Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on 24 April 2014 are confirmed as a correct record.
South West Devon Waste Partnership agreed this item on Thursday 23 October 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on 24 April 2014 are confirmed as a correct record.
South West Devon Waste Partnership Thursday 24 April 2014
PRESENT:
Councillor Thomas, in the Chair. Councillor Vincent, Vice Chair. Councillors Croad, Doggett and Tyerman.
Observer Members: Councillor Doggett and Michael Leaves.
Apologies for absence: Councillors Brazil, Hart and Williams, Charles Uzzell.
Also in attendance: Barry Ashbee (SWDWP Contract Manager), Wendy Barratt (County Waste Manager, Devon County Council), Paul Carey (Managing Director MVV Environment Devonport Ltd), Sally Farley (Service Manager, Torbay Council), Jane Ford (MVV Community Liaison Manager), Rachel Galbraith (SWDWP Project Co-ordinator), Tracey Lee (Chief Executive, Plymouth City Council), Martin Pollard (SWDWP Project Manager), Chris Randall (Strategic Finance Manager), Mark Turner (SWDWP Project Director), Liz Waugh (Communications Consultant), David Whitton (Head of Capital Development and Waste Management, Devon County Council), Lynn Young (Democratic Support Officer).
The meeting started at 10.05 am and finished at 12 noon.
Note: At a future meeting, the committee will consider the accuracy of these draft minutes, so they may be subject to change. Please check the minutes of that meeting to confirm whether these minutes have been amended.
53. DECLARATIONS OF INTEREST
There were no declarations of interest in accordance with the code of conduct.
54. MINUTES
Agreed that the minutes of the meeting of the South West Devon Waste Partnership Joint Committee held on 24 October 2013 are confirmed as a correct record.
55. CHAIR'S URGENT BUSINESS
There were no items of Chair’s urgent business.
56. PROJECT UPDATE
The Partnership received a verbal project update report from Mark Turner, Project Director. Members were informed that since the last committee –
(a) work on the site was progressing well;
South West Devon Waste Partnership Thursday 24 April 2014 (b) Hot Commissioning was due to commence in late 2014;
(c) IT systems and interfaces were being developed;
(d) Barry Ashbee had been recruited as the Contract Manager and would take over the role of Authority Representative from Martin Pollard;
(e) Martin Pollard, Project Manager, was leaving the Council within the next three months to take up alternative employment.
The Chair thanked Mark Turner for his report.
Councillor Michael Leaves proposed a vote of thanks for Martin Pollard. This was seconded by Councillor Croad.
57. UPDATE OF MVV CONSTRUCTION PROGRAMME AND SITE ACTIVITIES
Martin Pollard, Project Manager, gave a presentation providing an update on MVV’s construction programme and site activities since October. Members were informed that since the last committee –
(a) construction activities continued on-site – the turbine had been installed and the boiler pressure test was successfully completed;
(b) MVV was holding to the reported six week delay;
(c) the start of Hot Commissioning was due in November 2014, with operational service due to commence in January 2015;
(d) in the period November 2013 – March 2014 there had been five planning condition contraventions involving exceeding site working hours. All were minor breeches and had been self-reported by MVV;
(e) a sub-station planning application for Goschen Yard had been approved;
(f) the following works had been completed or were ongoing –
• boiler interconnections; • cladding and roofing works; • steelwork remediation; • mechanical and electrical services; • reception hall slab had been completed • steel frame was being erected;
(g) MVV’s future activities included –
• steam cycle works to connect to turbine; • air cooled condenser installation;
South West Devon Waste Partnership Thursday 24 April 2014 • cladding and roofing; • fit out of offices and control room.
The Chair thanked Martin Pollard for his report.
58. OVERVIEW OF PROJECT COMMUNICATIONS
Liz Waugh, the Partnership’s Communication Consultant provided a verbal update on recent and upcoming communication activity. Members were informed that –
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 89 KB | DownloadRead as text |
Follow South West Devon Waste Partnership at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2022 | Contract and facility performance and current statusAgreed contract change to reduce printing weighbridge tickets; m) There had been a lighting review for LED exchange; ... | Agreed | Open |
| 18 Nov 2021 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Roger Croad is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Appointment of chair and vice chairAgreed that in accordance with the Joint Working Agreement Schedule: 1) Councillor Mark Cocker is appointed as Chair ... | Agreed | Open |
| 15 Oct 2020 | Date and location of next meetingAgreed - 21 October 2021 as the date of the next meeting. | Agreed | Open |
| 17 Oct 2019 | Appointment of Chair and Vice ChairAgreed that in accordance with the Joint Working Agreement Schedule C clause 4 – (1) Councillor David Thomas is appoi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.