Application GRANTED conditionally subject to an additional condition that noise generated by the generator measured at the nearest residential property shall not exceed 5dBA above background noise levels, in accordance with policy CS34 of the Core Strategy.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
The main part of this state of the art research facility is the large wave tank. In developing this, it became apparent that in order to manage moisture levels above the tank it would be necessary to have an Air Handling Unit (AHU) larger than originally envisaged. The increased size would have made it difficult to accommodate the AHU internally and would have resulted in a significant loss of valuable space above the tank. Therefore, it is for this reason that the University now seek to locate a larger AHU externally.
The University consider that a solution has now been reached which is satisfactory to colleagues in Urban Design and the Public Protection Service. The purpose of the letter is to emphasise that whilst the requirement for the larger size AHU only became apparent in the detailed development of the design, both its size and its proposed location are critically important to the main objective of this project, namely to provide a world class research facility in Plymouth, stimulating economic activity and generating jobs.
The recommendation on the application remains as in the main report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.