Grosvenor House and Warwick Crescent Refurbishment

Approved Committee 1 paper

Housing approved this item on Tuesday 23 September 2014. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

(1) approval was given to tender the works based on an estimated budget of £3.1 million. (2) following a full tender evaluation authority to enter into contract with the preferred bidder be delegated to the Head of Housing and Property Services.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Housing

Purpose of report

1.1To seek permission to go out to tender and appoint a contractor to undertake planned maintenance works to 1-54 Grosvenor House, 2-20 (Evens) Warwick Crescent and 22-44 (Evens) Warwick Crescent.

1.2To seek permission to spend £3.1M to undertake works including external and communal decorations, re-roofing, new passenger lifts and lift shaft. The works are required to ensure the integrity of the buildings, reduce their on-going maintenance and improve the living environment for residents.

1.3If approved, it is anticipated that the works could commence by April 2015.

Recommendations

i. That approval is given to tender the works based on an estimated budget of £3.1M.

ii That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.

Background

3.1All the properties in Grosvenor House and Warwick Crescent are located within the St Thomas ward. Grosvenor House was constructed in 1953 and both the Warwick Crescent blocks were constructed in 1967.

1 www.portsmouth.gov.uk 3.2 Grosvenor House contains 54no. properties whilst the two blocks in Warwick Crescent contain 10no. properties each. The properties are a mix of one, two and three bed flats and maisonettes.

3.3There are no leaseholders present in any of the blocks within this scheme.

3.4A key aspect of the scheme is the work planned at Grosvenor House. The block comprises two wings, one of 5 storeys and the other 7 storeys. Access to the upper floors is via a number of stairwells, two of which have lift shafts. Both of these are undersized and cause problems for residents living in the block, particularly families with pushchairs.

It is proposed to construct a new lift tower to provide two modern passenger lifts to the north of the east wing and also form a new communal entrance to the building at ground floor level.

3.5Grosvenor House also suffers from a number of additional defects to the structure including corrosion of its steel frame to the blocks east wing.

It is proposed to undertake remedial structural repairs. These will include replacing sections of the steel frame to the east wing together with associated concrete repairs.

3.6The roofs to all the blocks are in a poor condition and require new roof coverings and associated repairs.

It is proposed to replace the roof coverings with a new single ply including insulation to the roof. The rainwater will also be redirected to discharge externally and away from the private balconies.

3.7The external and communal areas to all the blocks were last decorated in 2002; a number of areas are in a poor condition, where decorations are not flaking they are faded and require redecoration together with associated repairs.

It is proposed to redecorate all the external and communal areas and undertake associated repairs.

3.8The blocks have various unsecured refuse areas that are not ideally located for collections; the ball court is a location for anti-social behaviour as well as not being extensively used since the Sedgely Close ball courts were constructed; the entrances to the blocks require reconfiguration and there is a demand for scooter storage.

It is proposed to relocate the refuse areas to more accessible locations, remove the ball court, reconfigure the main entrance and create scooter storage area. Options for cycle stores, additional sheds and car parking are also being explored.

2 www.portsmouth.gov.uk 3.9 A fire risk assessment has been undertaken and planned actions have been identified.

It is proposed to install emergency LED lighting to the escape routes of all the blocks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grosvenor House and Warwick Crescent RefurbishmentReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 4 attended
SW
Councillor Steve WemyssCabinet Member, present
DF
Councillor David FullerOpposition spokesperson, apologies, sent representative
DH
Councillor David HorneOpposition spokesperson, apologies
SP
Councillor Stuart PotterOpposition spokesperson, absent

More from Portsmouth Housing

All decisions
MeetingDecisionOutcome
20 Jul 2020 Development of Affordable Housing - Highgrove Lodge Site(1) The Cabinet Member for Housing approved Capital Expenditure of £ 5.1m, to deliver 6 new properties housing 24 adu... Approved Open
9 Mar 2020 Resources for Rough Sleepers in Portsmouth (information report)The contents of the information report were noted. (This is not subject to call-in provisions.) Noted Open
9 Mar 2020 Development of Affordable Homes - Huntsman Close, Havant(1) the Cabinet Member for Housing approved Capital Expenditure of £1.9m, to deliver 10 new affordable housing proper... Approved Open
9 Mar 2020 Council Housing Maintenance and Improvements and Housing IT Business Software 2020/21The Cabinet Member for Housing agreed: (1) That the area programmes and allocation of finance for the funding of the ... Agreed Open
27 Jan 2020 Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies