Councillor Coker, Cabinet Member for Strategic Planning and Infrastructure introduced the report on the Adoption of Highways Permitting Scheme. Under the new permitting scheme anyone wishing to carry out works on the public highway must initially apply to the City Council as Highway Authority for permission. As such the Highway Authority can refuse, approve and place conditions on each notice. Following a discussion, Cabinet agreed: · For the Council to proceed to the statutory consultation process; · That following the consultation process, any objections or comments are considered by the Cabinet Member Strategic Planning & Infrastructure and delegated authority is provided to the Head of Plymouth Highways to proceed to adopt the Plymouth City Council Permit Scheme.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Date of meeting: 11 November 2019 Title of Report: Plymouth City Council Permit Scheme - Highways Permitting Scheme Lead Member: Cllr Mark Coker, Cabinet Member for Strategic planning and infrastructure Lead Strategic Director: Anthony Payne, Strategic Director for Place Author: Nikki Neale, Network Management – Highways & Traffic Management Contact Email: [email protected] Your Reference: NN301019 Key Decision: No Confidentiality: Part 1
Purpose of Report The Purpose of the report is to outline the benefits of adopting Plymouth City Council Scheme (PCCPS) and obtain agreement to proceed to statutory consultation in order to implement the PCCPS
Currently Statutory Undertakers have a right to occupy, which means Statutory Undertakers put their notices on the system & carry out their works. Under the new permitting scheme anyone wishing to carry out works on the public highway must initially apply to the City Council as Highway Authority for permission. As such the Highway Authority can refuse, approve and place conditions on each notice.
Under the permitting scheme anyone working on the public highway must display a permit board at each site, which will include information regarding the contractors and length and times of the works.
Recommendations and Reasons
It is recommended that Cabinet:
1. Agree for the Council to proceed to the statutory consultation process; Reason : There is a statutory requirement for the Highways Authority to carry out a full consultation of stakeholders. Consultation must be for a minimum of 8 weeks giving sufficient time to adequately respond to consultees as set out in Statutory Guidance for Highways Authority Permit Schemes, Appendix B.
2. Agree that following the consultation process, any objections or comments are considered by the Cabinet Member Strategic Planning & Infrastructure and delegated authority is provided to the Head of Plymouth Highways to proceed to adopt the Plymouth City Council Permit Scheme.
Reason: In order to expedite the process and implement (if appropriate) PCCPS in line with DfT’s desired timeline for adoption by 1st April 2020. The highways permitting scheme replaces the current noticing scheme and is being introduced following a directive by the DfT under the Traffic Management Act 2004.
Cabinet Committee Paper Oct 19 OFFICIAL PLYMOUTH CITY COUNCIL The key objective of the Permit Scheme is to minimise delays to road users and give the City Council greater control of works being undertaken on its road network.
Alternative options considered and rejected The alternative option is to continue under the current noticing scheme. This option is rejected as it contravenes the directive from the DfT to implement the scheme. In addition the existing noticing scheme gives less control for the Highway Authority of the network which would contravene the City Council’s objective to reduce congestion and keep our City moving.
Relevance to the Corporate Plan and/or the Plymouth Plan The proposals within this report support the Council in achieving the vision to be ‘One of Europe’s most vibrant waterfront cities, where an outstanding quality of life can be enjoyed by everyone’. The proposals within this report support the Councils priorities as a Growing City and a Caring Council through maintaining an efficient transport network, supporting economic growth that benefits as many people as possible and ensuring Plymouth is a welcoming city.
Implications for the Medium Term Financial Plan and Resource Implications: The Permit Scheme is aimed at being self-financing. This includes overhead costs, including the funding of the additional staff required to administer the scheme (4 FTE) and covers all associated pensions & benefits, IT costs, management and invoicing for them. The Permit Scheme costs and income must be kept separately from all other income. Regulators must see a clear separation between other costs & charges and an annual statement must be provided to the DfT.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.