REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE
ON: 15 JUNE 2015
REPORT OF: THE ENGINEER AND SURVEYOR
SUBJECT: BUILDING WORKS REPORT
Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1502/3 South Chapel – refurbishment Tender stage 205,000 205,000 Nil See separate report to this meeting
1504 Internal redecoration – rolling Assessing 20,000 20,000 Nil Works deferred until 2015/16 programme programme requirements to enable economies of scale. Works are planned to the waiting rooms and the North Chapel foyer. Quotations to be obtained.
1505 Steam cleaning paving – Assessing 6,000 6,000 Nil Works deferred until 2015/16 programme rolling programme requirements to enable economies of scale
1507 Waiting room toilet facilities Works in 8,800 8,800 Nil Tenders obtained and accepted for works progress to North Cloister and Waiting Room toilets.
TCG 02.06.2015 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1508 Water feature Assessing 3,000 3,000 Nil There is a need to re-evaluate the working requirements of the water feature and this will be the subject of a future report of the Joint Committee. Interim measures introduced to facilitate the features operation
1509 Works to Mess Room Works being 2,600 2,600 Nil Works to incorporate safety railing deferred specified until 2015/16 programme and these will be undertaken in the first quarter of the 2015/16 financial year. Quotations being sought.
1510 Crematory/Committal areas Assessing 9,000 9,000 Nil Works deferred until 2015/16 programme requirements to enable economies of scale
1511 Mercury abatement project – Implementation 9,500 9,500 Nil Acoustic grills due for installation early sound attenuation June
1601 Redecoration of North Chapel 10,000 See item1504. Budget now included in and Foyer item 1504
1602 External Redecoration – Assessing 5,000 5,000 Works identified to the external North rolling programme requirements Cloister including remediation of leak
1603 Steam Cleaning Paving – 3,000 3,000 See item1505. Budget now included in rolling programme item 1505
1604 Consultants Fees for Document 10,000 10,000 Consultants Gardiner and Theobald Tendering Building production engaged and are producing contract Consultancy Role documentation
TCG 02.06.2015 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1605 Buildings and External Paving 3,000 Requirement to produce an Asset – Asset Management Plan Management Plan will be incorporated in relevant contract documentation (see item 1605) 1606 Renewal of White Lining Assessing 2,000 2000 requirements
1607 Internal Redecoration – rolling 5,000 See item1504. Budget now included in programme item 1504
1608 External Paving and Walls Assessing 0 1500 1500 Area of defective paving and wall identified requirements for remedial work. Quotation to be obtained
Note
Items previous reported as completed are not shown
TCG 02.06.2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Works ProgrammeReport | 91 KB | DownloadRead as text |
Follow Portchester Crematorium Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Dec 2021 | Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. | Decided | Open |
| 13 Dec 2021 | Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... | Approved | Open |
| 13 Dec 2021 | Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... | Approved | Open |
| 13 Dec 2021 | Manager and Registrar’s ReportRESOLVED that the report be received and noted. | Noted | Open |
| 13 Dec 2021 | Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.