Agreed to – 1. approve the introduction of a Community Infrastructure Levy for Plymouth, which once adopted will replace the Council’s tariff based approach as the primary means by which pooled contributions are secured to mitigate the impacts of development; 2. delegate authority to the Assistant Director for Development and Regeneration (Planning Services), in consultation with the Cabinet Member for Planning, Strategic Housing and Economic Development, to prepare a Preliminary Draft Community Infrastructure Charging Schedule in consultation with appropriate stakeholders (including the Cabinet Member for Transport and Assistant Director for Finance, Assets and Efficiencies); 3. instruct officers to report the Draft Community Infrastructure Levy Charging Schedule to Cabinet following engagement with stakeholders on the Preliminary Draft; 4. approve the publication of the Plymouth Infrastructure Needs Assessment as an evidence base document, and delegate authority to the Cabinet Member for Planning, Strategic Housing and Economic Development to approve the publication of updates to the Infrastructure Needs Assessment in a periodic basis, in consultation with appropriate stakeholders; 5. instruct officers to report back to a future meeting of Cabinet with proposals for using a meaningful proportion of CIL within the neighbourhoods in which it is raised. This recommendation was proposed by Councillor Pengelly and seconded by Councillor Michael Leaves.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
The report sets out the programme for moving to a Community Infrastructure Levy (CIL) scheme for Plymouth, including approval of an Infrastructure Needs Assessment as a key evidence base in support of CIL and wider resource planning and prioritisation, and seeks approval for a process of community and stakeholder engagement.
CIL is a new levy that local authorities in England and Wales can choose to charge on new developments in their area to help fund infrastructure improvement. It was first introduced by the previous Government in April 2010, but is now a major plank of the current Government’s localism agenda, with provisions identified in the Localism Bill.
Regulations adopted in April 2010 determine that, post-April 2014, CIL will be the only significant means by which local planning authorities can secure pooled contributions from developments to address infrastructure needs. These same Regulations also limit the extent that the Council can secure such contributions through planning obligations now. It is therefore in the Council’s interests to move towards adopting a CIL regime at the earliest possible opportunity.
The money raised through CIL can be used to support new development by funding infrastructure that the city, local communities and neighbourhoods need - for example new road schemes, park improvements or improvements to local school capacity. The system is relatively simple and can be applied to most new buildings. It will be for the Council to determine, and publish, how it intends to use CIL.
The Government encourages local authorities to introduce CIL because it:
• Delivers funding for infrastructure projects that support growth and benefit the local community that might not otherwise be forthcoming from other sources. • Gives local authorities increased flexibility and freedom to set priorities - as well as a predictable funding stream that allows them to plan ahead more effectively.
• Provides developers with much more certainty 'up front' about how much money they will be expected to contribute to mitigate the impacts of their developments, which in turn encourages greater confidence and higher levels of inward investment.
• Ensures greater transparency for local people, because they will be able to understand how new development is contributing to their community.
• Enables local authorities to allocate a share of the levy raised in a neighbourhood to deliver infrastructure that the neighbourhood wants (the Government has stated that it intends to consult on and subsequently further amend the CIL Regulations to ensure that a ‘meaningful proportion’ of CIL receipts are allocated to neighbourhoods).
A CIL Charging Schedule needs to be put in place in order to secure developer contributions in this way. Charges can be based on the size, type and / or location of the new development.
Councils must set the levy or levies in the Charging Schedule at a level which does not put at serious risk the overall development of their area, and so evidence on development viability must underpin the level that the levy is set.
Charging authorities must also draw on infrastructure planning that underpins the development strategy for their area, and there needs to be demonstrable evidence of a funding gap in relation to the delivery of infrastructure in order to justify introducing CIL. The Council therefore needs to put in place an Infrastructure Needs Assessment (INA) to enable it to adopt a CIL. Plymouth’s Draft Infrastructure Needs Assessment is attached as the Appendix to this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.