Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on Thursday 16 December 2010 are confirmed as a correct record.
South West Devon Waste Partnership agreed this item on Thursday 7 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on Thursday 16 December 2010 are confirmed as a correct record.
South West Devon Waste Partnership Thursday 16 December 2010
PRESENT:
Councillor Butt, in the Chair. Councillor Michael Leaves, Vice Chair. Councillors Bowyer, Croad and Hart.
Observer Members: Councillor Doggett and Vincent.
Apologies for absence: Councillor Carroll.
Also in attendance: Barry Keel, Chair of Project Executive; Mark Turner, Project Director; Martin Pollard, Project Manager; Ben Jennings, County Waste Manager, Devon County Council; Ian Harrison, Deputy Executive Director of Environment, Economy and Culture, Devon County Council; Sally Farley, Service Manager, Torbay Council; Charles Uzzell, Environment Commissioner, Torbay Council; Dominic Measures, Devon Audit Partnership; Liz Waugh, Communications Consultant; Rachel Galbraith, PFI Project Co-ordinator; Ross Johnston, Democratic Support Officer.
The meeting started at 2pm and finished at 4pm.
Note: At a future meeting, the committee will consider the accuracy of these draft minutes, so they may be subject to change. Please check the minutes of that meeting to confirm whether these minutes have been amended.
27. INTRODUCTIONS AND APOLOGIES
Councillor Dave Butt welcomed members to the meeting.
28. DECLARATIONS OF INTEREST
There were no declarations of interest.
29. MINUTES
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on Thursday 28 October 2010 are confirmed as a correct record.
30. CHAIR'S URGENT BUSINESS
OPTION SEVEN UPDATE
Ben Jennings, County Waste Manager gave a presentation on Option 7 as requested at the Partnership’s meeting held on 28 October 2010. Members were informed that –
South West Devon Waste Partnership Thursday 16 December 2010 (a) Option 7 was an alternative solution based on the Energy Park proposal by Peterborough Renewable Energy Ltd and had been suggested as an alternative solution to energy from waste by the local opposition group called Devon Alliance for Incineration Alternatives (DAIA);
(b) the Peterborough proposal was not yet in construction and its exact configuration was not yet finalised. It was primarily a biomass energy generation facility, where biomass (coppicing, waste wood and farm residues) was to be combusted to produce electricity;
(c) the claimed benefits of the Option 7 proposal included –
• Cleaner: plasma vitrification, the process used in Option 7, treated all bottom and fly ash and provided a cleaner inert aggregate than a mass burn incinerator. This process could be used in conventional energy from waste but it did have a very large energy demand;
• Cleaner: Nitrogren Oxide emissions were reduced from plasma vitrificaton;
• Greener: It should allow slightly more material to be recovered but would require wholesale changes to current collection arrangements if used by the Partnership;
• Cheaper: No evidence to substantiate this claim;
(d) the Peterborough proposal was a thermal combustion energy generating plant and not a waste treatment facility although it had many similarities to a conventional energy from waste in terms of involving combustion, emissions, controls, compliance, etc. It needed a very large site to operate economically. Plasma vitrification was an unproven process that was not used on a large scale at present in the UK, in contrast the Partnership was opting to use a process, which was proven and reliable;
(e) Peterborough Renewable Energy Ltd had not registered an interest in bidding for the Peterborough Council residual waste contract;
(f) SUST-N, a local company in Devon, were undertaking a feasibility study of using biomass in a commercial business in the future.
The Chair thanked Ben Jennings, Project Officer for his presentation.
Agreed that a copy of the presentation be emailed to all members
South West Devon Waste Partnership Thursday 16 December 2010 31. PROJECT UPDATE
The Partnership received a Project Update Report from the Project Director. Members were informed that –
(a) the Call for Final Tenders were received by the Partnership on 5 November 2010;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 93 KB | DownloadRead as text |
Follow South West Devon Waste Partnership at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2022 | Contract and facility performance and current statusAgreed contract change to reduce printing weighbridge tickets; m) There had been a lighting review for LED exchange; ... | Agreed | Open |
| 18 Nov 2021 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Roger Croad is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Mark Cocker is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Date and location of next meetingAgreed - 21 October 2021 as the date of the next meeting. | Agreed | Open |
| 17 Oct 2019 | Appointment of Chair and Vice ChairAgreed that in accordance with the Joint Working Agreement Schedule C clause 4 – (1) Councillor David Thomas is appoi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.