SHORELINE MANAGEMENT PLAN REVIEW DURLSTON HEAD TO RAME HEAD

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 19 October 2010. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

Agreed that – (1) the Shoreline Management Plan Review (SMP2), is adopted, as it relates to Plymouth; (2) a Shoreline Asset Management Plan is produced; (3) an investigation of opportunities for co-funding of defence works, is supported; (4) the submission of a funding application to the Environment Agency, to fund coastal defence works, is supported.
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Cabinet

CITY OF PLYMOUTH

Subject: Shoreline Management Plan Review (SMP2) Durlston Head to Rame Head Committee: Cabinet Date: 19 October 2010 Cabinet Member: Councillor Fry and Councillor Wigens CMT Member: Director for Development and Regeneration Author: Victoria Hutchins Plymouth Transport & Highways / Thomas White (PCC Head of Network Management) Contact: Tel: 01752 398048 E-mail: [email removed] Tel: 01752 308053 E-mail:[email protected] Ref: PL1043989/R01 Part: I

Executive Summary: Plymouth City Council owns, and is responsible for, 5km of shoreline around the City Boundary.

The Shoreline Management Plan 2 (SMP 2), is a non-statutory policy document that looks at coastal and flood risk management issues relating to the coastline around England and Wales over the next 100 years. Prepared by Halcrow for the Department for Environment, Food and Rural Affairs (Defra), SMP2 updates the original SMP of 1998. The part of the Plan relating to Plymouth’s foreshore has been prepared in consultation with the South Devon & Dorset Coastal Group, of which PCC are a member.

Within the South West region, each section of the coastline has been divided into individual policy units and these tend to cover areas with similar erosion characteristics. The policy for Plymouth is primarily to “Hold the existing defence line”. For each area, actions are identified to be completed ahead of the next SMP review in 2015. Adopting SMP2 will commit the Council to preparing a Shoreline Asset Management Plan and seeking co-funding opportunities for coastal defence works.

SMP2 will be used in allocating Defra Annual Budget of £600 million to maintain and improve coastal defences. The Council has applied for £3.5 million from this budget to implement coastal defence schemes in 2011/2012; these are listed in Appendix 3. Members are recommended to • Approve the adoption of the SMP2 as it relates to Plymouth • Agree to the production of an associated Shoreline Asset Management Plan (SAMP) • Support investigation of opportunities for co-funding of defence works • Support submission of funding application to EA to fund coastal defence works

The cost of implementing the above recommendations is estimated to be £80k which is being sought from the Defra annual budget.

Adopting the SMP2 ensures Plymouth is compliant with Environment Agency policy and, therefore, puts the City in a stronger position when bidding for part of the £600 million national budget for coastal defences. PL1043989/R01Shoreline Management Plan Review Adoption Report Corporate Plan 2010 - 2013:

SAMP is a fundamental driver for improvements which support growth in the city (CIP12) and provides a framework for achieving the aspiration to be one of Europe’s finest waterfront cities.

Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land

The SMP2 identifies the level of intervention needed along the coastline. The SAMP will identify the more specific works and costs associated with them. An application for £80,000 of funding to produce a Shoreline Asset Management Plan for PCC was included in the Medium Term Plan (MTP) 2011/12 application to the EA. A preliminary indication on the success of the application is expected in November 2010.

However, failure to secure this funding will require other funding to be found to provide this statutory document.

Other Implications: e.g. Section 17 Community Safety, Health and Safety, Risk Management, Equalities Impact Assessment, etc. None

Recommendations & Reasons for recommended action: It is recommended that members: 1. Approve the adoption of the Shoreline Management Plan Review (SMP2), as it relates to Plymouth; 2. Agree to produce a Shoreline Asset Management Plan; 3. Support investigation of opportunities for co-funding of defence works; 4. Support submission of funding application to EA to fund coastal defence works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SHORELINE MANAGEMENT PLAN REVIEW DURLSTON HEAD TO RAME HEADReport 76 KB DownloadRead as text
PDF
Shoreline Management Plan Review Appendix 1Appendix 3.3 MB Download
PDF
Shoreline Management Plan Review Appendix 2Appendix 105 KB Download
PDF
Shoreline Management Plan Review Appendix 3Appendix 44 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
IB
Councillor Ian BowyerMember, present
PB
Councillor Peter BrookshawMember, apologies
TF
Councillor Ted FryVice-Chair, present
GJ
Councillor Glenn JordanMember, present
ML
Councillor Michael LeavesMember, present
SL
Councillor Samantha LeavesMember, present
GM
Councillor Grant MonahanMember, present
VP
Councillor Vivien PengellyChair, present
MW
Councillor Mrs WatkinsMember, present
KW
Councillor Kevin WigensMember, present

More from Plymouth Cabinet

All decisions
MeetingDecisionOutcome
14 Sep 2026 Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... Approved Open
14 Sep 2026 Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... Approved Open
24 Aug 2026 Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... Approved Open
24 Aug 2026 Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... Decided Open
24 Aug 2026 SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies