Quarter 3 2025/26 Corporate Performance Report

Noted Executive 2 papers

AI summaryCabinet noted Peterborough City Council's Quarter 3 2025/26 corporate performance report covering 79 indicators, with 35% on or above target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ3 2025/26 corporate performance report
Money£100,000 per monthEstimated B&B cost saving
What happens nextQ4 reportingNext quarterly cycle
Who it affectsPeterborough residentsAll council service areas

What was decided

Cabinet noted the Quarter 3 2025/26 Corporate Performance Report, taking no further action.

Why

The report is the standard quarterly assessment of 79 performance indicators across all council service areas, required for ongoing oversight. Report P46, P47

What happens next

CGL Aspire's new five-year drug and alcohol services contract is scheduled to begin on 1 April 2026, with co-location and enhanced offers planned. Report P6

A Service Improvement Plan is in place for the Drug Treatment Outcomes measure, with close monitoring of progress expected. Report P8

The money

  • £100,000 per month Estimated cost avoidance from reduced bed and breakfast use Report P10
  • £300,000 Added to Council Tax owed due to VOA valuation delays Report P43
  • more than £500,000 Owed by a small number of property management companies Report P43
  • 507 Total affordable homes expected across 2025/26, with 256 already completed and 251 forecast for Q4 Report P30
  • 70% Reduction in households in bed and breakfast from the previous year, leaving around 29 households Report P10
  • 37% Year-on-year rise in Universal Credit claims due to ill-health in Peterborough Report P7
  • 81.8% Council Tax collection rate, 1.8% behind target Report P43
  • 94% Invoices paid within 30 days in Q3, against a 95% target Report P39

Implications

  • Financial: Council Tax collection is 1.8% behind target, with staff vacancies earlier in the year and VOA delays contributing. Report P43
  • Staffing: Mandatory learning completion fell to 63% in Q3 following the introduction of a new learning system and a planned pause. Report P45
  • Risk: Safeguarding processes reduced risk in 95% of cases in Q3, outperforming the England average of 91%. Report P10
  • Staffing: Average sickness days per employee have risen slightly, attributed to seasonal illness and more accurate reporting. Report P45
  • Other: Workforce pressures may affect recruitment as ICB funding transfers and PCC, CCC and CPFT compete for similar roles. Report P5
  • Other: Drug Treatment Outcomes measure remains below target, with only a 0.1% improvement shown in October and November data. Report P8

Who and where

  • Unpaid carers in Peterborough, with over 4,500 now registered on the digital support platform Report P2
  • Children in care in Peterborough, with numbers falling to 423 from 434 in Q2 Report P15
  • Care leavers and care experienced young people across housing, EET and pathway planning Report P20, P21, P22
  • Households at risk of or experiencing homelessness, with around 70 approaches per week Report P10, P12
  • Local businesses and suppliers, with 53% of council spend in Peterborough against a 60% target Report P25, P26
  • Council Tax payers, with a small number of property management companies owing more than £500,000 Report P43
  • Job seekers and people on out-of-work benefits, totalling 7,470 against a 7,800 target Report P32
  • Children missing education, with numbers dropping sharply after a period of focused home visits Report P17

Timeline

  • November 2025: Greater Peterborough Network began delivering the community stop smoking service after a tender process Report P6
  • Q3 2025/26 (October to December 2025): Reporting period covered by the performance report Report P46
  • December 2025: Housing Needs Advice and Outreach Service launched, transforming call management Report P10
  • 1 December 2025 to 31 January 2026: Multi-agency Winter of Action Plan runs in the city centre Report P24
  • 9 January 2026: Care Quality Commission published its assurance report rating safeguarding arrangements as Good Report P10
  • 1 April 2026: CGL Aspire's new five-year drug and alcohol services contract starts Report P6
  • Q4 2025/26 (forecast): Around 251 further affordable homes are forecast for completion Report P30

Plain English for the jargon

  • MASH: Multi-Agency Safeguarding Hub, a partnership team handling safeguarding contacts
  • EHCP: Education, Health and Care Plan, a statutory plan for children with special educational needs
  • CME: Children Missing Education
  • EHE: Electively Home Educated children
  • CIL: Community Infrastructure Levy, a charge on new development
  • Section 106: Planning obligations used to secure developer contributions for infrastructure
  • EET: Education, Employment or Training
  • LEVI: Local Electric Vehicle Infrastructure, a government funding programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item108

Resolved

RESOLVED to note the Corporate Performance Report for Quarter Three, 2025/26.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

CORPORATE PERFORMANCE REPORT Q3 2025 - 2026 303 304 KEY ACHIEVEMENTS:

A concentrated focus on identifying and supporting unpaid carers has led to an increase in the numbers receiving an assessment or review. There has also been good engagement with our digital carers support platform, with over 4,500 carers in Peterborough now registered. There has been a corresponding reduction in the numbers of people approaching the council for care and support due to carer breakdown. Our reablement service continues to deliver LIVE WELL good outcomes, with 84% completing their reablement with no need for long-term care FOR LONGER and support. This is high compared to the 305

national average of 77%.

CHALLENGES:

Although we have seen an improvement in the paid employment rate for people with learning disabilities, this remains low, as does the rate for people known to mental health services. In recent weeks there has been a focus on promoting the supported employment and job coaching support provided by City College. Pathway one development (reablement and intermediate care alignment) and increase in the council workforce once the ICB transfers funding. PCC/CCC and CPFT will all be actively recruiting into similar roles, which may impact our ability to recruit. KEY ACHIEVEMENTS:

Performance for the 14-day mandated newbirth visit within the Healthy Child Programme remains strong. In Q2 2025/26, delivery was 87%, showing sustained coverage. More recent data for November 2025 shows an improvement to 95%, reflecting continued progress in early contact and responsiveness within the service. CGL Aspire Peterborough has been awarded a new five-year contract to deliver drug and alcohol services, starting 1 April 2026. Preparations are underway to mobilise the new contract, which will see services co-located across the city, an enhanced offer for 18–25-year-olds, and further development of recovery support in Peterborough. Work is underway to ensure people with drug and alcohol problems leaving prison can quickly access support services for continuity of care. A new data matching process is being embedded and is already leading to service improvements. The Peterborough community stop smoking service has changed provider following an open and transparent tender process. Greater Peterborough Network (GPN) began delivering the service in November 2025.

HEALTH Universal Credit claims due to ill-health rose by 37% in Peterborough over the past year, matching national trends. While this highlights ongoing health challenges, it also suggests more residents are accessing financial support. Peterborough accounts for nearly 40% of UC claimants in the combined authority area, with long-term sickness a leading cause of economic inactivity. 306 CHALLENGES:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q3 PCC corporate performance report January 2026 FINALReport 25 MB DownloadRead as text
PDF
Quarter 3 2025/26 Corporate Performance ReportReport 228 KB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
SQ
Councillor Shabina Qayyum Leader of the CouncilChair, present
MF
Councillor Mohammed Farooq Deputy Leader & Cabinet Member for Growth and RegenerationVice Chair, present
ZA
Councillor Zameer Ali Cabinet Member for Communities, Poverty & Public HealthCommittee Member, present
NB
Councillor Neil Boyce Cabinet Member for Adults Social CareCommittee Member, present
KC
Councillor Katy Cole Cabinet Member for Children's ServicesCommittee Member, present
AE
Councillor Angus Ellis Cabinet Member for Environment & TransportCommittee Member, present
CH
Councillor Christian Hogg Cabinet Member for Housing and Regulatory ServicesCommittee Member, present
MJ
Councillor Mohammed Jamil Cabinet Member for Finance & Corporate GovernanceCommittee Member, present

On this subject at Peterborough

Search all
  1. Quarter 3 2025/26 Corporate Performance ReportThis decision
  2. Quarter 2 2025/26 Corporate Performance ReportNoted
  3. Quarter 2 2025/26 Corporate Performance ReportNoted

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open
25 Aug 2026 Approval to deliver the construction phase of the sports quarter leisure developmentCabinet unanimously RESOLVED to: 1. Approve acceptance and use of the £20,000,000 grant from the Department of Busine... Approved Open