Agreed that – 1. Cabinet approve variations, virements and reprofiling between years of the MTFF , and seek approval from Council for the 5 year capital programme amended for new approvals, shown below: 2011/12 2012/13 2013/14 2014/15 Total £000 £000 £000 £000 £000 Capital Budget Approved at Full Council Feb 2011 85,201 18,488 5,660 5,829 115,178 Additional Schemes Approved at Full Council April 2011 4,174 1,114 677 337 6,302 Capital Budget Approved at Full Council April 2011 89,375 19,602 6,337 6,166 121,480 0 0 0 0 Impact of Closedown 2010/11 – Year End Reprofiling 8,841 0 0 0 8,841 Changes to Variations, Virements and Reprofiling (see appendix G) (2502) 2,345 448 0 291 New Approvals (see below) 1,597 0 1,021 0 2,618 0 0 0 0 Revised Capital MTFF to be Approved 97,311 21,947 7,806 6,166 133,230
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
This report represents the final performance and financial monitoring report for 2010/11 showing the final position for the year, outlining key issues that have arisen during the year with particular focus given to the variations in the final quarter.
Performance Some of the more significant performance issues during the year outlined in the report include: • Key safeguarding measures are performing strongly due to focused management action. • Significant improvements in educational attainment across early years foundation stage as well as a further narrowing of the gap for pupils achieving 5 A*-C (GCSE) in English and Maths. • Action to reduce waste and increase recycling included increased processing capacity; expansion of the garden waste scheme; expansion of recycling to some multi occupancy properties, and the introduction of new recycling schemes (e.g. low energy light bulbs and batteries) • Support for carers which exceeded the target for the year.
Revenue The final position for the year, assuming the transfers to and from reserves as proposed in the report are approved, is net spend of £201.930m giving a deficit of £0.105m. As is normal practice, this report proposes a number of adjustments to the financial accounts following the final financial health review always undertaken by the Section 151 Officer at the end of the year. Decisions made as part of this report will feed into the Council’s annual Statement of Accounts which is subject to external audit. Should all proposals be approved, there will be a requirement for a transfer from the Working Balance, leaving a net working balance of £11.412m at 31 March 2011, which represents 5.5% of the net revenue budget for 2011/12. The Medium Term Financial Strategy is to maintain a Working Balance of at least 5% net revenue spend.
Previous reports had indicated a potential overspend for the year due in particular to budget pressures in both children’s services and community services. Due to extensive management action across all departments to stop or minimise spend wherever possible the overspend was virtually avoided. Whilst this is good news, many of the final savings in the last quarter were one- off and will not therefore necessarily reduce the underlying pressures faced by departments in future years.
Capital The Council achieved spend of £69.718m against the revised capital programme of £77.457m as approved in January 2011, which equates to 90%. A sum of £0.318m will be transferred to revenue to meet accounting standards on capital expenditure, and a corresponding transfer of grant or reduction in revenue contributions for the year will be made to ensure there is no impact on the revenue budget.
The Council continues to face a series of challenging issues into the medium term. The impact of the in-year 2010/11 grant funding reductions plus the reduced funding for 2011/12 and beyond means the Council have to have robust plans if it is to continue to improve.
Our result for 2010/11 shows the Council has come very close to achieving the very challenging budget. There must not be complacency as the Council moves into 2011/12. To achieve the budget in the coming year all departments must achieve their declared Delivery Plans, which amount to £13.3m.
Corporate Plan 2011-2014:
Monitoring of the Council’s performance and financial position during the year is fundamentally linked to delivering the corporate improvement priorities within Council’s corporate plan.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.