Application GRANTED conditionally, subject to S106 agreement delegated to the Assistant Director for Strategic Planning and Infrastructure to refuse if not signed by target date (30 June 2015) or other date agreed through an extension of time. The following amendments were also made: · For condition 48 to refer to condition 46 within the text to read: ‘with the exception of the superstore as restricted in condition 46, the retail units shall not exceed a total of 350sqm Gross Internal Area (m2). · To include the following wording to informative number (8): ‘with the exception of the supermarket’. Informative number 8 should now read: Informative: Development is not liable for a community infrastructure levy contribution: (8) The Local Planning Authority has assessed that this development, due to its size or nature, is exempt from any liability under the Community Infrastructure Levy Regulations 2010 (as amended) with the exception of the supermarket.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Date Valid 11/08/2014 Ward St Peter & The Waterfront
Site Address LAND AT MILLBAY, MILLBAY ROAD PLYMOUTH Outline mixed use development comprising up to 600 dwellings (Class C3), up to 8,600sqm Class A1, A2, A3, A4, A5 and D1, up to 12,500sqm Proposal office use (Class B1), hotel (Class C1), multi-storey car park for up to 600 cars, with associated engineering works, highway improvements, public realm and landscaping Applicant English Cities Fund Application Type Outline Application Planning Committee: 09 Target Date 30/06/2015 Committee Date April 2015 Decision Category Major - more than 5 Letters of Representation received Case Officer Katherine Graham Grant conditionally subject to S106 agreement delegated to Assistant Director for Strategic Planning and Infrastructure to refuse if not signed by Recommendation target date (30th June 2015) or other date agreed through an extension of time.
Click for documents www.plymouth.gov.uk/planningdocconditions?appno=14/01448/OUT/planningdo cconditions?appno=13/02361/LBC 1. Description of site
The 6.95 hectare application site area is located along part of the waterfront of the Millbay area. This includes along the east side of the inner basin extending up to Millbay Road and Ferry Port Road to the north boundary, Clyde Quay and East Quay to the south of the site. The site area does not include Ballard House and wraps around this building, however does include the buildings along Bounds Place (accessed from Millbay Road) and the pub Sippers. Brunel Way is currently being used as a construction access for Plot A1, which is a previously approved part of the Millbay redevelopment site. This is currently under construction, and nearing completion. The site area along East Quay extends up to West Hoe Road along its East boundary. East Quay is sited at a lower level than West Hoe Road. The residential units along West Hoe Road are a mix of Victorian and flatted developments. The east boundary of this part of the site is characterised by a limestone retaining wall which decreases in height as the site levels increase to the south of the site. East Quay itself is currently characterised by an access road along the waterfront boundary and areas where spoil has been stored. To the south of East Quay is a boundary shared with Millbay Marina Village, which is served by Custom House Lane accessed via a one way system along Great Western Road. This site area does not include Trinity Pier, which currently comprises a corrugated shed structure used for storage by ABP. Clyde Quay mainly consists of an area of hardstanding and bunding with pedestrian access around the perimeter. The south side of Clyde Quay has an area of stone sea bank. Cargo, Cargo 2 and the Plymouth School of Arts are located to the north of the site, and have formed earlier phases of the redevelopment of the area. Further to the north is the Pavilions site and a mix of buildings along Bath and Martin Streets. Ferry Port Road to the north of the application site runs along the north of the Inner Basin and serves the ferry terminal area. The inner basin walls are Grade II listed structures. As part of the development of Plot A1, there has been the construction of an ‘Interim Boulevard’. Whilst this is proposed to be the same location as the final boulevard, the current boulevard has been constructed as a temporary arrangement and finish.
2. Proposal description
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.