The Cabinet Member for Housing: (1) approved Capital Expenditure of £6.6m, to deliver 13 new properties housing 28 adults with Learning disabilities, comprising of five, 4 bed shared flats and eight, 1 bed flats to be held in the Supported Housing Portfolio within the Housing Revenue Account. (2) delegated authority to the Head of Housing, Neighbourhood and Building Services in consultation with the Head of Finance & S151 Officer to amend the composition and spending profile of the proposed schemes in order to meet planning and design requirements and also to agree the use of either Grant funding or 141 receipts whilst ensuring that the schemes remain financially viable following any necessary changes. (3) delegated the Director of Housing, Neighbourhood and Building to apply for any grant funding to support the scheme. (4) Delegated the Director of Housing, Neighbourhood and Building Services, Director of Regeneration and the Section 151 Officer to agree the value and appropriation of land between the General fund and Housing Revenue Account.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek approval from Cabinet Member for Housing to instruct Housing, Neighbourhood and Building's Design Team to deliver a new development of 13 flats on the redundant Longdean Lodge site.
1.2To seek approval of the financial appraisal delivering 13 new properties, this in turn delivers new homes for 28 adults with learning disabilities within the Supported Housing Portfolio.
1.3The development could potentially deliver annual savings to the general fund of c. £325,000p.a. Due to the provision of a six month building occupation time. It is estimated that this could be realised in full from November 2021.
Recommendations
2.1That the Cabinet Member for Housing approves Capital Expenditure of £6.6m, to deliver 13 new properties housing 28 adults with Learning disabilities, comprising of five, 4 bed shared flats and eight, 1 bed flats to be held in the Supported Housing Portfolio within the Housing Revenue Account.
2.2That the Cabinet Member for Housing delegates authority to the Head of Housing, Neighbourhood and Building Services in consultation with the Head of Finance & S151 Officer to amend the composition and spending profile of the proposed schemes in order to meet planning and design requirements and also to agree the use of either Grant funding or 141 receipts whilst ensuring that the schemes remain financially viable following any necessary changes.
1 www.portsmouth.gov.uk 2.3 That the Cabinet Member for Housing delegates the Director of Housing, Neighbourhood and Building to apply for any grant funding to support the scheme.
2.4That delegation is given to the Director of Housing, Neighbourhood and Building Services, Director of Regeneration and the Section 151 Officer to agree the value and appropriation of land between the General fund and Housing Revenue Account.
Background
3.1Following the completion of the feasibility study permission is sought to progress the scheme to deliver supported Housing for Adults with learning disabilities. This is supported by the Housing and Support Strategy Implementation Group based at the Kestrel centre. The group consists of Housing, Adult Social Care, Solent NHS Trust.
3.2A financial appraisal has been completed showing the scheme will deliver savings to the general fund of £325,000 per annum,. The savings are estimated to deliver at 50% in 2021/22 as the supported housing business partner understandably allows a six month building occupation, as it is not viable to move 28 adults simultaneously, will the full savings being realised in 2022/23. The building also generates a yearly rental yield of £176,000 to the Housing Revenue Account.
3.3The recently approved Housing and Social Care Scrutiny report dated 4 th December 2018 supports the delivery of alternative models of accommodation beyond the initial learning and disability group, working with the Director of Adult Social Care and other directors as appropriate.
3.5The supported housing business partner will seek to secure grant funding from Homes England to support the scheme, it should be noted that this funding cannot be used alongside 141 receipts.
Reasons for recommendations
4.1These homes will provide much needed homes for residents and support Portsmouth City Councils corporate priority 1 " Make Portsmouth a city that works together, enabling communities to thrive and people to live healthy, safe and independent lives".
4.2The schemes will increase the overall number of homes in the HRA and will improve its viability to allow for continued maintenance and tenant services to residents.
4.3The scheme will improve the living environment for residents moving in.
2 www.portsmouth.gov.uk 4.4 The scheme will allow Adult Social Care to decommission two adult learning disability residential care homes and move clients from homes which are sub- standard.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.