Agreed – (1) that the capital programme is amended to include the Royal William Yard coast path link project; (2) that a grant is accepted from Natural England to the value of £237,000 to enable delivery of the coast path link; (3) that the new staircase and section of the South-West Coast Path is included onto the Council’s asset register and officers are instructed to add this asset to the existing lease agreement between Plymouth City Council and Urban Splash; (4) the procurement strategy for delivering the projects and to delegate authority to the Assistant Director for Place, in consultation with the Portfolio Holder for Environment, to agree the contracts.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Plymouth City Council has been offered a grant of £237,000 by Natural England to facilitate the delivery of a project to re-route the South West Coast Path (SWCP) through Devil's Point Park to connect this area to the nationally important Grade I Listed Royal William Yard (RWY). Delivering the important link between RWY and the Park will involve constructing a stairway into the Yard that will enable the SWCP to be connected all the way around the peninsula on which the Park and the RWY are situated. Providing this complete route around the peninsula will deliver a long held aspiration to connect these two popular features, enable communities to be directly linked to the attractions within RWY and enable greater use of the Park.
Constructing the staircase and re-routing the SWCP around the headland will enable better use of the outstanding natural and historical assets of both the Park and the Yard and promote the economic and cultural vitality of the area. It will also provide a stunning new visitor attraction for the SWCP that will enhance the visitor experience within this part of Plymouth. The multiple benefits that would result from the delivery of the project are the reason that Natural England have offered to fund the works as part of their role to improve and promote a network of National Trails. The excellent working relationship developed with Natural England as part of the Plymouth Green Infrastructure Project has helped to secure the funding for Plymouth rather than it being spent in other areas of the country.
The funding would be provided by Natural England as a grant payable on delivery of the project and the access link must be in place by the end of this financial year. This places a very challenging time scale on the delivery of the works.
To enable the project to be completed within the specified time scales it is proposed that we utilise Urban Splash as a contractor to deliver the works. Urban Splash has already secured planning permission and listed building consent for the coast path link and has produced design work for the project. As the developers of the RWY and having previously developed the proposals for the access link, Urban Splash are in a unique position to support delivery of the works. They are also very supportive of the proposal as it would open up a new route into the Yard and enable them to support the local community’s aspirations for the area.
Revised Jun 2012 As the full amount of funding needed to deliver the project is being provided by external sources the Council will not have to contribute financial to the project. The role the Council will play is to facilitate delivery of the project and manage the grant funding. Plymouth City Council would retain ownership of the new asset (the stairway and new section of coast path) but these features would be added to the existing lease the Council has with Urban Splash so they would be responsible for maintenance.
The delivery of this new access link would provide economic, social and environmental benefits and would deliver a long held aspiration of the local community. In the current situation the Council is the only organisation that can facilitate delivery of this exciting project. Corporate Plan 2012-2015:
This project directly supports the City Vision by enhancing the waterfront and enabling residents and visitors to have greater opportunities to access the exceptional natural and historic assets the area offers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.