Approval was given to implement a temporary traffic regulation order for up to 2 years but that only the bus lane closure is implemented immediately with a formal report back in March 2017 (or earlier if needed) by the Director of Transport, Environment & Business Support having reviewed the position.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of this report is to seek approval to implement a temporary traffic regulation order (TTRO) facilitate the redevelopment of the Chaucer House site in Isambard Brunel Road.
Recommendations
2.1That approval is given to implement a temporary traffic regulation order to restrict the use of Isambard Brunel Road (between Greetham Street and Station Street) to buses, hackney carriages, cycles, service vehicles and for access only, and further to enable the temporary closure of the existing bus lane and footway forward to Chaucer House. It should be recognised that, due to the construction period of the works, the TTRO is likely to remain in place for up to 2 years.
Background
3.1Planning permission has been granted for the redevelopment of Chaucer House to provide purpose-built student accommodation. Construction is planned to take place over the next 2 years; the development will be completed and available to students in time for the start of the 2018 academic year. Due to the confined nature of the site the developer seeks to occupy that part of the highway currently used as a footway and bus lane on the south side of Isambard Brunel Road to establish a site compound and facilitate implementation of the development.
3.2A plan is appended to this report indicating the proposed signing, controls and temporary relocation of the bus stops to give effect to the temporary traffic regulation order on the ground. The 4 pay and display parking bays in Dugald Drummond Street will also be suspended as part of this order.
1 www.portsmouth.gov.uk 4. Reasons for recommendations
4.1Whilst a licence to occupy the highway for such purposes can be granted under section 14(1) of the Highways Act, bus priority on this route is essential to the efficient operation of the public transport network within the city and it is not felt that this can be secured by integrating the bus services with the general traffic use of Isambard Brunel Road.
4.2As a consequence it is proposed to limit the use of Isambard Brunel Road (between Greetham Street and Station Street) to buses, cycles, hackney carriages, service vehicles and for access for the duration of the construction period via a temporary traffic regulation order.
4.3Upon completion of the build, reinstatement of the bus lane and a comprehensive improvement to the public realm within the area occupied by the developer is envisaged. All of the costs associated with implementing the temporary traffic regulation order and the subsequent public realm improvement will be met by the developer, secured through the Section 106 planning agreement associated with the permission.
4.4In addition to facilitating the development, this revised operation of Isambard Brunel Road will provide an opportunity to observe the effectiveness of the approach and inform a future decision on the benefits of potentially establishing such an arrangement on a permanent basis, which could enable a wider public realm improvement.
5. Options considered and rejected
5.1Buses currently operate within a dedicated lane, separate from the traffic flow on Isambard Brunel Road. The option of integrating the bus services into the general traffic lanes of Isambard Brunel Road was considered but rejected, as this would compromise the efficient operation of the bus network in the city.
6. Equality Impact Assessment
6.1A preliminary EIA has been completed and found that the recommendations do not have a negative impact on any of the protected characteristics as described in the Equality Act 2010. No parking is being taking away from disabled people and the affected bus stops will remain accessible for all users.
Legal implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.