1. Purpose
1.1The purpose of this report is for the Audit Committee to note and comment on the Risk Management Report and provide them with a more detailed analysis of departmental mitigation plans.
2. Background and key issues
2.1The Council recognises that there are risks in everything it does and has a duty to manage these risks in a balanced, structured, and cost-effective way.
2.2As part of the Deep Dive risk review the Council continues to periodically review identified risks across the Council. Following discussions with the owners and a review of the evidence available to support the controls captured the findings are detailed below.
RISK: Safeguarding - Adults. CLT Owner: Stephen Taylor Key Contacts: Debbie McQuade
Triggers / Impact: • Severe, negative impact on Council reputation and publicity if safeguarding not able to be fully assured, and harm befalls vulnerable people and / or their carers.
Proposed Mitigations: • Effective recruitment and retention • Strong effective partnership and governance arrangements - Safeguarding Adults Board. • Partners in care and health have reviewed safeguarding procedures, workflow and delivery model. Revised safeguarding model implemented with some ongoing amendments to ensure adequate reporting.
Assurance: • Following discussion with the risk owner in September 2025 residual risk likelihood reduced from 4 to 3 given all the work that has been done in this area. As a consequence, the residual risk overall reduced from 16 to 12, so amber from red.
• It should also be noted that the recent CQC report stated that PCC was demonstrating a strong commitment to safeguarding through effective systems,
364 20 July 2026 Audit Committee Agenda Item 11
skilled staff, multiagency collaboration, and a culture of continuous improvement. The authority is responsive to safeguarding concerns, prioritises person-centred practice, and actively learns from incidents to improve future outcomes. There is a clear focus on timely intervention, risk management, and making safeguarding personal, with robust governance and oversight supporting these efforts.
Evidence Reviewed: • A review of the vacancy and recruitment tracker shows that the safeguarding team RAG status is green as 7 FTE occupy 7 posts which, in addition, is supported by a comprehensive practitioner training matrix. • The Cambridge and Peterborough partnership safeguarding board website provides all the detail and processes to follow to adhere to the statutory guidance around multi-agency safeguarding arrangements. • The safeguarding operating model and supporting links comprehensively detail the criteria for an adult who may require support within the duties within section 42 of the Care Act.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Governance Statement 2025/26The Audit Committee agreed the recommendations as amended: 1. To note the arrangement for compiling, reporting on, an...
Draft Statement of Accounts 2025/26The Audit Committee agreed the recommendations: 1. To review and approve the Draught Statement of Accounts 2025/26, s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.