Approved the revised Local Plan timetable set out in this report for the (LDS) and the Minerals and Waste Development Scheme. 2. Granted delegated authority to Assistant Director Planning & Economic Growth to make minor amendments to the LDS and Minerals and Waste Development Scheme and Development Plan Document timetables as necessary. 3. Noted the progression of other Portsmouth Development Plan Documents and Supporting Planning Policy documents.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of this report is to detail and seek approval for the revisions to the Local Plan timetable set out in the Local Development Scheme (LDS).
Recommendations
2.1To approve the revised Local Plan timetable set out in this report for the Local Development Scheme (LDS) and the Minerals and Waste Development Scheme.
2.2To grant delegated authority to Assistant Director Planning & Economic Growth to make minor amendments to the LDS and Minerals and Waste Development Scheme and Development Plan Document timetables as necessary.
2.3Note the progression of other Portsmouth Development Plan Documents and Supporting Planning Policy documents.
Background
3.1The Local Planning Authority is preparing a new Portsmouth Local Plan to guide the future development of the city. The new Local Plan will set out details on the level of development that will take place and where it will be located, and identify the infrastructure needed to support this growth. It will contain planning policies that will inform and influence the quality of development delivered in the city by guiding decision-making on planning applications. Critical to the development of the Local Plan is sound supporting evidence to assess the need, impact, viability and deliverability of development.
3.2A Local Development Scheme (LDS) is required under Section 15 of the Planning and Compulsory Purchase Act 2004 (as amended). The LDS must 1 www.portsmouth.gov.uk specify the development plan documents, the subject matter of those development plan documents and the geographical areas they cover and the timetable for the production and adoption of them. For Portsmouth City Council this is primarily the new Portsmouth Local Plan.
3.3Local planning authorities have an obligation to keep the LDS up to date and publish it on their website. Portsmouth's LDS was last updated on 8th March 2022 following approval by the Cabinet.
The Revised Portsmouth Local Plan Timetable
3.4Additional time has been necessary to continue discussions with the Members Cross Party Working Group. Progress of the options has been made however due to the Local Elections in May the group was unable to meet for some time which has meant the March timetable has slipped. A further final meeting of the Cross-Party Working Group is scheduled to occur prior to the Cabinet meeting to consider this report meaning that 9 meetings will have been undertaken since 30th November 2021. Following those meetings it has been agreed that a spatial strategy will be pursued that maximise delivery within the emerging strategic sites identified across the city and that the Tipner West site will be progressed with a delivery of 1,250 homes in addition to substantial employment floorspace.
3.5The outcome of the decisions on development at Tipner and the other options will require a full reassessment of the potential housing supply and related policies. The work programme for the Plan has a number of dependencies that will depend an agreed spatial strategy for the quantity and location of new development in the city; background evidence and assessment work (i.e. transport, infrastructure provision, sustainably appraisal and habitat regulations assessment) and engagement with other local authorities on unmet housing need cannot be progressed or finalised ahead of this.
3.6A full review of the Local Plan timetable has therefore been undertaken; the estimated target date for the Council's Regulation 19 version of the Plan has been moved to Spring 2023, moving likely Submission of the Plan to late summer 2023. The timescales for the latter stages of the plan preparation (post 'Submission') will be outside of the Council's direct control.
Table 1. Updated LDS Timetable for the new Local Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.