Growth and Prosperity Overview and Scrutiny Panel agreed this item on Wednesday 19 September 2012. Below is the council's own wording, with the papers it was decided on.
Agreed that – (1) Ian Ellis would provide a briefing report on the maintenance of cycle routes to all panel members via email; (2) Ian Ellis would email to all panel members a copy of the Winter Service Plan and the most recent priority list for road maintenance.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Report to Growth and Prosperity Overview and Scrutiny Panel
GROWTH AND PROSPERITY OSP Highway Maintenance Update
v1.0 4 September 2012 Not protectively marked 1 Introduction
Following on from the Growth and Prosperity Scrutiny Panel’s review of Highway maintenance in November/December 2010, progress reports were submitted to the Panel on 11th July 2011 and 17th October 2011. This report details the actions taken since that report.
2 Scrutiny recommendations
The recommendations and progress to date are as follows:
1) that the Transport and Highways Partnership review service levels in relation to highways maintenance to improve value for money.
The service levels for highway maintenance are dictated by the Code of Practice for Highway Maintenance Management; this recommends the intervention levels for safety defects, response times for repairing defects and the methodology for defining inspection frequencies.
Any variation from the Code of Practice could jeopardise the Authority’s defence when dealing with third party accident claims against the council; consequently, the work undertaken to date in reviewing levels of service has been undertaken in a logical, structured way in order that potential risks can be properly considered.
For the initial stage of the review, Plymouth City Council commissioned Amey to provide a report on the reasons for highway claims against the Council. The report was completed in March 2012, and made numerous recommendations to improve the way in which inspections, reporting and repairs could be undertaken to better defend against highway accident claims.
Following on from this initial piece of work, and following legal advice, a review has been undertaken of the Council’s existing Safety Inspection Policy to ensure that it is sufficiently robust to defend against claims. The review has considered the current inspection regime and has identified changes that better aligns to the Code of Practice and adopts a new road hierarchy. This has been undertaken in partnership with the Council’s Risk and Insurance team, and is due to be submitted to Cabinet for approval in November 2012.
Finally, a further piece of work is due to be commissioned that will consider options and recommendations for changes to defect response times to enable repairs to be dealt with more efficiently. It is proposed that changes will be considered and risk assessed against the new proposed road hierarchy. Consideration will also be given to alternative repair techniques.
2) that highways maintenance be assured of greater emphasis within the transport and highways capital programme alongside new works, but not at the expense of other areas of prioritised work;
Local Transport Plan (LTP) capital expenditure on carriageway resurfacing and reconstruction was increased from £1.187m in 2010/11to £1.820m in 2011/12. This budget was used to progress the Operation Upgrade campaign.
GROWTH AND PROSPERITY OSP Page 2 of 3 An additional £1.3m was made available in October 2011 for carriageway resurfacing. This funded additional works under the Operation Upgrade banner in the 2011/12 financial year, although £161,000 has been carried forward to 2012/13.
For 2012/13 the Local Transport Plan (LTP) the total capital allocation for carriageway resurfacing and reconstruction is £750,000 in the addition to the £161,000 carried forward from 2011/12. Additionally, £257,000 has been allocated to footway resurfacing. The reduction on last year’s capital allocation reflects the need to fund other priorities within the 2012/13 transport capital programme, including the maintenance works for Laira Bridge.
3) that an Invest to Save Bid be submitted by officers to successfully secure additional capital funding;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth and Prosperity Overview and Scrutiny Panel at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.