Agreed - (1) to delegate to the Strategic Director for Place the negotiation, finalisation and signing of a legal agreement to transfer areas of South Yard (namely Areas 1 and 5) from the Secretary of State for Defence to the Council; (2) to authorise officers to prepare a ... view the full minutes text for item 102.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Appendix A – Site plans Appendix B – Sensitivity Analysis Appendix C – Equality Impact Assessment
Revised Jul 2013 Appendix A – Site Plans Figure A1 – A plan of South Yard showing areas considered City Deal transfer
Area 5 being considered for Area 1 being transfer to Plymouth City considered for Council as part of City Deal transfer to Plymouth City
Area 2 Retained by MoD
Area 4 Retained by MoD
Area 3 Retained by MoD HM Naval Base Devonport
South Yard
Area 4A Retained by MoD
Area 3A Retained by MoD
Revised Jul 2013 Figure A2 - proposed master-plan layout for transferred areas of South Yard
Revised Jul 2013 Figure A3 – potential employment estimated from proposed master-plan layout for transferred areas of South Yard
Revised Jul 2013 Appendix B – Sensitivity Analysis of Risks
City Deal – South Yard
Sensitivity of Assumptions
There are a great deal of assumptions included in the business case to come up with a viable proposition, that will not leave the PCC with a legacy of annual revenue costs and a capital payback of between 20-25 years.
The key risks and their financial implications are:
Risk No Description Values (excluding inflation) 1 Project Funding, further grants and capital 1. Capital costs never funding not available recovered 2. Revenue is wiped out and an annual cost of £225k per annum is r equired to operate the site – no payback 2 Cost of Construction, annual inflation of 6% 1. Capital costs increase by £2m. 2. Payback increases by 5 years 3 Construction delayed by 2 years eg through 1. Capital costs increase slow receipt of additional grants and loans by £3m. 2. Payback increases by 5 years 4 Private development of Area 5 does not 1. Lost revenue of £150k happen per annum. 2. Payback increases by 4 years 5a Rental income – reduced occupancy to 50% 1. Revenue is wiped out and an annual cost of £100k per annum is required to operate the site – no payback 5b Rental income – rental values 25% lower than 1. Annual income reduced expected by £250k per annum 2. Payback increases by 26 years. 6 Operating costs underestimated by 25% 1. Annual income reduces by £265k 2. Payback increases by 21 years
1. Project Funding In addition to the loans, grants and capital injection so far offered (£20m), there are assumptions of further inward investment: Additional grant funding of £25m Additional PCC capital of £5m Revised Jul 2013 Risk 1. There will be no further grant or other capital funding available. This would mean there is only enough funds available to prepare area1 East and West Sites, and Build 3 buildings on Area 1 East. The PCC would therefore have to seek developers to develop the buildings in Area 1 West and complete Area 1 East, instead of the PCC building them (which will generate rental revenue). Without additional funding there will be insufficient funding available to prepare Area 5 for development. If this scenario developed then Area 5 site and plans would need to be mothballed and MoD security gates revised to avoid their ongoing revenue security costs. 2. If grant funding was reduced by £5m and capital funding increased by £5m, then the payback increases to 40 years.
Cost Implication The capital costs would never pay back, and there will be an annual operational cost of £225k per annum.
2. Cost of construction The cost of construction is assumed to increase by 4% annually,
Risk This is below current estimated construction cost indexation which is around 6% but is hoped to be short-term assuming the market reacts quickly to demand.
Cost Implication At 6% construction inflation, there would be a further £2m of capital required to complete the job, and it would take an additional 5 years for the project to pay back.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.