DECISION: The Cabinet Member: 1) Noted the forecast year-end budget position for the DSG as at 30 September 2018, together with the associated explanations contained within this report. 2) Approved the necessary adjustments to the DSG to reflect: · Early year's budgets and DSG income budget, to reflect the adjustment in grant funding due to pupil number changes, as set out in paragraphs 3.30 and 3.31. · An adjustment to the DSG to reflect the decision by the Secretary of State to approve the transfer of £1.0m to capital to support the development of Redwood Park School. · An adjustment to the DSG to reflect the decision to support The Harbour School in May 2018.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of this report is to inform Cabinet Member of the projected revenue expenditure of the Dedicated Schools Grant (DSG) for the current financial year 2018-19 as at the end of September 2018.
Recommendations
It is recommended that Cabinet Member:
2.1Notes the forecast year-end budget position for the Dedicated Schools Grant as at 30 September 2018, together with the associated explanations contained within this report.
2.2Approves the necessary adjustments to Dedicated Schools Grant to reflect:
Early years budgets and DSG income budget, to reflect the adjustment in grant funding due to pupil number changes, as set out in paragraphs 3.30 and 3.31.
An adjustment to the DSG to reflect the decision by the Secretary of State to approve the transfer of £1.0m to capital to support the development of Redwood Park School.
An adjustment to the DSG to reflect the decision to support The Harbour School in May 2018.
1 www.portsmouth.gov.uk 3. Background
3.1The DSG is a ring-fenced grant for Education and can only be used for the purposes of the Schools Budget as defined in the School and Early Years Finance (England) Regulations.
3.2The original DSG budget for the financial year 2018-19, was approved by the Cabinet Member for Education and endorsed by Schools Forum in January 2018. Further budget adjustments were agreed by the Cabinet Member and endorsed by Schools Forum in July 2018. This report provides the Cabinet Member with the latest forecast estimate of the year- end outturn as at 30 September 2018.
3.3Table 1 below sets out the forecast year-end financial position of the DSG budget as at 30 September 2018.
Table 1 - Dedicated Schools Grant Projected Original Revised Projected over / budget Budget outturn (under) 2018-19 2018-19 2018-19 spend £000's £000's £000's £000's Income DSG Brought forward 2017-18 (413) (4,687) (4,687) 0 DSG and other specific grants (79,592) (70,389) (70,284) 105 Total Income (80,005) (75,076) (74,971) 105
Expenditure Primary ISB 34,230 28,561 28,561 0 Secondary ISB 14,742 11,305 11,305 0 Special school place funding 1,556 1,556 1,607 51 Inclusion Centre Place funding 346 301 301 0 Alternative provision place funding 1,082 1,082 1,082 0 Total Delegated 51,956 42,805 42,855 51
De-delegated and central budgets 1,385 1,538 1,539 1 Early Years 14,204 14,131 14,157 26 High Needs 12,460 12,462 12,852 390 Expenditure approved by the Secretary of State 0 1,000 1,000 0 Approved support to Special Schools 0 868 868 0
Total Expenditure 80,005 72,804 73,271 467
DSG Carried forward 0 2,272 1,700 (573)
2 www.portsmouth.gov.uk Academy conversions and post 16 recoupment
3.4Since the original budget was set in January 2018, there have been a number of academy conversions and Post 16 place adjustments; these have been included within the revised budget along with the one academy conversion (Meon Infant School) during the period from 1 July to 30 September 2018.
Special School places
3.5Special school places are expected to overspend by £50,800. This is mainly due to the additional seven places agreed at Willows Centre for Children for pupils who started school in September 2018.
3.6In addition, the summer term class lists identified an additional pupil placed at Mary Rose Academy, which lead to a further increase in place funding. As the autumn term class lists will not be confirmed by the SEND team until November 2018 it has been assumed that the additional place will be paid for the full financial year. Once the autumn term class lists have been confirmed the forecast may be adjusted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.