OPERATIONAL RISK MANAGEMENT UPDATE REPORT

Agreed Finance 1 paper

Audit and Governance Committee agreed this item on Friday 21 January 2011. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

Agreed that – (1) the current position with regard to operational risk management be noted; (2) written responses to the questions raised at (d), (e) and (f) above would be circulated to Committee Members via the Democratic Support Officer. (This item was considered in conjunction with the Independent Review of the Council’s Risk Management Maturity report detailed under minute 63).
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Audit and Governance Committee

Executive summary

At the meeting of the Audit Committee on 11th December 2009, I reported that Services were engaged in a revision to their Operational Risk Registers in order to identify and align risks with their Business Plans in accordance with guidelines on operational risk management introduced as part of the 2008/9 Business Planning guidance document “Striving for Excellence”.

This revised approach, together with a supporting guide for managers, “Risk Management and Business Planning”, was endorsed and approved by this Committee on 25th January 2008.

This report now outlines the continuing progress being made across Services in delivering Operational Risk Registers based on this approach.

The total number of operational risks now reported has increased from 115 to 118, comprising 4 high (red) risks, 63 medium (amber) risks and 51 low (green) risks.

Commentary on the high risk areas is included in the report together with details of control actions/mitigation in place.

Corporate Plan 2011/2014 as amended by the four new priorities for the City and Council: Operational Risk Registers are being aligned to Business Plan objectives which are in turn linked to the Corporate Plan and Corporate Improvement Priorities. This ensures that appropriate links are identified with individual risks where control action contributes to the delivery of a key corporate objective.

Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land : None arising specifically from this report but control measures identified in risk registers could have financial or resource implications.

Other Implications: e.g. Section 17 Community Safety, Health and Safety, Risk Management, Equality Impact Assessment etc. None arising specifically from this report but community safety and health and safety risks are taken into account in the preparation of risk registers.

Recommendations & Reasons for recommended action: The Audit Committee is recommended to note the current position with regard to operational risk management.

Alternative options considered and reasons for recommended action: Effective risk management processes are an essential element of internal control and as such are an important element of good corporate governance. For this reason alternative options are not applicable.

Background papers: Plymouth City Council Risk Management Strategy and Policy Statement Operational Risk Registers and associated working papers “Risk Management and Business Planning” Guidance Note, January 2008 Previous reports on risk management to Audit Committee

Sign off:

Head SW Head DS Head Head Head Head of of Leg of HR of AM of ITof Fin Strat Proc Originating SMT Member : Assistant Director, Democracy and Governance

CRM/MJH/RM Monitoring Report 21 Jan 2011 2 Report of Director of Corporate Support to Audit Committee 21st January 2011

Operational Risk Management Update Report

1. Introduction

1.1At the meeting of the Audit Committee on 11 December 2009, I reported that Services were engaged in a revision to their Operational Risk Registers in order to identify and align risks with their Business Plans in accordance with guidelines on operational risk management introduced as part of the 2008/9 Business Planning guidance document “Striving for Excellence”.

1.2This revised approach, together with a supporting guide for managers, “Risk Management and Business Planning”, was endorsed and approved by this th Committee on 25 January 2008.

1.3This report now outlines the continuing progress being made across Services in delivering Operational Risk Registers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OPERATIONAL RISK MANAGEMENT UPDATE REPORTReport 110 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
PB
Councillor Peter BerrowChair, present
RC
Mr R ClarkeAdvisory Member, present
TE
Councillor Tudor EvansVice-Chair, present
PM
Councillor Pauline MurphyMember, present
LM
Lynne MylesAdvisory Member, apologies
DS
Councillor David StarkMember, present
IS
Mr I StewartCo-Optee (voting), present
JT
Councillor Jack ThompsonMember, present

On this subject at Plymouth

Search all
  1. OPERATIONAL RISK MANAGEMENT UPDATE REPORTThis decision
  2. Operational Risk and Opportunity Management - Update ReportAgreed
  3. Operational risk & opportunity management - update reportAgreed
  4. Operational risk and opportunity management - update reportAgreed
  5. Operational risk management - update reportAgreed
  6. Operational risk updatesAgreed

More from Plymouth Audit and Governance Committee

All decisions
MeetingDecisionOutcome
14 Jan 2025 Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. Agreed Open
28 Nov 2022 Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... Agreed Open
28 Nov 2022 Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... Agreed Open
29 Nov 2021 Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... Agreed Open
11 Oct 2021 Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies