Agreed – (1) that the Directors address the remaining shortfall in 2010/11; (2) that the latest 2010/11 capital forecast of £77.457m is noted and the City Council is Recommended to approve that the following new schemes (included in the latest forecast) are added to the programme for 2010/11 - (a) Jennycliff Café environmental works £0.050m; (b) Market electrical refurbishment (majority to follow in 11/12) £0.025m; (3) the reinstatement of the Weston Mill cemetery reserve, by a transfer back from the revenue invest to save reserve, totaling £0.071m, to meet the costs of essential improvement works in 2010/11; (4) the budget virements as follows - ? reallocation of development budget savings across service heads - £466,000; ? separation of Chief Executive departmental management from Policy and Performance Unit for reporting purposes - £512,000; ? transfer of budget for Community Support Grant scheme from corporate items to Corporate Support - £100,000
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
This report outlines the performance and finance monitoring position of the Council as at the end of the third quarter, December 2010 (to 20th January 2011 for capital).
The primary purpose of this report is to detail how the Council is delivering against its key performance indicators in terms of performance, and its financial measures using its capital and revenue resources. It is deliberately strategic in focussing on key areas of performance, expenditure, and risk, and includes under each Departmental Business section a scorecard, incorporating a summary of performance.
At this stage, the Council is forecasting a revenue overspend at year end of £1.964m a reduction on that reported in the September monitoring report (September quarter reported an overspend of £3.342m) against a net revenue budget of £201.825m (1%). The main variations relate to
• Children’s Services £1.725m: The department continues to experience continuing pressures on the looked after children budget due to increased numbers compared to budget in the Independent Sector Placements in residential Care and in Foster Care. Further modelling of the numbers of children is taking place to predict when diversion from care strategies will bring spend back to budget in order to ensure intervention is targeted in the right areas. Safeguarding is however, paramount. There is also a forecast increase in the cost of transporting children with complex needs, and officers are currently reviewing the children’s transport policy and will present options to Cabinet at a future meeting.
• Community Services £0.511m: The main reason for the overspend in community services is due to continuing pressures in Learning Disability services relating to long stay residential services and supported living, and an increase in short stay residential and nursing care. The transformation agenda continues to shape the future of adult social care services in Plymouth. In terms of environmental services an ageing fleet of specialist vehicles has led to an increase in repair costs and increases in subsequent vehicle hire costs. The department is working with external consultants to reclaim a landfill tax rebate which will help to reduce the forecast overspend. It is hoped this will be received in the current year.
• Development £0.111m: The department is facing an increased cost pressure of winter highway maintenance following the adverse weather conditions at the end of last year, and increased costs in respect of the waste management project team due to the acceleration of the project.
Directors continue to take action wherever possible to reduce spend and it is anticipated that the overspend will further reduce by year end.
The latest approved Capital Programme for the year as approved by Full Council in December 2010 is £92.179m. This is now forecast to reduce to £77.457m by year end due to reprofiling and other movements on the programme. Actual spend to date (20th January 2011) is £48.863m. New schemes totalling £0.075m are to be referred to full Council for inclusion on the programme.
The provisional Grant Settlement for 2011/12 was received on 13 December 2010. The result is a significant reduction in funding over the next two years. The Corporate Management Team is working with the Cabinet to develop a transformational change programme that fundamentally challenges the organisation’s culture, structure and approach to service delivery. Further details are outlined in the 2011/12 budget reports.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.