(1) The 6-metre extension to the 'school keep clear' zig zag restriction as proposed under TRO 24/2017 is not implemented; (2) The existing 'school keep clear' zig zag restriction is remarked on the highway, approximately 4 metres shorter in overall length; (3) The layby is constructed and the adjacent double yellow lines amended, as proposed under TRO 24/2017; (4) The 'school keep clear' restriction is reassessed following completion of the building works within the school (Summer 2018), in terms of the potential closure of the pedestrian entrance nearest Northern Parade.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To consider the response to the public consultation on proposed amendments to stopping and waiting restrictions under traffic regulation order no.24 of 2017, and consider the information received and options available.
Appendix A (pages 5-6): Notice of proposals Appendix B (pages 7-11): Public response to the formal proposals and officer comments
Recommendations
2.1The 6-metre extension to the 'school keep clear' zig zag restriction as proposed under TRO 24/2017 is not implemented;
2.2The existing 'school keep clear' zig zag restriction is remarked on the highway, approximately 4 metres shorter in overall length;
2.3The layby is constructed and the adjacent double yellow lines amended, as proposed under TRO 24/2017;
2.4The 'school keep clear' restriction is reassessed following completion of the building works within the school (Summer 2018), in terms of the potential closure of the pedestrian entrance nearest Northern Parade.
Background
3.1On 5 July 2016, approval was given to carry out camera enforcement outside schools within Portsmouth: http://democracy.portsmouth.gov.uk/documents/s11534/Camera%20Enforcement%20of%20S chool%20Zig%20Zags%20r.pdf
1 www.portsmouth.gov.uk 3.2 The Northern Parade schools site is one of nearly 20 schools in the city identified for automatic camera enforcement of the yellow zig zags markings outside the entrance. Despite various public campaigns and engagement with the schools and parents, compliance with the 'no stopping' restriction remains low in Doyle Avenue.
3.3The current layout of the restriction is unsuitable for the images required to be captured on camera, and therefore a 6-metre extension to the zig zags was proposed. This was chosen as a low-cost option that would require minimal time and highways works to implement.
3.4.1 On-street parking availability is of concern to local residents, which was highlighted during the initial consultation on proposing to extend the 'school keep clear' markings with the loss of 1 daytime parking space. 5.5 metres is allowed for an average parking space, and the proposal would affect 6 metres of the highway.
3.4.2 As a result, the proposal was revised to include an amendment to 20 metres of double yellow lines to accommodate the construction of an adjacent layby using part of the footway between Northern Parade and the service road linking Doyle Avenue / Kipling Road. The footway is over 5 metres in width.
Reasons for recommendations
4.1The consultation showed that the loss of parking that would occur as a result of the proposal was unacceptable to local people. Whilst reconfiguring and remarking the 'school keep clear' restriction is a relatively expensive option and one likely to cause minor damage to the road surface, it represents a balance between local parking needs and the requirements for camera enforcement.
4.2Constructing the layby for the purpose of parking up to 4 vehicles will provide legitimate parking space, take vehicles off the carriageway and deter the current practice of driving over the footway and parking on it adjacent to the private property.
4.3Building works within the school grounds, including 9 additional parking spaces, are due to commence at the end of June 2017 and be completed in Summer 2018. Until that work is complete, closure of the westernmost pedestrian gate will not be possible. As per the recommendation, the 'school keep clear' markings will be reviewed in conjunction with the requirements for pupil entrances at a later date.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.