Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on 24 October 2013 are confirmed as a correct record.
South West Devon Waste Partnership agreed this item on Thursday 24 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on 24 October 2013 are confirmed as a correct record.
Public Document Pack
South West Devon Waste Partnership Thursday 24 October 2013
PRESENT:
Councillor Thomas, in the Chair. Councillor Vincent, Vice Chair. Councillors Croad, Tyerman and Williams.
Observer Members: Councillors Doggett and Leaves.
Apologies for absence: Councillor Hart.
Also in attendance: Anthony Payne, Director for Place, David Whitton, Head of Capital Development and Waste Management (Devon County Council), Sally Farley, Service Manager (Torbay Council), Mark Turner, Project Director, Martin Pollard, Project Manager, Liz Waugh, Communications Consultant, Wendy Barratt, County Waste Manager (Devon County Council), Jenni Doudoulakis, PFI Co- ordinator, Ross Johnston and Lynn Young, Democratic Support Officers.
The meeting started at 10.00 am and finished at 11.00 am.
Note: At a future meeting, the committee will consider the accuracy of these draft minutes, so they may be subject to change. Please check the minutes of that meeting to confirm whether these minutes have been amended.
43. APPOINTMENT OF CHAIR AND VICE-CHAIR
Agreed that in accordance with the Joint Working Agreement Schedule C clause 4 –
(1) Councillor David Thomas is appointed as Chair until the first meeting of the Joint Committee after the 1 May 2014;
(2) Councillor Brian Vincent is appointed as Vice-Chair until the first meeting of the Joint Committee after the 1 May 2014.
Councillor Thomas, Chair thanked Councillor Croad, the outgoing Chair, for all his work during the previous 12 months.
44. DECLARATIONS OF INTEREST
There were no declarations of interest.
45. MINUTES
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on Thursday 25 April 2013 are confirmed as a correct record.
South West Devon Waste Partnership Thursday 24 October 2013 46. CHAIR'S URGENT BUSINESS
There were no items of Chair’s Urgent Business.
47. PROJECT UPDATE
The Partnership received a Project Update report from Mark Turner, Project director. Members were informed that since the last Committee –
(a) MVV had continued to progress with the design of the facility, which was being continually evolved and refined;
(b) MVV were working with the Partnership to develop the waste delivery IT systems and procedures including electronic number plate recognition, which would facilitate a swift turnaround for SWDWP vehicles entering and leaving the site;
(c) the detailed financial allocation mechanism between the partnership councils was being finalised;
(d) the recruitment process for a partnership Contract Manager had now started, and it was hoped that the successful candidate would be in post for the New Year;
(e) MVV operational staff were now being recruited. It was anticipated that there would be 33 operational staff and part of their training could include some time at an operational plant in Germany;
(f) MVV continually monitored progress against the planning and permit conditions and provided a regular update to the partnership;
(g) since April, MVV had four breaches of Planning conditions of exceeding the operating hours condition with the last one being on 3 July 2013;
(h) in the period Jul 2013 – Sept 2013 seven public complaints had been received by MVV – the main areas of concern were noise and the distribution of information letters;
(i) MVV had extended the area for their latest newsletter drop in September;
In response to members’ questions it was reported that -
(j) Jane Ford (Community Liaison Manager) responded to, or visited local residents who complained, as part of her role;
(k) the partnership Contract Manager (when appointed) post was envisaged for the duration of the contract, and would be the partnership representative and interface with MVV.
South West Devon Waste Partnership Thursday 24 October 2013 48. UPDATE OF MVV CONSTRUCTION PROGRAMME AND SITE ACTIVITIES
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESReports_pack | 77 KB | DownloadRead as text |
Follow South West Devon Waste Partnership at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2022 | Contract and facility performance and current statusAgreed contract change to reduce printing weighbridge tickets; m) There had been a lighting review for LED exchange; ... | Agreed | Open |
| 18 Nov 2021 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Roger Croad is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Mark Cocker is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Date and location of next meetingAgreed - 21 October 2021 as the date of the next meeting. | Agreed | Open |
| 17 Oct 2019 | Appointment of Chair and Vice ChairAgreed that in accordance with the Joint Working Agreement Schedule C clause 4 – (1) Councillor David Thomas is appoi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.