AI summaryPeterborough Cabinet approved £1,138,537 of active travel grant from CPCA and awarded works to M Group for three walking and cycling schemes in the city.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAward to M Group Services Limited
Money£1,138,537Total grant from CPCA for three schemes
What happens nextCapital Programme amendment reported next BCRSubject to Grant Funding Agreement completion
Who it affectsPedestrians and cyclists in PeterboroughThree routes across the city
What was decided
Cabinet accepted the £1,138,537 grant and approved officers entering into a Grant Funding Agreement with the Cambridgeshire and Peterborough Combined Authority. Report P2
Cabinet noted an amendment to the Capital Programme will be reported in the next BCR report to Cabinet, recognising the funding and expenditure. Report P3
Cabinet approved the award of works to M Group (Services) Limited under the existing Peterborough Highways Term Service Contract for the three named schemes. Report P4
Why
The funding comes from the Government's Consolidated Active Travel Fund, split 30% to Peterborough and 70% to Cambridgeshire County Council, based on population and a capability rating. Report 2.1, 2.2
Active travel improvements are expected to encourage more cycling and walking, reducing car journeys, emissions and supporting healthier lifestyles. Report 3.1, P23
The two larger schemes have had value for money assessments as part of the funding approval process, and Stanham Way opens a new pedestrian and cycle route to a business park. Report 6.1
What happens next
Officers will complete the Grant Funding Agreement with CPCA and obtain legal advice on its terms before project spend commences. Report P20, 7.1
Further design work will be undertaken on the Bourges Boulevard cycleway to determine which section(s) to upgrade, in consultation with the Cabinet Member. Report P16
Further survey and consultation work is planned on the existing Stanham Way bridge, with Ward Councillors and key stakeholders including the landowner O&H. Report P15, 4.1
The money
£1,138,537 Total Consolidated Active Travel Fund grant awarded to Peterborough by CPCA Report P2, 2.2
£275,000 Stanham Way Cycleway contract value to M Group Report P5
£663,537 Bourges Boulevard Cycleway contract value to M Group Report P6
£200,000 Peterborough Station Quarter Citylink contract value to M Group Report P7
£106,000 Section 106 funding already secured for Stanham Way project Report P15
£358,950 Previous active travel funding received for Bourges Boulevard design Report P16
£48 million Levelling Up Fund secured for the wider Peterborough Station Quarter project Report P17
£1.5m Towns Fund secured for the wider Peterborough Station Quarter project Report P17
Options considered
Rejected: Not to progress with the schemes. All schemes provide significant benefits to pedestrians and cyclists, and alternative funding has already been secured to develop all three projects. Report 9.1
Implications
Financial: Capital expenditure of £1,138,537 will be funded by confirmed grant from CPCA, with short-term borrowing required until grant claims are met. Report 5.1
Financial: If the project is aborted, development and design costs would need to be expensed to a revenue account, though this risk is described as low. Report 5.2
Legal: Advice from Legal Services will be obtained on the terms of the Grant Funding Agreement with CPCA before project spend commences. Report P20
Equalities: No equalities issues arise from the proposal; active travel elements will support all groups to walk and cycle safely. Report 8.1
Climate: Construction is expected to increase emissions from energy, transport, water, waste and carbon-intensive materials. Report P24
Climate: Mitigation includes M Group's use of HVO-fuelled vehicles, material reviews, and a tool allowing designers to select lower-embodied-carbon materials. Report P25
Legal: The Peterborough Highway Services Contract was procured under the Competitive Dialogue Procedure and permits the Council to call off works within its scope. Report 7.1
Who and where
Pedestrians and cyclists in Peterborough using the three improved routes Report 3.1, P23
Residents and workers accessing Stanham Way business park from the south via Crown Lakes Country Park Report P15
Ward Councillors for the scheme areas Report 4.1
Landowner O&H at Stanham Way Report 4.1
M Group (Services) Limited as the appointed contractor Report P1, P4
Cambridgeshire and Peterborough Combined Authority as grant funder Report 1.1, 2.2
Timeline
3 November 2025: CPCA Funding Committee approved allocation of the Consolidated Active Travel Fund Report 2.2
2026: Main construction works planned for the Station Quarter City Link package Report P19
16 December 2025: Cabinet decision to accept the grant and award the works contract Report P8
Plain English for the jargon
CPCA: Cambridgeshire and Peterborough Combined Authority
Consolidated Active Travel Fund: Government fund supporting local authorities to develop and construct walking, wheeling and cycling facilities in England
s106 funding: Section 106 planning obligation contributions from developers, used here to part-fund the Stanham Way project
HVO: Hydrotreated Vegetable Oil, a lower-carbon fuel used by M Group's vehicles
City Link package: First phase of the Peterborough Station Quarter project, focused on Queensgate roundabout, including removal of two subways and new footways and cycleways
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item71
Resolved
RESOLVED to; 1. (a) Approve acceptance of the grant and (b) approve the Council/relevant officers to enter into a Grant Funding Agreement/s with Cambridgeshire and Peterborough Combined Authority (CPCA) in respect of the £1,138,537 awarded to the active travel schemes listed below. 2. Note that an amendment to the Capital Programme will take place to recognise the funding and expenditure associated with this grant and will be reported as part of the next BCR report to Cabinet. 3. Approve the award of works to M Group (Services) Limited, under the existing Peterborough Highways Term Service Contract for the following schemes and contract amount(s) subject to the completion of the associated Grant Funding Agreement/s: • Stanham Way Cycleway - £275,000 • Bourges Boulevard Cycleway - £663,537 • Peterborough Station Quarter Citylink - £200,000
Word for word from the decision Peterborough published for this meeting.Source: democracy.peterborough.gov.uk
This report is seeking approval to award highway works to the value of £1,138,537 to M Group Limited (formerly Milestone Infrastructure Services Limited) for the delivery of three active travel schemes.
Recommendations
1. Cabinet to (a) approve acceptance of the grant and (b) approve the Council/relevant officers to enter into a Grant Funding Agreement/s with Cambridgeshire and Peterborough Combined Authority (CPCA) in respect of the £1,138,537 awarded to the active travel schemes listed below.
2. Note that an amendment to the Capital Programme will take place to recognise the funding and expenditure associated with this grant and will be reported as part of the next BCR report to Cabinet.
3. Cabinet to approve the award of works to M Group (Services) Limited, under the existing Peterborough Highways Term Service Contract for the following schemes and contract amount(s) subject to the completion of the associated Grant Funding Agreement/s:
• Stanham Way Cycleway - £275,000
• Bourges Boulevard Cycleway - £663,537
• Peterborough Station Quarter Citylink - £200,000
3 16 December 2025 Cabinet Agenda Item No.5
1. Purpose
1.1The purpose of the report is to outline proposals for three active travel schemes and seek approval for construction subject to the completion of a Grant Funding Agreement between Peterborough City Council and the Cambridgeshire and Peterborough Combined Authority (CPCA).
2. Background and key issues
2.1The CPCA has received funding from the Government’s Consolidated Active Travel Fund. This Fund supports local authorities with developing and constructing walking, wheeling and cycling facilities in England.
2.2The Government’s funding allocation was calculated using a formula that takes into account population size and the CPCA’s capability rating for active travel which is a level 3. The split between Cambridgeshire County Council and Peterborough City Council is in line with previous transport grant funding, with 70% going to Cambridgeshire County Council and 30% going to Peterborough City Council. The City Council’s 30% equates to £1,138,537. The funding was approved at CPCA’s Funding Committee on 3 November 2025.
2.3The three active travel schemes to be delivered are:
2.3.1 Stanham Way cycleway. Stanham Way is a business park in the south east of Peterborough. Pedestrian and cycle access is available to the north and east of the business park, but it is not possible from the south because of a waterway, Stanground Lode. The project will look to improve and open up an old, existing bridge and provide pedestrian and cycle connections from Crown Lakes Country Park into Stanham Way. The Council has already secured £106,000 in s106 funding for this project. The construction costs are estimated to be £275,000 although further work is being undertaken on the existing bridge to understand the work that will be required to safely open it for public use.
2.3.2 Bourges Boulevard cycleway. The Council has received previous active travel funding, £358,950, to design an upgrade of the existing route between Bright Street and Junction 18 / Rhubarb Bridge. Due to the length of the route, it is being split into different sections from a design and future construction perspective. £663,537 of the Consolidated Active Travel Fund will be used to fund a section(s) of the Bourges Boulevard cycleway. Further design work will be undertaken before determining which section(s) should be upgraded, in consultation with the Cabinet Member. It is the Council’s intention to upgrade the entire route in future years, subject to future funding being secured.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.