The Cabinet: (1) Noted the results of the feasibility work to strengthen, clad and install sprinklers into Leamington House and Horatia House; (2) Agreed that it is financially unviable to undertake the works to strengthen, clad and install sprinklers into Leamington House and Horatia House, and as a result; (3) Agreed that on completion of the permanent rehousing of all households from Leamington House and Horatia House, the two blocks will be removed from charge, decommissioned and secured; (4) Gave delegated approval to the Director of Housing, Neighbourhood and Building Services authority to incur costs to carry out decommissioning works of Leamington House and Horatia House and secure both blocks; (5) Agreed that there is an opportunity for the sites to be redeveloped to create affordable/social housing and regeneration in this area of the City and requests the Regeneration Directorate working with the Housing Directorate to provide a report to Cabinet with an options appraisal for the demolition of Leamington House and Horatia House and redevelopment of the sites in consultation with the local and wider Somers town community and stakeholders; (6) Noted the loss of social housing units to the Housing Revenue Account and requests that the options appraisal for the development of the Leamington House and Horatia House sites includes the re-provision of a minimum of 272 social housing units to be held in the HRA.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To report to Cabinet the results of the feasibility work to strengthen, clad and install sprinklers into Leamington House and Horatia House and the options for the next steps.
Recommendations
2.1That the Cabinet:
2.1.1 Notes the results of the feasibility work to strengthen, clad and install sprinklers into Leamington House and Horatia House 2.1.2 Agrees that it is financially unviable to undertake the works to strengthen, clad and install sprinklers into Leamington House and Horatia House, and as a result 2.1.3 Agrees that on completion of the permanent rehousing of all households from Leamington House and Horatia House, the two blocks will be removed from charge, decommissioned and secured. 2.1.4 Gives delegated approval to the Director of Housing, Neighbourhood and Building Services authority to incur costs to carry out decommissioning works of Leamington House and Horatia House and secure both blocks. 2.1.5 Agrees that there is an opportunity for the sites to be redeveloped to create affordable/social housing and regeneration in this area of the City and requests the Regeneration Directorate working with the Housing Directorate to provide a report to Cabinet with an options appraisal for the demolition of Leamington House and Horatia House and redevelopment of the sites in consultation with the local and wider Somers town community and stakeholders. 2.1.6 Notes the loss social housing units to the Housing Revenue Account and requests that the options appraisal for the development of the Leamington House and Horatia House sites includes the re-provision of a minimum of 272 social housing units to be held in the HRA. 3. Background
3.1Leamington House and Horatia House were constructed in 1965. All the blocks are Bison Large Panel System (LPS) construction, each block is 18 storeys high and consisting of a total of 136 No. flats. There are 8 No. flats per storey, there are no flats on the ground floor and there are two escape stairwells per block.
3.2Leamington House and Horatia House each consist on every floor of of 2 No. one bedroom flats, 2. No two bedroom flats and 4 No. three bedroom flats.
3.3Throughout the evaluation process the City Council has worked in partnership with key agencies for example Hampshire Fire and Rescue service and engaged approrpriatle qualified independent experts including the British Research Establishment.
Cladding Removal
3.4The only Council owned high rise blocks of flats identified with Aluminium Composite Material (ACM) cladding were Horatia House and Leamington House, following the Grenfell tragedy work commenced on 23 June 2017 to remove all cladding to both blocks. The cladding at Horatia House was completely removed by 1 December 2017 whilst the cladding at Leamington House was completely removed by 19 January 2018.
Feasibility to replace the Cladding
3.5The original intention had been to remove the ACM cladding and replace with an appropriate alternative. On 7 August 2017 ECD Architects were appointed to undertake a feasibility study to investigate options for recladding the blocks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.