Audit and Governance Committee, Friday 21 January 2011 at 10.00am

INDEPENDENT REVIEW OF THE COUNCIL'S RISK MANAGEMENT MATURITY - SUMMARY

Agreed Finance 2 papers

Audit and Governance Committee agreed this item on Friday 21 January 2011. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

Agreed that – (1) the findings of the independent review be endorsed. (2) a written response to the question raised at (g) above would be circulated to Committee Members via the Democratic Support Officer. (This item was considered in conjunction with the Operational Risk Management Update report detailed under minute 62).
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Audit and Governance Committee

Plymouth City Council Independent review of the Council’s risk management maturity

Summary of key findings January 2011 Table of Contents 1 Introduction, scope and objectives...................................................................1

Introduction..................................................................................................................................................... 1

Scope and objectives of the review ................................................................................................................ 1

2 Approach to the review ......................................................................................2

Introduction..................................................................................................................................................... 2

Initial desktop review ...................................................................................................................................... 2

Interviews with key personnel......................................................................................................................... 2

Reporting and next steps................................................................................................................................ 3

3 Summary of key findings and recommendations.............................................4

Important caveat ............................................................................................................................................. 4

Key findings .................................................................................................................................................... 4

Overall conclusion .......................................................................................................................................... 5

Key recommendations arising......................................................................................................................... 5

Risk management of collaborative arrangements........................................................................................... 6

The information contained is this document is confidential to Plymouth City Council and Heath Lambert Limited. The document and its contents may not be reproduced or disclosed to any third party without the prior written consent of Plymouth City Council and Heath Lambert Limited.

© 2011 Heath Lambert Limited 1 Introduction, scope and objectives

Introduction

Heath Lambert was appointed risk management and insurance adviser to the Council on 1 October 2010. One of our first tasks on appointment was to commence an independent review of the framework for risk management (RM). This document sets out the key findings arising from that review.

Scope and objectives of the review

The review has been carried out by Judy Jones, Head of Public Sector Risk Consulting at Heath Lambert. It provides an independent assessment of the Council’s risk management maturity based upon the principles of best practice in risk management as defined by: the International Standard ISO 31000; the British Standard BS31100: 2008; HM Treasury and ALARM, the Public Risk Management Association.

The scope has encompassed the following aspects of the risk management process, as defined by HM Treasury in the Treasury Risk Management Assessment Framework (July 2009) and adapted by ALARM in the National Performance Model for Risk Management in the Public Sector:

• leadership and management • strategy & policy • people • partnerships, shared risks and resources • processes • risk handling & assurance • outcomes and delivery.

Our main objective has been to assess the current level of risk management maturity across the Council.

1 2 Approach to the review

Introduction

Our approach has been based on a comprehensive review of documentation together with a series of interviews.

Initial desktop review

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INDEPENDENT REVIEW OF THE COUNCIL'S RISK MANAGEMENT MATURITY: SUMMARYReport 978 KB DownloadRead as text
PDF
Independent review of RM Framework FINAL REPORT January2011 v2Report 1 MB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
PB
Councillor Peter BerrowChair, present
RC
Mr R ClarkeAdvisory Member, present
TE
Councillor Tudor EvansVice-Chair, present
PM
Councillor Pauline MurphyMember, present
LM
Lynne MylesAdvisory Member, apologies
DS
Councillor David StarkMember, present
IS
Mr I StewartCo-Optee (voting), present
JT
Councillor Jack ThompsonMember, present

More from Plymouth Audit and Governance Committee

All decisions
MeetingDecisionOutcome
14 Jan 2025 Committee Self-AssessmentIt was agreed that the terms of reference for the Committee would be shared along with the link to the self-assessment. Agreed Open
28 Nov 2022 Tracking DecisionsIt was agreed that a report would be submitted to the Audit and Governance Committee detailing work undertaken by int... Agreed Open
28 Nov 2022 Exempt BusinessAgreed that under Section 100(4) of the Local Government Act 1972, to exclude the press and public from the meeting f... Agreed Open
29 Nov 2021 Tracking DecisionsIt was agreed that the Chair and Vice Chair would discuss the issues surrounding the public availability of the Grant... Agreed Open
11 Oct 2021 Appointment of Chair and Vice ChairIt was agreed that Councillor Bingley is appointed as Chair, and Councillor Evans is appointed as Vice Chair for this... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies