Resolved
Agreed – (1) the revenue budget virements as set out on page 10 of the report ; (2) the new capital schemes indicated in table A totaling £0.881m.
Cabinet agreed this item on Tuesday 12 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed – (1) the revenue budget virements as set out on page 10 of the report ; (2) the new capital schemes indicated in table A totaling £0.881m.
This report is the second quarterly monitoring report for 2013/14 and outlines the finance monitoring position of the Council as at the end of September 2013.
The primary purpose of this report is to detail how the Council is delivering against its financial measures using its capital and revenue resources, and to approve relevant budget variations and virements, and the approval of new schemes to the capital programme.
The forecasted revenue overspend is £1.522m which is an improvement of £0.370m compared to the June 2013 report. The current estimated position shows an overspend of £1.114m in the People Directorate, an overspend of £0.464m in the Place Directorate, and an underspend of £(0.056)m in Corporate Items. This equates to a forecast net spend of £214.082m against a budget of £212.560m, which is a variance of 0.7%, although officers and members are working on actions to deliver a balanced outturn. As we have now reached the mid point in the year, red delivery plans have been incorporated in the revenue monitoring position.
The capital programme approved by Council in February 2013 covering 2013/14 to 2015/16 stood at £122.670m. Following approval of new schemes, re-profiling and variations, the capital programme increased to £159.903m as at the end of June 2013 (as reported in the quarter one monitoring report). The latest forecast at the end of September 2013, is £162.484m, which includes increases approved at Council in September, other delegated officer approvals, and assumes the approval of the recommendations for new schemes/scheme increases contained in this report.
The Brilliant Co-operative Council Corporate Plan 2013/14 -2016/17:
This quarterly report is fundamentally linked to delivering the priorities within the Council’s Corporate Plan. Allocating limited resources to key priorities will maximise the benefits to the residents of Plymouth.
1 Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Robust and accurate financial monitoring underpins the Council’s Medium Term Financial Plan. The Council’s Medium Term Financial Forecast is updated regularly based on on-going monitoring information, both on a local and national context.
Other Implications: e.g. Child Poverty, Community Safety, Health and Safety, Risk Management:
The reducing revenue and capital resources across the public sector has been identified as a key risk within our Strategic Risk register. The ability to deliver spending plans is paramount to ensuring the Council can achieve its objectives to be a Pioneering, Growing, Caring and Confident City.
Equality and Diversity:
Has an Equality Impact Assessment been undertaken: No
Recommendations & Reasons for recommended action:
That Cabinet:-
1. Note the revenue monitoring position and actions being taken
2. Approve the revenue budget virements as set out on page 10
3. Note the increase in the medium term capital programme forecast to £162.484m
4. Approve the new capital schemes indicated in table A totaling £0.881m and recommend to Council the increase to existing schemes totaling £0.627m
5. Note the Human Resources & Organisational Development Data
Alternative options considered and reasons for recommended action:
Actions are recommended in response to specific variances in finances identified throughout the report.
Published work / information:
2013/14 Budget Book Plymouth City Council – Budget Book 2013/14 Budget Scrutiny Plymouth City Council – Budget Scrutiny
None
Sign off:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CORPORATE MONITORING REPORT AS AT 30 SEPTEMBER 2013 (INCLUDING CAPITAL SCHEMES AND PROGRAMME APPROVALS)Report | 971 KB | DownloadRead as text |
Follow Cabinet at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... | Approved | Open |
| 14 Sep 2026 | Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... | Approved | Open |
| 24 Aug 2026 | Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... | Approved | Open |
| 24 Aug 2026 | Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... | Decided | Open |
| 24 Aug 2026 | SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.