Portsmouth City Council
Cabinet, Tuesday 15 September 2020 at 12.00pm

Leamington House and Horatia House Update and Next Steps

Noted Executive 4 papers

Cabinet noted this item on Tuesday 15 September 2020. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Notes the progress since the October 2019 Cabinet report. 2. Notes the output of the soft market testing for the deconstruction of the tower blocks. 3. Notes that the outline financial appraisal for an initial phase consisting of the two footprints is positive with the caveats noted in the financial implications. 4. Approves a change to the Capital Programme for the use of the Housing Revenue Account's (HRA) Major Repairs Reserve (MRR) to fund the deconstruction and site preparation of the two towers up to a value of £10m. 5. Delegates authority to the Director of Regeneration in consultation with the Director of Housing, Neighbourhood and Building Services and the Section 151 Officer to tender and enter into contract with the preferred bidder for the deconstruction work following full evaluation of the tender. That the Council approves 1. That the full deconstruction and redevelopment scheme for the two tower blocks is added to the capital programme in the sum of £120m. 2. That the scheme is funded by a suitable mix of HRA and General Fund Prudential Borrowing as determined by the S.151 Officer. 3. That the scheme can only proceed, including through its procurement gateways, if a satisfactory financial appraisal which demonstrates viability is approved by the Section151 Officer. 4. That, given the early stage of design, delegated authority be given to the Section151 Officer to vary the overall scheme cost and borrow as required but subject to the Section 151 Officer being satisfied that the associated financial appraisal demonstrates continued viability and acceptable risk and that the gross cost of the scheme does not exceed £145m. 5. In the event that the scheme varies significantly from the design parameters (described in section 5) and/or the gross cost exceeds £145m, even if viability can still be demonstrated, the scheme will not proceed without further approval from the City Council.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To provide Cabinet with a progress update including

1.1.1. Deconstruction Options Appraisal & Soft Market Testing 1.1.2. Design Team Appointment 1.1.3. Telecommunication re-siting 1.1.4. Peregrine Falcons

1.2Note the continued commitment to engage the wider community to explore the 'wider area improvements' and the incorporation into the design brief of all the feedback from the community engagement work undertaken in 2019 including the seven key themes that emerged from all the feedback;

1. Build appropriate homes 2. Make better use of green space and space for children 3. No more student accommodation 4. Consider wider area improvements 5. Better parking options 6. No tower blocks 7. Re-provide the social housing lost when the tower blocks go

1.3To report back the initial financial viability assessment of a development on the 'foot prints' of the two tower blocks based on an overall development of 440 units and including 272 social housing units to be held within the Housing Revenue Account 1.4. To seek permission from Cabinet to tender and appoint a contractor to undertake the deconstruction of the two tower blocks

1.5To seek permission from Full Council to proceed with the wider development (described in paragraph 1.3 above) at an estimated total cost of £120m subject to:

1.5..1. the development remaining viable through the design stages and remaining within certain other financial parameters 1.5..2. the development remaining sustainably within the administrations agreed principles (section 5)

Recommendations

2.1That the Cabinet:

2.1.1 Notes the progress since the October 2019 Cabinet report.

2.1.2 Notes the output of the soft market testing for the deconstruction of the tower blocks.

2.1.3 Notes that the outline financial appraisal for an initial phase consisting of the two footprints is positive with the caveats noted in the financial implications.

2.1.4 Approves a change to the Capital Programme for the use of the Housing Revenue Account's (HRA) Major Repairs Reserve (MRR) to fund the deconstruction and site preparation of the two towers up to a value of £10m.

2.1.5 Delegates authority to the Director of Regeneration in consultation with the Director of Housing, Neighbourhood and Building Services and the Section 151 Officer to tender and enter into contract with the preferred bidder for the deconstruction work following full evaluation of the tender.

2.2That City Council approves the following:

2.2.1 That the full deconstruction and redevelopment scheme for the two tower blocks is added to the capital programme in the sum of £120m.

2.2.2 That the scheme is funded by a suitable mix of HRA and General Fund Prudential Borrowing as determined by the S.151 Officer.

2.2.3 That the scheme can only proceed, including through its procurement gateways, if a satisfactory financial appraisal which demonstrates viability is approved by the Section151 Officer. 2.2.4 That, given the early stage of design, delegated authority be given to the Section151 Officer to vary the overall scheme cost and borrow as required but subject to the Section 151 Officer being satisfied that the associated financial appraisal demonstrates continued viability and acceptable risk and that the gross cost of the scheme does not exceed £145m.

2.2.5 In the event that the scheme varies significantly from the design parameters (described in section 5) and/or the gross cost exceeds £145m, even if viability can still be demonstrated, the scheme will not proceed without further approval from the City Council.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HL Development Design Team Synopsis (appendix 2)Appendix 594 KB Download
PDF
HL Integrated Impact Assessment (IIA) (appendix 5)Appendix 137 KB Download
PDF
HL community engagement report (appendix 3)Appendix 11 MB Download
PDF
Leamington House and Horatia House Update and Next StepsReport 792 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
GV
Councillor Gerald Vernon-Jackson CBEChair, present
SP
Councillor Steve PittVice-Chair, apologies
DA
Councillor Dave AshmoreCommittee Member, present
SH
Councillor Suzy HortonCommittee Member, present
LH
Councillor Lee HuntCommittee Member, present
DS
Councillor Darren SandersCommittee Member, present
LS
Councillor Lynne StaggCommittee Member, present
MW
Councillor Matthew WinningtonCommittee Member, present
TW
Councillor Tom WoodCommittee Member, absent
HM
Councillor Hugh MasonCommittee Member, present

On this subject at Portsmouth

Search all
  1. Leamington House and Horatia House Update and Next StepsThis decision
  2. Leamington House and Horatia House - Update and Engagement Next StepsNoted
  3. Leamington House and Horatia House Next StepsNoted
  4. Update on Leamington House and Horatia House rehousing of households (information item)Noted

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies