HIGHWAYS MAINTENANCE TASK AND FINISH GROUP PROGRESS REPORT
AgreedScrutiny1 paper
Growth and Prosperity Overview and Scrutiny Panel agreed this item on Monday 11 July 2011. Below is the council's own wording, with the papers it was decided on.
Agreed that – 1 a f urther update on the Invest to Save BID and Service Levels would be brought to the panel for discussion in October 2011. 2 officers would speak with the Street Cleansing department regarding gulley cleansing regimes; Under this item the panel agreed that the task and finish group work was an excellent piece of scrutiny and welcomed officers comments regarding the road network repairs that would deliver positive results for the public.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Report to Growth and Prosperity Overview and Scrutiny Panel
Executive summary
Following on from the Growth & Prosperity Scrutiny Panel’s Review of Highways Maintenance in November/December 2010, a report was submitted to Cabinet on the 19th January 2011recommending that further work be undertaken by officers to identify what, if any, of the Scrutiny recommendations would be appropriate to take forward. This report details the actions taken since that report. The recommendations and progress to date are as follows:
1) that the Transport and Highways Partnership review service levels in relation to highways maintenance to improve value for money.
Tranport and Highways is currently working closely with the council’s Risk and Insurance team and its solicitors to review draft proposals to change the existing highways maintenance service levels. Current proposals include altering defect response times and the frequency of highway inspections in order to undertake more permanent repairs, both first time and overall, thereby improving value for money.
Such changes may make it harder or impossible to defend claims unless a well reasoned argument can be made to depart from the Code of Practice “Well Maintained Highways”. Consequently, officers are undertaking a more detailed risk assessment of the proposals, incorporating a review of detailed statistical evidence, i.e. traffic flows, insurance claims, defects etc., to ensure that they are defensible and well considered.
It is anticipated that a final proposal, will be presented to Cabinet later this financial year.
2) that highways maintenance be assured of greater emphasis within the transport and highways capital programme alongside new works, but not at the expense of other areas of prioritised work;
Local Transport Plan (LTP) capital expenditure on carriageway resurfacing and reconstruction has been increased from £1.187m in 2010/11to £1.820m in 2011/12. These works are currently in progress as part of the Operation Upgrade campaign.
In addition to the capital expenditure, a further £610,800 revenue funding has been allocated to permanent patching works. Of this, £432,000 has been received from the Department for Transport as part of its £200m allocation to local authorities to repair roads damaged by the recent harsh winter.
Consequently, total carriageway revenue and capital funding has been increased by £980,000 on 2010/11 budgets.
3) that an Invest to Save Bid be submitted by officers to successfully secure additional capital funding;
An Invest to Save Bid, based on reducing footway defects, is currently being considered and, subject to developing a viable business case, is likely to be submitted by the end of September 2011.
It is the hope that by making positive in-roads in to the footway maintenance back-log, the council’s insurance premiums, and by extension, the Transport and Highways’ insurance contributions may be significantly reduced over time. This should enable footway revenue funding to be diverted into carriageway repairs.
4) that despite the current difficult economic climate and the budget position of the authority, the council should consider giving a higher priority to highway maintenance needs over and above other priorities included in the Council’s Capital Programme;
Currently the Council’s Capital Programme is fully committed but the Highways team will continue to work with the Capital Delivery Board to seek additional funding in particular from external funders, e.g. commuted sums from developers and Section 106 funding.
5) that the Council’s Insurance Reserve be reviewed to identify whether an element could be diverted to planned preventative term maintenance instead;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth and Prosperity Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.