Councillor Coker, Cabinet Member for Strategic Planning and Infrastructure introduced the item on Tamar Bridge and Torpoint Ferry 2020/21 Revenue Estimates and Capital Programme. David List, Bridge Manager, was also in attendance. Following a discussion, Cabinet agreed to: · Recommend TBTFJC’s 2020/21 Revenue Estimates and Capital Programme to Council for approval.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Date of meeting: 14 January 2020 Title of Report: Tamar Bridge & Torpoint Ferry 2019/20 Revenue Estimates and Capital Programme Lead Member: Councillor Mark Coker (Cabinet Member Srategic Planning and Infrastructure) Lead Strategic Director: Anthony Payne (Strategic Director for Place) Author: David List, General Manager, Tamar Bridge and Torpoint Ferry Contact Email: [email removed] Your Reference: Key Decision: No Confidentiality: Part I - Official
Purpose of Report The Tamar Bridge and Torpoint Ferry are operated, maintained and improved jointly by Plymouth City Council and Cornwall Council on a ‘user pays’ principle, being funded by toll income using powers derived from the Tamar Bridge Act. The crossings are governed by the Tamar Bridge and Torpoint Ferry Joint Committee (TBTFJC) comprised of five councillors from each of the parent Authorities. The finances of the joint undertaking are effectively ring-fenced by the Tamar Bridge Act, and it is operated as a self-financing business. TBTFJC’s revenue and capital expenditure are funded entirely from Bridge and Ferry toll income and do not affect the budgets of either Plymouth City Council or Cornwall Council. TBTFJC’s Terms of Reference require the Cabinets of the Joint Authorities to recommend TBTFJC’s budgets to their respective Full Councils. This report presents TBTFJC’s 2020/21 Revenue Estimates and Capital Programme report submitted to TBTFJC on 6 December 2019 and draft minutes recording TBTFJC’s endorsement.
Recommendations and Reasons That the Cabinet recommends TBTFJC’s 2020/21 Revenue Estimates and Capital Programme to Council for approval.
Alternative options considered and rejected The TBTF Strategic Plan 2018-2022 and associated Annual Plans are designed to deliver safe, reliable and efficient crossings of the Tamar. The key priorites and delivery actions support the Plan and maintain established service delivery characteristics.The proposed budgets provide the resources to deliver the plan. Asset maintenance has been designed to optimise service delivery and life cost.
Relevance to the Corporate Plan and/or the Plymouth Plan OFFICIAL PLYMOUTH CITY COUNCIL The Tamar Bridge & Torpoint Ferry links are key gateways to the City and provide opportunities for investment, jobs and growth particularly in the wider context of Plymouth as the regional economic centre.
Providing a safe well-maintained road network contributes to the economic well-being of the City, supporting the Council’s Growth priority.
Implications for the Medium Term Financial Plan and Resource Implications: Finance – The proposed revenue budget and capital financing will be funded entirely from the undertaking’s own income. Bridge and Ferry traffic volumes from April 2020 onwards have been assumed to remain unchanged from those estimated for the current year. The longer term financial model accommodates the 33% toll increase enacted in November 2019. The TBTFJC’s borrowing requirements are provided through Cornwall Council. This arrangement together with subsequent servicing costs of the loans being funded from toll revenue means that approval of TBTFJC’s Revenue Estimates and Capital Programme will not affect Plymouth City Council budgets. Human – The proposed budgets support the approved TBTF Strategic Plan 2018-2022 and associated Annual Plans and these will be delivered by the existing organisation using its own staff, contractors and consultants, with support from the parent authorities. IT – The IT implications are restricted to incremental improvement of existing systems as part of the Business Plan and associated projects. Land – No land issues arising from this item.
Carbon Footprint (Environmental) Implications:
Approval of budgets will ensure that planned maintenance and appropriate operational oversight of the crossings will continue, providing reliable journey times minimising the potential for longer diversionary journeys or congestion related pollution.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.