Portsmouth City Council
Cabinet, Tuesday 5 March 2024 at 2.00pm

North Portsea Coastal Defence Scheme

Approved Executive 1 paper

Cabinet approved this item on Tuesday 5 March 2024. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

A greed to delegate authority to the Chief Executive in consultation with the S151 Officer to implement and deliver Phase 5 of the North Portsea Coastal Scheme and to enter into any design, construction or support contract arrangements required, subject to the maximum financial commitment from Portsmouth City Council remaining within the existing approved value of £282k, and to allow the Chief Executive to delegate - in full or part - this authority to the Director of Economy, Planning and Transport.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1Cabinet members to delegate authority to the Chief Executive in consultation with the S151 Officer to implement and deliver Phase 5 of the North Portsea Coastal Scheme and to enter into any design, construction or support contract arrangements required, subject to the maximum financial commitment from Portsmouth City Council remaining within the existing approved value of £282k, and to allow the Chief Executive to delegate - in full or part - this authority to the Director of Economy, Planning and Transport. No additional financial commitment is required from Portsmouth City Council.

Background

3.1The North Portsea Coastal Scheme delivers enhanced flood defences to the north of Portsea Island, providing a 1-in-500 year standard of protection. On completion, this will protect: 4,234 residential properties, 490 commercial properties, two arterial road access routes, a primary rail route, two Scheduled Monuments, 89 electrical sub-stations, 17 educational facilities and two MoD properties for the next 100 years.

3.2The decision to undertake the North Portsea Coastal Scheme was taken to Full Council in 2014 and authority was granted to undertake the programme of works, split between five phases. Phases 1-3 are now complete. Phase 4 will be 1 www.portsmouth.gov.uk - Not Classified -

complete in 2024 and Phase 5 is programmed to start construction later this year following successful procurement.

3.3Cabinet notes the progress made on the construction of North Portsea Coastal Scheme and confirms the plans for Phase 5 at Ports Creek should be implemented.

3.4Phase 5 is located at the north of Portsea Island, parallel to the A27. It lies between Ports Creek roundabout in the west (at the eastern end of Phase 3, Tipner Lake), and Anchorage Park in the east (at the western end of Phase 1, Anchorage Park).

3.5For Phase 5, the team has begun a fully OJEU compliant procurement process to appoint a Construction Contractor. A short-listing process will be carried out, with five compliant bidders invited to tender for the contract. The tender process will identify a preferred bidder by the end of July 2024.

3.6Work has been undertaken with quantity surveyors to estimate the construction costs for Phase 5 and has estimated construction costs to be £22.3m. The tender returns will give cost a better certainty.

3.7Across the scheme there is a funding gap of c.£13m and this gap needs to be closed in its entirety prior to Portsmouth City Council awarding the construction contract for Phase 5 and scheme completion. The Project Board and S151 officer have approved that the tender for Phase 5 can run in parallel to seeking additional funding, as the tender returns will give clarity on the scale of the funding gap.

3.8The original Flood Defence Grant-in-Aid (FDGiA) application for this scheme was completed almost 10 years ago. During this time, material costs for the scheme have significantly increased due to inflation, pandemics, conflicts across the globe and Brexit. In addition to this, site access on Phase 5 has been restricted due to alternative access roads being deemed unacceptable for use due to their proximity to residential properties. This restricted access has significantly elongated the programme and cost of the scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North Portsea Coastal Defence SchemeReport 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
SP
Councillor Steve PittChair, present
SH
Councillor Suzy HortonVice-Chair, present
DA
Councillor Dave AshmoreCommittee Member, present
KB
Councillor Kimberly BarrettCommittee Member, present
IH
Councillor Ian HolderCommittee Member, present
LH
Councillor Lee HuntCommittee Member, apologies
HM
Councillor Hugh MasonCommittee Member, present
DS
Councillor Darren SandersCommittee Member, present
GV
Councillor Gerald Vernon-Jackson CBECommittee Member, apologies
MW
Councillor Matthew WinningtonCommittee Member, apologies

On this subject at Portsmouth

Search all
  1. North Portsea Coastal Defence SchemeThis decision
  2. Southsea and North Portsea Island Coastal Schemes updatesNoted
  3. Proposed removal of 3 parking zones (AA Newbolt Road, AC Farmlea Road and JD Portsea North)Decided
  4. Flood Prevention Works - North Portsea and SouthseaNoted
  5. North Portsea Flood Defences - Construction Phase 1Decided
  6. North Portsea Island Coastal Flood and Erosion Risk Management SchemeApproved

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies