Resolved
DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A)
Education noted this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A)
1.1The purpose of this report is to provide an update on the progress of:
Urgent school condition projects Secondary school sufficiency schemes aimed at increasing secondary school place capacity within the city Special school sufficiency schemes aimed at ensuring that schools can take children with more complex SEND.
1.2The quarterly budget monitoring report (also on this agenda) contains information in relation the financial position of the education capital programme.
2.1It is recommended that the Cabinet Member notes the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
3. School modernisation (urgent condition) projects
3.1The urgent condition projects have been identified through Asset Management Plan meetings, condition surveys and recommendations by Education officers concerning the needs of specific pupils.
1 3.2 Three urgent condition projects from the 2017-18 programme have been completed, and have been removed from the projects in progress dashboard.
3.3There is one "live" condition project remaining from the 2017-18 programme, which is being completed in phases to minimise disruption to the school. Final end date is expected to be March 2019.
3.4There were 10 urgent condition projects approved in the 2018-19 programme at the start of the financial year, plus a contingency allowance for urgent emerging works. Four additional urgent condition projects have been reported since the start of the financial year.
3.5Since the last report, two urgent condition projects have been commissioned, funded from the contingency for urgent emerging works:
Copnor Primary - boiler replacement feasibility study. The existing gas fired heating system is failing and has reached the end of its working life. The study will allow the required works to be scoped out. Harbour Tipner - boiler replacement. Following an Annual inspection, one of the two boilers at this school has been found to be beyond economic repair. The other boiler is working but will not be sufficient for the heating season. Therefore, the failing boiler was replaced. Southsea Infants - urgent temporary repairs to windows
3.6Completed condition projects from the 2018-19 programme have been removed from the progress dashboard.
3.7The proposed works at Craneswater Annexe have also been removed, as it has been agreed that, due to the poor condition of the building, the pupils will be moved to a different location for September 2019.
3.8In summary, the urgent condition projects currently in progress are:
2017-2018 modernisation programme - 1 project 2018-2019 modernisation programme - 6 projects
3.9Risks to the progress of the individual projects, as detailed in the Progress dashboard at Appendix A, have been updated. Apart from explanations where there have been completion delays, no new risks to the progress of the projects have emerged since the last report.
4. Secondary sufficiency schemes (phase 2)
4.1The Secondary School Place Strategy 2017-2023 outlined the immediate and medium-term pressures on secondary school places. The Strategy and the feasibility studies informed the recommendations to address future sufficiency issues. The council has previously approved funding for school expansions.
2 4.2 The progress of individual schemes, as detailed in Appendix A, has been updated.
4.3No risks to the progress of the projects have emerged since the last report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: School Modernisation Programme: Live Projects Progress Dashboard: November 2018Appendix | 181 KB | Download |
PDF |
School Modernisation Programme for the 2nd QuarterReport | 139 KB | DownloadRead as text |
Follow Education at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jan 2020 | Education Portfolio Budget Monitoring Report for the Second Quarter 2019/20DECISION: The Cabinet Member for Education noted the Education Portfolio forecast revenue and capital budget position... | Noted | Open |
| 20 Mar 2019 | Willows Centre for Children - end of statutory consultation to close and reopen the Centre under Solent Academies TrustRecommendations The Cabinet Member: a) Considered the response to the statutory consultation carried out on the propo... | Approved | Open |
| 14 Feb 2019 | Dedicated Schools Grant 2018-19 Quarter Three Budget MonitoringDECISION: The Cabinet Member noted the projected year-end budget position for the Dedicated Schools Grant as at 31 De... | Noted | Open |
| 14 Feb 2019 | Education Portfolio Budget Monitoring Report for the Third Quarter 2018/19DECISION: The Cabinet Member noted the Education Portfolio forecast revenue and capital budget positions, as at the e... | Noted | Open |
| 14 Feb 2019 | School Modernisation Programme for the 3rd Quarter 2018 - 19DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects, the secondar... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.