Agreed that – (1) the plans to deliver a kerb side glass recycling service across the city by April 2014 are endorsed, subject to a further report and Council approval of the change to the capital programme ; (2) it is noted that officers will conduct a soft market testing for the options around a replacement Materials Recycling Facility; (3) the plans to deliver a pilot operation for kerb side glass collection by September 2012, are approved; (4) approval is given to the plans to extend garden waste collection on a trial basis for November 2011 and to extend the service coverage for the remaining 19,500 properties in the city, by April 2012, that have gardens; (5) approval is given to the Environmental Services Programme Governance Terms of Reference (Appendix 3) and delegation of authority as set out at Appendix 3 paragraph 4.3 to the officer who is the Chair of the Executive Group to allow the programme to progress at the required pace, in order to meet the timetable outlined in the report; (6) it is noted that the Executive Group for the programme will commission and deliver a communication plan for customers and media to support the implementation of these changes.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
This paper makes a series of recommendations to improve the recycling and waste collection performance for the Council. The most significant change proposed is to collect glass within the existing green bins for all customers in the city. This change is estimated to add 4% to the recycling rate and is consistent with our obligations in securing the waste PFI and our contract with MVV. The paper also proposes the introduction of a pilot glass recycling scheme for one of the existing collections rounds (round 6) by September 2012, in order to allow the Council to learn how best to provide the service.
Additional changes are also proposed to the garden waste collection service. This scheme will be extended to include November 2011 as a trial to determine the tonnage of garden waste collected at this time of year. The scheme will also be expanded to cover the remaining properties in the city with gardens by April 2012. Hereafter all new properties with gardens in the city will also receive this service.
The paper also recommends some changes to the way vehicles supporting the service are paid for, so that the overall costs can be reduced and the service reliability can be maintained.
Additionally the paper recommends a review of the depots used by the Council across the city once the Energy from Waste planning decision is made. At this point it may be possible to re align resources providing services to the city and realise a capital receipt from any space freed up.
Finally the paper proposes the establishment of a programme to deliver these changes overseen by an Executive Group, including Member representation, with appropriate delegated authority.
Corporate Plan 2011-2014:
The recommendations made in this report compliment existing initiatives such as Energy from Waste to provide comprehensive, innovative and efficient waste collection and disposal for the city. The ambition of these changes is consistent with the City and Council priority to raise aspiration and supports the priority to provide value for the communities. The key performance metrics this work will support are the recycling rate, with an estimated increase overall of nearly 4.5%. In addition this work will maintain the currently high customer satisfaction levels (72% report being highly or fairly satisfied) with the waste collection service.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Subject to approval this paper commits resources to the delivery of a pilot for glass recycling and implementing the garden waste extension and expansion. A summary of the additional (not currently budgeted) costs associated with these changes is shown below (the cost of glass recycling is considered commercially sensitive and is therefore included under Part 2):
FY 11/12 FY 12/13 FY 13/14 Rev Capital Rev Capital Rev Capital Garden Waste Expansion £83,000 £84,000 £84,000
Totals £83,000 £84,000 £84,000
Costs included under Part 2 is by virtue of Categories 3(a) and (d) of paragraph 10.4 of Part 5 of Plymouth City Council's Constitution.
The successful implementation of this scheme will add to the financial pressures the Council are facing, with an on-going budget pressure of £84k each year. This will have implications in terms of additional delivery plans which will need to be developed to off-set these extra costs in order to keep the Council's budget in balance. These additional plans will be considered at CMT and reported back in the next Joint Performance and Finance Report for quarter ending September 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.