N oted and approve the Q4 2021/22 Quarterly Update report as submitted to Cabinet by the Company at Appendix One. 2. Noted and approve the financial accounts for the Company for the period ending 31 March 2022, at Appendix Two. 3. Noted the progress reported on the existing project at Brewery House, Hambrook Street. 4. Noted the appointment of the two Non-Executive Directors to RHL and the formal board meeting that was held for both RHL and RGL on 12th April 2022. 5. Noted that the engagement and collaboration of the Company with the Council on the Horatio and Leamington private Build-to-Rent units in Somerstown is progressing in-line with the approved development pipeline in the five-year business plan for the Company. 6. Noted the Director of Regeneration is no longer a board member of the Ravelin Group and has been replaced by the Acting Director for Property and Development in line with the decision made by the Board on 12th April 2022. The change allows the Director of Regeneration to act unencumbered in supporting the Shareholder in any required commercial decision making.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The report is provided in line with the shareholders requests for further detailed reporting and the advice on good governance in local authority wholly owned companies.
1.2The report will provide updates as follows:
1.2.1. To update the Cabinet on the City Council's ownership of shares in Ravelin Group Limited ("RGL") and subsidiary companies Ravelin Housing Limited ("RHL") and Ravelin Property Limited ("RPL").
1.2.2. To provide key highlights from RHL on individual projects updating on activities undertaken during the fourth quarter (December 2021 to March 2022).
1.2.3. To report on the companies unaudited Micro Entity Financial Statements, for the accounting period ending 31st March 2022.
Recommendations
That the Cabinet, as shareholder is: -
2.1To note and approve the Q4 2021/22 Quarterly Update report as submitted to Cabinet by the Company at Appendix One.
2.2To note and approve the financial accounts for the Company for the period ending 31 March 2022, at Appendix Two.
2.3To note the progress reported on the existing project at Brewery House, Hambrook Street. 1 www.portsmouth.gov.uk 2.4. Note the appointment of the two Non-Executive Directors to RHL and the formal board meeting that was held for both RHL and RGL on 12th April 2022.
2.5Note that the engagement and collaboration of the Company with the Council on the Horatio and Leamington private Build-to-Rent units in Somerstown is progressing in-line with the approved development pipeline in the five-year business plan for the Company.
2.6Note the Director of Regeneration is no longer a board member of the Ravelin Group and has been replaced by the Acting Director for Property and Development in line with the decision made by the Board on 12th April 2022. The change allows the Director of Regeneration to act unencumbered in supporting the Shareholder in any required commercial decision making.
Background
3.1On 28 February 2019, Cabinet approved the business case for the establishment of RHL to act as a property development company for the Council.
3.2On 15 December 2021, Cabinet Sub-Committee approved the Ravelin Housing Limited five-year Business Plan and Investment and Development Plan.
3.3On 12 April 2022, the City Council entered into a Shareholders' agreement with (a) Ravelin Group Limited and (b) Ravelin Housing Limited which sets out that the group of companies has been established for commercial and profit-making purposes, to carry out the business in accordance with the agreements and that the parties had entered into the agreements to regulate the manner in which the companies carry out their business.
3.4The Shareholders Agreements set out details for the reporting requirements of the Company which includes the need to submit to the Council a quarterly project update report on activities and a report on financial accounts.
4. Reasons for recommendations 4.1. The reports in Appendix One and Two are required of the Companies under their respective Articles of Association (i.e., their own constitution) and the Shareholder Agreements with the Council.
4.2The reports have been scrutinised by the Director of Regeneration, the Director of Finance and S151 Officer on behalf of the Council. The Officers are comfortable that the companies are operating within the parameters of the Business Plan approved by the Cabinet in December 2021 and have no concerns to raise in relation to their performance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.