Agreed that – (1) the progress on the development of options for Deep Lane junction is noted; (2) Option B (D) is approved as the preferred option to be further developed and included within the Eastern Corridor major scheme bid; (3) Option C is approved as the lower cost alternative option to be further developed and included within the Eastern Corridor major scheme bid; (4) Juli Wileman (Major Scheme Project Manager) is thanked for handling all the comments and suggestions from the community since the start of the works at Gdynia Way. (The order of the agenda was changed and this item was brought forward)
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
1.1This report records progress on the development of options for the A38 Deep Lane Junction, which is part of the Eastern Corridor High Quality Public Transport (HQPT) Scheme.
1.2A junction improvement at Deep Lane is required in order to accommodate future traffic growth and traffic generated by the strategic residential and employment developments along the Eastern Corridor.
1.3During 2009 Plymouth City Council, Devon County Council and the Highways Agency have been working in partnership to develop alternative options for Deep Lane Junction. Around fifteen options were investigated, but following an initial appraisal that considered operational efficiency, the promotion of sustainable transport, environmental impact, network resilience, safety and cost, four options were short listed and then developed in more detail.
1.4These four options were the subject of a public consultation event towards the end of 2009 and a Stage 1 Scheme Assessment Report in March 2010 which considered the costs, benefits, risks, environmental impact and technical issues associated with each option.
1.5The results of the public consultation and the outputs of the Stage 1 Assessment Report have been considered by Plymouth City Council, Devon County Council and the Highways Agency and Officers have recommended two options to be developed further and included within the Eastern Corridor High Quality Public Transport Major Scheme Business Case. One option would be the “Preferred Option” and the other option would be the “Lower Cost Alternative”.
1.6The submission of the Major Scheme Business Case to DfT, which will also be considered as part of the Regional Funding Allocation process, is programmed for the first half of 2011.
1 2.0 Corporate Plan 2010-13:
2.1The Eastern Corridor Major Scheme and the submission of the business case to secure capital funding, is a key project for delivering the Local Transport Plan, the Local Development Framework (LDF) Core Strategy, the North Plymstock Area Action Plan (AAP) and South Hams District Council’s Sherford AAP.
2.2The scheme directly assists Corporate Improvement Priority 11 “Improving Access across the City” and the submission of the business case is a key milestone for CIP 11 in 2010/11. It will provide faster and more reliable journey times for public transport services along the Eastern Corridor, linking new and existing residential areas with better access to employment, education, leisure, retail and healthcare facilities.
3.0Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
3.1There are no financial implications as a direct result of the recommendations in this report. The costs associated with the preferred option will be included in the next overall Eastern Corridor HQPT scheme forecast, which is returned periodically to the DfT. _________________________________________________________________ 4.0 Resource Implications:
4.1There are no resource implications arising from this report
5.0Other Implications: e.g. Section 17 Community Safety, Health and Safety, Risk Management, Equalities Impact Assessment, etc.
5.1There are no other implications directly arising from this report.
6.0Recommendations & Reasons for recommended action:
6.1The Cabinet is requested to:
1. Note the progress on the development of options for Deep Lane Junction 2. Approve Option B (D) as the Preferred Option to be further developed and included within the Eastern Corridor Major Scheme Bid 3. Approve Option C as the Lower Cost Alternative option to be further developed and included within the Eastern Corridor Major Scheme Bid
Reasons:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.