Resolved
Agreed to award a three year contract, containing an option to extend the contract for a further three years, to the ‘most economically advantageous tenderer ’ as identified in the contract award report.
Cabinet agreed this item on Thursday 12 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to award a three year contract, containing an option to extend the contract for a further three years, to the ‘most economically advantageous tenderer ’ as identified in the contract award report.
This report summarises the recent tender process for a remodelled Advice and Information Service and recommends award of the contract to a single provider.
Advice and information is a key part of Plymouth City Council and NHS Plymouth's universal service offer. Our vision is to ensure that everybody in Plymouth can access consistent and high quality advice and information when they need it. In addition it is recognised that targeted enhanced service provision based on need in priority neighbourhoods and communities is also required.
Plymouth City Council’s current advice and information contracts are due to end on 30 September 2012. The level of projected expenditure on the future remodeled service to replace this provision required a full competitive tender in accordance with the Council’s Contract Standing Orders. This competitive procurement was run as a one stage process.
The new service will meet the health, social care, wellbeing and financial inclusion advice and information needs of the people of Plymouth. As well as being universally accessible it is recognised that the service will be required to target work where the need is greatest.
The contract award report is submitted to Cabinet as a separate confidential report.
Corporate Plan 2012 – 2015:
Reduce Inequality – by targeting advice and information where it is most needed on issues such as financial inclusion, health & wellbeing, social care, employment.
Provide Value for Communities – by selecting the most economically advantageous tender, by supporting the use of volunteers, by engaging local communities, and by remodelling provision to be consistent and high quality
Deliver Growth – by providing advice and information on financial inclusion and employment / job seeking
Revised Jun 2012 Raise Aspiration – by ensuring people in Plymouth are well informed about opportunities / services
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
The annual contract value of the new service will realise annual savings of approximately £82,833 per year for the length of the contract.
Other Implications: e.g. Child Poverty, Community Safety, Health and Safety, Risk Management and Equality, Diversity and Community Cohesion:
Child Poverty: a focus of the service will be to provide advice and information on financial inclusion which will impact positively on child poverty.
An Equality Impact Assessment has been completed. No adverse impact was identified as a result of this however contract monitoring arrangements will continue to assess any impacts post contract award.
Recommendations & Reasons for recommended action:
To award a three year contract, containing an option to extend the contract for a further three years, to the ‘most economically advantageous tenderer’ as identified in the Contract Award Report.
Alternative options considered and reasons for recommended action:
The option of not awarding any contract was considered but disregarded due to the importance of ensuring advice and information services are available to the people of Plymouth.
Background papers: http://www.plymouth.gov.uk/eia_adviceinformationasc.pdf
Sign off:
Fin People Leg 1490 HR N/A Corp N/A IT N/A Strat JK- FAC121 8/ Prop Proc 281 3 001- ALT TOCS Originating SMT Member: Pam Marsden Have you consulted the Cabinet Member(s) named on the report? Yes
Revised Jun 2012
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CONTRACT AWARD: ADVICE AND INFORMATION SERVICEReport | 31 KB | DownloadRead as text |
Follow Cabinet at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... | Approved | Open |
| 14 Sep 2026 | Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... | Approved | Open |
| 24 Aug 2026 | Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... | Approved | Open |
| 24 Aug 2026 | Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... | Decided | Open |
| 24 Aug 2026 | SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.