Decision The Cabinet Member for Transport: · Considered the objection to the making permanent of the experimental one way (except cycles) working in Edgeware Road and Bonchurch Road; · Approved that the provisions of the Portsmouth City Council (Bonchurch Road and Edgeware Road)( One-way except Cycles) (No.8) Experimental Traffic Regulation Order 2023 be made permanent.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To consider the objection to making permanent the experimental one-way (except cyclists) streets on Bonchurch Road and Edgeware Road.
Recommendations
It is recommended that the Cabinet Member for Transport:
2.1Considers the objection to the making permanent of the experimental one way (except cycles) working in Edgeware Road and Bonchurch Road; and
2.2Approves that the provisions of the Portsmouth City Council (Bonchurch Road and Edgeware Road) (One Way except Cycles) (No.8) Experimental Traffic Regulation Order 2023 be made permanent.
Background
3.1Historically, complaints have been received from residents of Bonchurch Road and Edgeware Road about traffic using the roads as "short cuts", and conflict between oncoming vehicles, where the running carriageway is too narrow to allow cars to pass each other, and there are few places to pull in and allow oncoming traffic to pass. A review of turning count data concluded that the use of both roads as a "short cut" to avoid the signalised junction is a perceived issue and was not indicated by the data collected.
1 www.portsmouth.gov.uk 3.2 A scheme to implement a one-way system at this location was taken to the then Cabinet Member for Traffic and Transportation on the 12 March 2009 1. However, following local opposition at the time, the scheme was not progressed.
3.3A petition objecting to the implementation of the one-way traffic system in Edgeware Road was received on 30 January 2009. This contained 64 signatures from residents within Edgeware Road.
3.4As well as the petition, nine letters of named representation were received during the statutory consultation period. As a result of this resident feedback, the recommendation that the scheme be deferred was accepted.
3.5Additional requests from residents of Bonchurch and Edgeware roads for a one- way system were received in early 2022.
3.6In response to these requests, a feasibility assessment was undertaken by Portsmouth City Council considering road speeds, traffic counts, turning counts and historical road traffic collision data. The work concluded several feasible options at this location to address issues identified through data collection during the feasibility and stakeholder engagement activities.
3.7Resident engagement activity then took place in October 2022 to confirm the final option for implementation and is outlined in section 5 of this report.
3.8The preferred option following resident engagement was for the installation of a one-way system with contraflow cycling on Bonchurch Road and Edgeware Road. As identified in the original scheme proposal, there was conflicting desire from residents pertaining to the direction of traffic on their road.
3.9Additional traffic count data and turning count data was collected to assess the best option for the direction of traffic. Owing to the conflicting views of the residents of Bonchurch Road and Edgeware Road, a one-way (except cycles) was progressed on an experimental basis, to assess the suitability of the direction of one-way traffic. The experimental Traffic Regulation Order (ETRO) came into force on 28 April 2023.
3.10Following the formal ETRO consultation period, which came to an end on the 28 October 2023, one objection has been received. This objection is as follows:
"There has been one way scheme on my road and two adjacent. My road is closest to the traffic light between Rodney Rd and eastern Rd, this means it takes me at the minimum 7 minutes for someone to let me into the que and this is very unsafe because of oncoming traffic so close to the bend from the eastern Rd going around the corner which is a blind bend.
1 T&T Report - results of statutory consultation for one-way
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Residents Parking Zones Future ProgrammeDECISION The Cabinet Member for Transport: 1. Approved progressing the RPZs Future Programme for proposed new zones a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.