That in order to implement the Council adopted Shoreline Management Plan and Portsea Island Coastal Strategy, the Cabinet agreed:- (1) To commence development of the detailed design using the information gathered from the public consultation exercise. (2) That whilst option D is shown to be the preferred option, the final design for the scheme will also have to take into account costs, local topography and various stakeholder interests. It is likely that the final scheme will be a combination of options C and D and that detailed design should commence on this basis. (3) To delegate authority to the Head of Service for Transport and Environment to submit the final business case to the Environment Agency in consultation with the Cabinet Member for Environment and Community Safety.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
Subject: North Portsea Island Coastal Flood and Erosion Risk Management Scheme - Public consultation findings and progression into detailed design.
Report by: Head of Service, Transport and Environment
Wards affected: Baffins, Copnor and Hilsea.
Key Decision: No
1. Purpose of item To: 1.1 Inform Cabinet of the results of the public consultation for North Portsea Island Flood Defence Schemes. 1.2 Advise that the project is currently on programme to meet the requirements of the Environment Agency's Programme of Acceleration and Growth (PAG) and officers now seek agreement to undertake detailed design based upon the preferred option identified from the public consultation exercise undertaken in February and March 2014. 2. Recommendations In order to implement the Council adopted Shoreline Management Plan and Portsea Island Coastal Strategy, Cabinet agree:- 2.1 To commence development of the detailed design using the information gathered from the public consultation exercise. 2.2 That whilst option D is shown to be the preferred option, the final design for the scheme will also have to take into account costs, local topography and various stakeholder interests. It is likely that the final scheme will be a combination of options C and D and that detailed design should commence on this basis. 2.3 To delegate authority to the Head of Service for Transport and Environment to submit the final business case to the Environment Agency in consultation with the Cabinet Member/Portfolio Holder for Environment and Community Safety.
3. Background The last couple of months have seen a lot of progress on the North Portsea Island Coastal Flood and Erosion Risk Management Scheme as we rapidly converge on the preferred option for each frontage. Initial concept designs were developed to allow full multi-criteria assessment of the shortlisted options including costing of all options for each sub-frontage. The initial costing exercise was accelerated to allow latest cost estimates to be used in this year's MTP submission.
The project team has been engaging with key stakeholders including the Environment Agency, Natural England and PCC Planning Department to capture information from these wider influence groups to advise the option selection process.
Public consultation on the shortlist of options has now closed following a very positive reception from local residents, businesses and visitors to the city. Four drop-in consultation events were held around the North Portsea area with good attendance at all events, particularly the first held in Anchorage Lodge which was attended by over 110 people. In total approximately 400 feedback questionnaires were completed including those collected by the project team out and about around the coastline and those completed online.
Option D (see appendix) was the preferred option by a small margin during the public consultation. However, initial costs, topographic and ground investigations now being undertaken by the Project Team and Consultants show that the most cost effective and environmentally acceptable design for the majority of the flood defence will be a combination of Options C and D.
Surveys have been undertaken to establish the condition and buried extents of existing coastal defence structures in both North Portsea and Southsea. Surveys included trial pits, cover surveys, core samples and sheet pile thickness tests, interpretive reports are currently being compiled.
The project is currently on programme to meet the requirements of the EA's Programme of Acceleration and Growth (PAG).
4. Risks In order to continue to meet the programme requirements of PAG it will be necessary for PCC to progress the Detailed Design for Phase 1 of the project at risk until funding is approved by the Environment Agency.
5. Equalities Impact Assessment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.