Agreed, subject to approval of minute 7a below, to – (1) approve a tender exercise using a two stage design and build procurement process for the delivery of a £2.5m direct development commercial employment scheme at Langage to provide 2,787 square feet of high quality, sustainable accommodation facilitating or supporting up to 80 full time jobs; (2) delegate to the Cabinet Member for Finance the authority to make the key decision to award the building contract following the tender exercise.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Plymouth City Council is committed to promoting the growth of the local economy and the creative use of Council land and property assets to support employment. This report provides the exciting opportunity to actively promote the growth agenda and create / support up to 80 FTE jobs. This will be achieved by providing 2,787 sq m of sustainable high quality, speculative employment accommodation for small and medium-sized businesses on Council owned land at Langage Science Park, Plympton, Plymouth. The estimated cost of the project is £2.5 million and the completed and fully let development will also provide the Council with a valuable long term income stream and add to its existing commercial property portfolio.
A detailed demand and supply report has been completed (March 2013) by Jones Lang LaSalle which concluded that Plymouth has a shortage of high quality, modern employment space facilities. The cost value gap of the private sector delivering these much needed employment schemes has led to market failure to provide high quality employment accommodation in Plymouth. Therefore there is strong justification for the public sector to intervene and progress such schemes by direct development.
It is proposed that the development will incorporate sustainable technologies to minimise carbon emissions and running costs, potentially including the following: solar photovoltaic, increased levels of insulation, increased levels of natural daylight and ventilation and highly efficient heating systems.
Approval is now required to authorise the above expenditure and progress the procurement of the Main Contractor. It is proposed that this project be delivered using one of the Framework Contractors (through a mini tender competition) and that it is delivered via a two stage design and build tender process with full contractor design. The framework used will incorporate a local employment scheme to facilitate work placements and apprenticeships.
It is being recommended that Cabinet delegate their key decision to accept the tender to expedite efficient letting of the contract.
Revised Dec 2012 Corporate Plan 2012-2015:
Deliver Growth This project will directly contribute to this priority by providing a supply of high quality business space. It will facilitate job creation through the feasibility/construction phase and importantly through the provision of speculative workspace. Using Government Best Practice (1 job created per 35sq m) it is estimated that 80 full time jobs could be supported as a result of this investment (excluding the temporary construction jobs). These jobs will help contribute to and increase the GVA of the area.
In addition the project will unlock additional serviced development plots (a key target under Level 2) that could be delivered in the future by PCC, sold to owner occupiers or developers.
Raise Aspirations Currently the site is an undeveloped parcel of land which has been barricaded to prevent unsociable activities taking place. The delivery of new, high quality business space will assist in raising aspirations for existing, surrounding businesses and new businesses occupying the premises. By providing high quality facilities it will help contribute to greater business confidence, give people something to be proud of and embed civic pride.
The opportunity to occupy modern facilities will hopefully lead to more comfortable working environments for employees, which in turn will help raise aspirations and motivation.
Reduce Inequality The provision of high quality workspace built to modern standards will help reduce inequality by making the premises fully accessible.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.