The Cabinet Member for Traffic & Transportation: 1. Noted the current financial pressure as a result of the concessionary reimbursement; 2. Gave approval for the award of contracts for supported bus services to operate for 3 years from Sunday 27 March 2016 in accordance with Appendix A. 3. Acknowledged that the bus services outlined in Appendix B contain a list of tendered services and that some of those services will be run commercially (at no cost to the council) and the remainder are the tendered bus routes that are the least value for money. Therefore it is recommended that they are no longer financially supported; with the exception of the 19/19A service which will be retained. 4. The Director of Transport, Environment and Business Support was given delegated authority to remove bus stop infrastructure from redundant routes as appropriate; 5. The Director of Transport, Environment and Business Support was given delegated authority to make any necessary adjustments in consultation with the Cabinet Member for Traffic and Transportation for any variations to the contract award within procurement rules and overall approved budget for the Traffic and Transportation Portfolio. N.B. This decision is not subject to call-in due to the timing implications this would have on securing bus routes in the city, as agreed by the Monitoring Officer and in consultation with the Chair of Scrutiny Management Panel.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report considers the outcome of the re-tendering of the subsidised bus service contracts in Portsmouth to be awarded for three years from Sunday 27 March 2016.
2. Recommendations That the Cabinet Member for Traffic & Transportation
2.1Notes the current financial pressure as a result of the concessionary reimbursement;
2.2Gives approval for the award of contracts for supported bus services to operate for 3 years from Sunday 27 March 2016 in accordance with Appendix A.
2.3Acknowledges that the bus services outlined in Appendix B contain a list of tendered services and that some of those services will be run commercially (at no cost to the council) and the remainder are the tendered bus routes that are the least value for money. Therefore it is recommended that they are no longer financially supported;
2.4The Director of Transport, Environment and Business Support is given delegated authority to remove bus stop infrastructure from redundant routes as appropriate;
2.5The Director of Transport, Environment and Business Support is given delegated authority to make any necessary adjustments in consultation with the Cabinet Member for Traffic and Transportation for any variations to the contract award within procurement rules and overall approved budget for the Traffic and Transportation Portfolio.
1 www.portsmouth.gov.uk 3. Background
3.1Under section 63 of the Transport Act 1985 English local authorities outside London have an implied duty to provide subsidised bus services where there are no commercial services and where they think it appropriate. This is usually arranged by inviting tenders from bus operators. The Act does not set out the level of support required.
3.2The current tendered bus contracts were due to expire on Saturday 4 June 2016. However due to the publication of the councils indicative budget savings on the 18 November 2015 it was necessary to terminate the current contracts to end on the 26 March 2016. Section 10 clause 39.2 of the contract allowed for either party to give notice.
3.3Currently 87% of the bus network in Portsmouth is commercially operated and the Council aims to fulfil its implied duty within the Transport Act 1985 by funding a number of routes within the available budget through the regulated market, ensuring residents can access health facilities, shops and the primary, commercial bus network.
3.4A full EU Procurement Process has been carried out for the provision of supported bus services in Portsmouth. Contracts were tendered for 3 years extendable from the end of year 1 in increments of no less than 1 year with a start date of Sunday 27 March 2016 and an end date of Saturday 30 March 2019.
3.5The tender process was carried out through Intend, the Council’s electronic tendering system and conducted as an open procedure.
3.6Tenders returned by the closing date of the 6 January 2016 were from:
First Hampshire & Dorset Ltd Southdown Motor Company Trading As Stagecoach (South) Ltd
3.7Each compliant tender was evaluated in accordance with a set of pre- determined award criteria. The evaluation criteria are shown in the Tender Evaluation Process Appendix F.
Reasons for recommendations
4.1Like all local authorities, the council is facing further reductions in the revenue support grant. The approval of the council’s indicative budget savings on the 9th December 2015 includes a saving to be made on tendered bus services.
4.2During 2015 / 2016 the council experienced a significant increase in reimbursement payments to bus operators to take them over the allocated budget. This has placed additional financial pressures on the Traffic & Transportation cash limits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.