EASTERN CORRIDOR HIGH QUALITY PUBLIC TRANSPORT SCHEME: DEEP LANE PROPOSALS

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 8 June 2010. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Agreed that – (1) the progress on the development of options for Deep Lane junction is noted; (2) Option B (D) is approved as the preferred option to be further developed and included within the Eastern Corridor major scheme bid; (3) Option C is approved as the lower cost alternative option to be further developed and included within the Eastern Corridor major scheme bid; (4) Juli Wileman (Major Scheme Project Manager) is thanked for handling all the comments and suggestions from the community since the start of the works at Gdynia Way. (The order of the agenda was changed and this item was brought forward)
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report records progress on the development of options for the A38 Deep Lane Junction, which is part of the Eastern Corridor High Quality Public Transport (HQPT) Scheme.

1.2A junction improvement at Deep Lane is required in order to accommodate future traffic growth and traffic generated by the strategic residential and employment developments along the Eastern Corridor.

1.3During 2009 Plymouth City Council, Devon County Council and the Highways Agency have been working in partnership to develop alternative options for Deep Lane Junction. Around fifteen options were investigated, but following an initial appraisal that considered operational efficiency, the promotion of sustainable transport, environmental impact, network resilience, safety and cost, four options were short listed and then developed in more detail.

1.4These four options were the subject of a public consultation event towards the end of 2009 and a Stage 1 Scheme Assessment Report in March 2010 which considered the costs, benefits, risks, environmental impact and technical issues associated with each option.

1.5The results of the public consultation and the outputs of the Stage 1 Assessment Report have been considered by Plymouth City Council, Devon County Council and the Highways Agency and Officers have recommended two options to be developed further and included within the Eastern Corridor High Quality Public Transport Major Scheme Business Case. One option would be the “Preferred Option” and the other option would be the “Lower Cost Alternative”.

1.6The submission of the Major Scheme Business Case to DfT, which will also be considered as part of the Regional Funding Allocation process, is programmed for the first half of 2011.

1 2.0 Corporate Plan 2010-13:

2.1The Eastern Corridor Major Scheme and the submission of the business case to secure capital funding, is a key project for delivering the Local Transport Plan, the Local Development Framework (LDF) Core Strategy, the North Plymstock Area Action Plan (AAP) and South Hams District Council’s Sherford AAP.

2.2The scheme directly assists Corporate Improvement Priority 11 “Improving Access across the City” and the submission of the business case is a key milestone for CIP 11 in 2010/11. It will provide faster and more reliable journey times for public transport services along the Eastern Corridor, linking new and existing residential areas with better access to employment, education, leisure, retail and healthcare facilities.

3.0Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land

3.1There are no financial implications as a direct result of the recommendations in this report. The costs associated with the preferred option will be included in the next overall Eastern Corridor HQPT scheme forecast, which is returned periodically to the DfT. _________________________________________________________________ 4.0 Resource Implications:

4.1There are no resource implications arising from this report

5.0Other Implications: e.g. Section 17 Community Safety, Health and Safety, Risk Management, Equalities Impact Assessment, etc.

5.1There are no other implications directly arising from this report.

6.0Recommendations & Reasons for recommended action:

6.1The Cabinet is requested to:

1. Note the progress on the development of options for Deep Lane Junction 2. Approve Option B (D) as the Preferred Option to be further developed and included within the Eastern Corridor Major Scheme Bid 3. Approve Option C as the Lower Cost Alternative option to be further developed and included within the Eastern Corridor Major Scheme Bid

Reasons:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Deep Lane OptionsAppendix A 974 KB Download
PDF
EASTERN CORRIDOR HIGH QUALITY PUBLIC TRANSPORT SCHEME: DEEP LANE PROPOSALSReport 69 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
IB
Councillor Ian BowyerMember, present
PB
Councillor Peter BrookshawMember, present
TF
Councillor Ted FryVice-Chair, apologies
GJ
Councillor Glenn JordanMember, present
ML
Councillor Michael LeavesMember, present
SL
Councillor Samantha LeavesMember, present
GM
Councillor Grant MonahanMember, present
VP
Councillor Vivien PengellyChair, present
MW
Councillor Mrs WatkinsMember, present
KW
Councillor Kevin WigensMember, present

On this subject at Plymouth

Search all
  1. EASTERN CORRIDOR HIGH QUALITY PUBLIC TRANSPORT SCHEME: DEEP LANE PROPOSALSThis decision
  2. Eastern corridor progress report (e3)Agreed
  3. Eastern corridor progress report (e3)Noted
  4. Eastern Corridor Major Scheme: Options for Deep Lane JunctionDecided
  5. Eastern corridor briefingDecided

More from Plymouth Cabinet

All decisions
MeetingDecisionOutcome
14 Sep 2026 Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... Approved Open
14 Sep 2026 Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... Approved Open
24 Aug 2026 Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... Approved Open
24 Aug 2026 Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... Decided Open
24 Aug 2026 SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies