REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE
ON: 14 SEPTEMBER 2015
REPORT OF: THE ENGINEER AND SURVEYOR
SUBJECT: BUILDING WORKS REPORT
Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1502/3 South Chapel – refurbishment Contract award 205,000 205,000 Nil See separate report to this meeting stage 1504 Internal redecoration – rolling Works part 20,000 20,000 Nil Works combined with 2015/16 programme programme completed and to enable economies of scale. Expenditure parts to be to date £4,210. Works completed to the assessed waiting rooms. Works to the North Chapel foyer are imminent.
1505 Steam cleaning paving – Assessing 6,000 6,000 Nil Works deferred until 2015/16 programme rolling programme requirements to enable economies of scale. Areas for treatment to be determined. 1507 Waiting room toilet facilities Completed 8,800 7,700 Minus Works to North Cloister and Waiting Room 1,100 toilets completed and final cost agreed.
TCG 27.08.2015 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1508 Water feature Assessing 3,000 3,000 Nil There is a need to re-evaluate the working requirements of the water feature and this will be the subject of a future report of the Joint Committee. Interim measures introduced to facilitate the features operation including the installation of a fixed access ladder to the underground plant.
1509 Works to Mess Room Works order 2,600 2,600 Nil Works to incorporate safety railing deferred placed until 2015/16 programme and these will be undertaken in the third quarter of the 2015/16 financial year.
1510 Crematory/Committal areas Assessing 9,000 9,000 Nil Works deferred until 2015/16 programme requirements to enable economies of scale. Investigation of new flooring to the crematory to be progressed.
1511 Mercury abatement project – Complete 9,500 14,246 Plus 4,716 Acoustic grills installed and working sound attenuation satisfactorily. Final cost agreed. Increase largely due to unforeseen installation issues.
1601 Redecoration of North Chapel 10,000 See item1504. Budget now included in and Foyer item 1504
1602 External Redecoration – Assessing 5,000 5,000 Works identified to the external North rolling programme requirements Cloister including remediation of leak
TCG 27.08.2015 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1603 Steam Cleaning Paving – 3,000 3,000 See item1505. Budget now included in rolling programme item 1505
1606 Renewal of White Lining Complete 2,000 675 Minus Works complete and final cost agreed. 1,325 1607 Internal Redecoration – rolling 5,000 See item1504. Budget now included in programme item 1504
1608 External Paving and Walls Assessing 0 1500 Plus 1,500 Area of defective paving and wall identified requirements for remedial work. Quotation to be obtained
Note
Items previously reported as completed are not shown
Terry Garvey Engineer and Surveyor
Background List of Documents – Section 100D of the Local Government Act 1972 - None
TCG 27.08.2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Works ProgrammeReport | 135 KB | DownloadRead as text |
Follow Portchester Crematorium Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Dec 2021 | Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. | Decided | Open |
| 13 Dec 2021 | Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... | Approved | Open |
| 13 Dec 2021 | Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... | Approved | Open |
| 13 Dec 2021 | Manager and Registrar’s ReportRESOLVED that the report be received and noted. | Noted | Open |
| 13 Dec 2021 | Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.