Growth and Prosperity Overview and Scrutiny Panel agreed this item on Monday 11 July 2011. Below is the council's own wording, with the papers it was decided on.
Agreed that – 1 major works to be communicated in advance to Members by Ward; 2 Members support officers initiative to seek 12 months notice for major works on the road network; 3 the panel recommend that officers pursue national leverage with other local authorities to extend notice and to achieve greater power to veto.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Report to Growth and Prosperity Overview and Scrutiny Panel
Executive summary
Introduction
Statutory Undertakers provide an essential service delivering and maintaining some of the most important infrastructure for the City, including electricity, gas, water and telecommunications. The majority of these make substantial use of the street for their distribution networks. The New Roads and Street Works Act 1991 (NRSWA), as revised by the Traffic Management Act 2004, provides the regulatory framework for the council to coordinate, approve and direct works effectively with the aim of minimising disruption.
The Authority has a duty to plan and co-ordinate works and events on the highway network, however, Utility Companies have statutory powers to carry out emergency works on the network at any time.
Noticing of works
Under NRSWA, statutory undertakers must notify the council of their planned works on the public highway. The period of notice that must be given before such works can commence, depends on the magnitude, nature and location of individual schemes:
§ Major works – 3 months § Standard works – 10 days § Minor works – 3 days § Immediate works (Urgent) – within 2 hours of works starting § Immediate works (Emergencies) - no later than 2 hours after work has begun.
Whilst the majority of street works are undertaken with little or no disturbance to the public, the council liaises with utility companies to discuss and agree the details of works with the potential to cause significant disruption. This will include agreeing working times and traffic management plans, e.g. a detailed understanding of the use of road/lane closures, and the use temporary traffic lights. Street Works Register
Under section 53 of NRSWA street authorities are required to maintain a register for every street for which they are responsible. The council operates an electronic street works register, Confirm Streetworks, which provides a single source of information relating to on-going and planned works on the public highway.
The Confirm Streetworks system also serves as the authority’s Notice management system, allowing the electronic receipt of street works notices from Statutory Undertakers in accordance with the national protocol for the Electronic Transfer of Notices (EToN). Once works are notified, the Streetworks Register provides the facility for the council to report on, and to coordinate all future and planned works.
Coordination Meetings
The council meets quarterly with Statutory Undertakers and neighbouring authorities in HAUC (Highway Authority and Utility Companies) meetings and JAGSW (Joint Authorities Group for the South West) to identify where programme clashes may occur, where works are scheduled within Traffic Sensitive Streets, and take appropriate action. This may mean imposing working hours restrictions or directing the utility companies to change their schedules. The meetings also enable the Council to discuss the duration of individual works, challenge these where appropriate, and also to discuss the Council’s own works programmes.
In some cases it is necessary for the authority to coordinate with Statutory Undertakers on a one-to- one basis. This might occur where an Undertaker is planning large scale maintenance works affecting a wider area over a longer time period, e.g. water mains rehabilitation works. Such meetings give the authority a chance to discuss and agree with the works promoter the timing of the works and the traffic management arrangements.
Weekly Road Report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth and Prosperity Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.